When is the Binghatti Starlight handover date?
Short answer
Binghatti Starlight's handover date is Q1 2026 on Binghatti's own project page, and the DLD registered completion date is 31 March 2026. Both have passed. The last DLD inspection, on 14 May 2026, recorded the tower at 63.11% complete, and the register still showed that figure on 29 September 2026. Binghatti has not published a revised date, and the 511 unit tower has not been handed over.
Registered completion date (DLD)
31 Mar 2026
Passed. DLD register via Continental Club, 29 Sep 2026
Latest construction progress
63.11%
DLD inspection, 14 May 2026
Developer's stated date
Q1 2026
Binghatti project page, accessed 