Azizi Developments new projects and handover dates

Azizi Developments new projects in Dubai: 25 projects, 15 under construction, 2 partly handed over, 4 off-plan, 4 handed over. Each row gives the latest Dubai Land Department (DLD) construction figure and the handover date, with a link to prices, payment plan and the handover date history.

Newest Azizi projects: launched or early construction

15 Azizi projects are off-plan or less than 15% built at the last DLD inspection.

All Azizi projects in Dubai: construction progress and handover dates

ProjectAreaStatusConstruction (DLD)Handover date
Azizi Abraham
Azizi Abraham handover date
Downtown Jebel Aliunder construction2% complete (DLD inspection, 24 Mar 2026)4 Aug 2027 (DLD registered completion date); Property Finder shows 30 Jun 2027
Azizi Amir
Azizi Amir handover date
Al Furjanunder construction2.35% complete (DLD inspection, 18 Mar 2026)Registered completion date 17 Jun 2027 (DLD); Q4 2027 on most portals
Azizi Arian
Azizi Arian handover date
Downtown Jebel Aliunder construction2% complete (DLD inspection, 24 Mar 2026)16 Jan 2028 (DLD registered completion date); portals list Q4 2027 to Q1 2028
Azizi David
Azizi David handover date
Al Jaddafunder construction2% complete (DLD inspection, 24 Mar 2026)Registered completion date 30 Sep 2028 (DLD); Q4 2027 on portals and broker listings
Azizi Emerald
Azizi Emerald handover date
Dubai Healthcare City (DHCC), Umm Hurair 2under construction3% complete (DLD inspection, 24 Mar 2026)DLD registered completion 13 Feb 2028; Q1 2028 (developer, via Continental Club); June 2027 at launch
Azizi Grand
Azizi Grand handover date
Dubai Sports Cityunder constructionAzizi 94% (Sep 2026); DLD 82.06% (24 Jun 2026)Not agreed: Q4 2024 to Q3 2026 depending on source; DLD registered date 2 Feb 2025
Azizi Leily
Azizi Leily handover date
Al Jaddafunder construction2% complete (DLD inspection, 24 Mar 2026)Registered completion date 30 Sep 2028 (DLD); Q4 2027 on Propsearch
Azizi Lina
Azizi Lina handover date
Downtown Jebel Aliunder construction2% complete (DLD inspection, 18 Mar 2026)30 Sep 2028 (DLD registered completion date); some broker pages still show Q4 2027
Azizi Neila
Azizi Neila handover date
Al Furjanunder construction38.53% complete (DLD inspection, 5 Oct 2026)30 Jul 2027 (DLD registered completion date); Property Finder shows July 2027
Azizi Raffi
Azizi Raffi handover date
Al Furjanunder construction2% complete (DLD inspection, 25 Mar 2026)Registered completion date 15 Jan 2028 (DLD); Q1 2028 on Property Finder; Sep 2026 at launch
Azizi Ruby
Azizi Ruby handover date
Jumeirah Village Circle (JVC)under construction3% complete (DLD inspection, 25 Mar 2026)DLD registered completion date 23 Jan 2028; Q4 2026 marketed at launch
Azizi Venice
Azizi Venice handover date
Dubai Southunder constructionVenice 3 at 76.04% (DLD inspection, 15 Jun 2026)No firm date; Azizi says handovers run through 2026 into 2027 (Sep 2026)
Azizi Wares
Azizi Wares handover date
Downtown Jebel Aliunder construction2% complete (DLD inspection, 18 Mar 2026)Registered completion date 4 Mar 2028; portals list Q4 2027 to Q1 2028
Azizi Zain
Azizi Zain handover date
Al Furjanunder construction66.21% complete (DLD inspection, 30 Jun 2026)DLD registered completion date 11 Oct 2027; Q4 2027 on portals
Burj Azizi
Burj Azizi handover date
Sheikh Zayed Road (Trade Centre First)under construction7.47% complete (DLD inspection, 3 Sep 2026)2029 per Azizi; DLD registered completion date 30 Aug 2030
Azizi Beach Oasis
Azizi Beach Oasis handover date
Dubai Studio Citypartly handed overPhase 2 53.22% complete (DLD inspection, 7 Sep 2026)Phase 1 handed over, Jan 2026. Phase 2: DLD registered completion date 30 Apr 2026, passed
Azizi Riviera
Azizi Riviera handover date
Meydan One, Mohammed Bin Rashid Citypartly handed overPhase 4 at 74% (Azizi, 31 Mar 2026); Rêve 79% (Azizi, 16 Jul 2026)Phases 1 to 3 complete; Rêve due Q4 2026; newer towers registered for Mar and May 2027
Azizi Gabriel
Azizi Gabriel handover date
Downtown Jebel Alioff-plan0% (DLD inspection, 17 Nov 2025; no later inspection published)Registered completion date 4 Jul 2028 (DLD); Q4 2028 on Bayut and Propsearch
Azizi Milan
Azizi Milan handover date
City of Arabia, Dubailandoff-plan0% at last DLD inspections (Apr to Sep 2025)DLD registered completion dates from Mar 2027 (Milan 51) to Sep 2028 (Milan Heights)
Azizi Noura
Azizi Noura handover date
Downtown Jebel Alioff-plan0% complete (DLD inspection, 13 Nov 2025); no later inspection publishedRegistered completion date 4 Jul 2028 (DLD); December 2027 on Property Finder
Azizi Rose
Azizi Rose handover date
Downtown Jebel Alioff-plan0% complete (DLD inspection, 16 Feb 2026)DLD registered completion date 4 Jul 2028; portals show Q4 2028
Azizi Central
Azizi Central handover date
Al Furjan, Jebel Ali Firsthanded overCompleted (DLD 100%, inspection 8 Jun 2026)Handover began July 2026 (Azizi); first promised for Q4 2025
Azizi Mirage 1
Azizi Mirage 1 handover date
Dubai Studio Cityhanded overCompleted, 100% (DLD inspection, 14 Oct 2025)Handed over from 24 Dec 2025 (Azizi, as Beach Oasis I); DLD registered completion date 30 Apr 2025
Azizi Pearl
Azizi Pearl handover date
Al Furjanhanded overCompleted, 100% (DLD inspection, 5 Jun 2024)Handed over 5 June 2024
Azizi Vista
Azizi Vista handover date
Dubai Studio Cityhanded overCompleted (DLD, 30 Sep 2025)Completed 30 Sep 2025 (DLD); handover from 22 Oct 2025 (Azizi)