When do Binghatti projects hand over?
Short answer
Six Binghatti projects are handed over: Ghost, Phoenix, Phantom, Azure, Avenue and Crest. The other 20, including Elite, Skyflame and Circle, are still under construction. Several have passed their published dates: Elite and Hills were listed for Q2 2026 and Starlight and Ruby for Q1 2026. The latest published date is Q3 2028, for Tilal Binghatti. On the Dubai Land Department register, Binghatti Haven was 76% complete and Binghatti Elite 53% complete on 24 September 2026. Binghatti's own dates and the figures on property portals do not always match, so check the date for your specific building in the sale and purchase agreement.
Projects handed over
6 of 26
Ghost, Phoenix, Phantom, Azure, Avenue, Crest
Most advanced, still under construction
76%
Binghatti Haven, DLD register, 24 Sep 2026
Furthest published date
Q3 2028
Tilal Binghatti, Propsearch
Binghatti Skyflame completion
31 Dec 2027
Binghatti, accessed 28 Sep 2026
Six projects are already handed over
Binghatti Ghost, Binghatti Phoenix, Binghatti Phantom, Binghatti Azure, Binghatti Avenue and Binghatti Crest are complete. Binghatti Avenue and Binghatti Crest finished years ago, in April 2022 and October 2023. Binghatti Ghost, Phantom and Azure finished more recently, between December 2024 and Q1 2026. The other 20 projects below are still under construction.
Handover date by project
Each row gives the date Binghatti or a portal has published, and the current status. Where a percentage complete is shown, it comes from the Dubai Land Department’s project register.
| Project | Area | Published date | Status |
|---|---|---|---|
| Binghatti Elite | Dubai Production City | Q2 2026 | Under construction, 53% (DLD, 24 Sep 2026) |
| Binghatti Hills | Dubai Science Park | Q2 2026 | Under construction, % not published |
| Binghatti Ghost | Al Jaddaf | Q1 2026 (Binghatti); DLD register shows it handed over on 24 Sep 2026 | Handed over |
| Binghatti Cullinan | Al Jaddaf | Not published by Binghatti; Propsearch estimate Q4 2027 | Under construction, 70% (Propsearch, 6 Aug 2026) |
| Binghatti Pinnacle | Al Jaddaf | Q4 2025, now passed | Under construction, % not published (Propsearch, 24 Sep 2026) |
| Binghatti Starlight | Al Jaddaf | Q1 2026 | Under construction, 63% (DLD, 24 Sep 2026) |
| Binghatti Phoenix | Jumeirah Village Circle | Not published; Binghatti lists it as ready to move | Handed over |
| Binghatti Moonlight | Al Jaddaf | Q2 2026 (Binghatti); estimate June 2026 (Propsearch) | Under construction, % not published |
| Binghatti Ruby | Jumeirah Village Circle | Q1 2026 (Binghatti); estimate Q4 2027 (Propsearch, 15 Aug 2026) | Under construction, 46% (DLD, 24 Sep 2026) |
| Binghatti Skyrise | Business Bay | Q4 2026 | Under construction, % not published |
| Binghatti Phantom | Jumeirah Village Circle | Completed Oct 2025 (Bayut) or Nov 2025 (Propsearch) | Handed over |
| Binghatti Vintage | Majan | Not published by Binghatti; estimate March 2027 (Propsearch, 19 Aug 2026) | Under construction, % not published |
| Binghatti Haven | Dubai Sports City | Q1 2026 | Under construction, 76% (DLD, 24 Sep 2026) |
| Binghatti Azure | Jumeirah Village Circle | Completed Dec 2024 (Propsearch) | Handed over |
| Binghatti Royale | Jumeirah Village Circle | Q4 2025 (Binghatti); no later confirmation found | Under construction, % not published |
| Binghatti Avenue | Al Jaddaf | Completed April 2022 (Propsearch) | Handed over, sold out |
| Binghatti Hillside | Dubai Science Park | Q2 2026 (Binghatti); estimate June 2026 (Propsearch) | Under construction, % not published |
| Tilal Binghatti | Dubailand, Academic City | Not published by Binghatti; Propsearch estimate Q3 2028 | Under construction, % not published |
| Binghatti Crest | Jumeirah Village Circle | Completed Oct 2023 (Propsearch) | Handed over |
| Binghatti Sky Terraces | Motor City | Not published by Binghatti; Property Finder lists April 2028 | Under construction, early stage |
| Binghatti Hillcrest | Arjan | Not published by Binghatti; Propsearch estimate Dec 2026 | Under construction, % not published |
| Binghatti Ivory | Al Jaddaf | Q4 2025, now passed | Under construction, % not published (Propsearch, 6 May 2026) |
| Binghatti Twilight | Al Jaddaf | Q1 2026 (Binghatti); estimate March 2026 (Propsearch) | Under construction, % not published |
| Binghatti Circle | Jumeirah Village Circle | Q2 2027 | Under construction, % not published |
| Binghatti Grove | Jumeirah Village Circle | Q1 2026 (Binghatti); estimate March 2026 (Propsearch) | Under construction, % not published |
| Binghatti Skyflame | Majan | 31 Dec 2027 | Under construction, % not published |
Where the developer and portals disagree
Three projects show a clear mismatch in what has been published.
- Binghatti Ghost. Binghatti’s own project page still gives Q1 2026 as the completion quarter. The DLD register, checked on 24 September 2026, lists the building as handed over, and Bayut’s building guide also expects handovers from Q1 2026. Buyers should treat the DLD register as the current position.
- Binghatti Ruby. Binghatti’s site gives Q1 2026. The DLD register put it at 46% complete on 24 September 2026, which does not fit a Q1 2026 handover. Propsearch, checked on 15 August 2026, gave an estimate of Q4 2027.
- Binghatti Phantom. Bayut’s building guide gives October 2025 as the completion month. Propsearch, checked on 16 September 2026, gives November 2025. Both agree the project is complete, only the exact month differs.
Binghatti Pinnacle and Binghatti Ivory both had a Q4 2025 target on Binghatti’s own site. Both dates have passed, and neither project has a revised date published or a confirmed handover reported elsewhere as of the dates in the table.
A separate note on names: Binghatti has three differently named towers in Dubai Science Park, Binghatti Hills, Binghatti Hillside and Binghatti Hillviews. The DLD register lists progress under Hillviews (33% complete, 24 Sep 2026), which is not necessarily the same building as Hills or Hillside. Check the exact building name against your sale and purchase agreement.
What to check before booking
- The exact building name and phase, not just the project name. Several Binghatti developments share a location with similarly named towers.
- The DLD project status for that exact building, using the Dubai Land Department’s project status enquiry service.
- The date in your sale and purchase agreement (SPA) and any grace period, which is extra time the contract allows after that date.
- How recently a portal’s figure was checked. Several of the dates above are estimates that have already passed without an update, so check the date given for each source before relying on it.
- Written confirmation from Binghatti for any project where the published date has passed, such as Binghatti Pinnacle or Binghatti Ivory.
Questions buyers also ask
Does Binghatti give one handover date for all its projects?
No. Each project has its own date. Some are already handed over, such as Binghatti Ghost and Binghatti Phantom, while Tilal Binghatti is not due until Q3 2028, per Propsearch.
Why do Binghatti's site and the DLD register sometimes disagree?
Binghatti's own project pages give a target quarter set at launch, which is not always updated once a project is handed over or delayed. The DLD register reflects inspection based progress and status at the date it was checked.
Where can I check a Binghatti project's construction progress myself?
The DLD's real estate project status enquiry service publishes a percentage complete for each registered building. Sites such as Propsearch mirror this register.
How many Binghatti homes were sold for 2026 handover?
Binghatti said nearly 90% of units scheduled for handover in 2026 were already sold, in a press release dated 25 March 2026.
What should I do if a Binghatti project's published date has already passed?
Check the DLD project status service for that building directly and ask Binghatti for the current date in writing. Binghatti Pinnacle and Binghatti Ivory both had a Q4 2025 target that has passed without a revised date published.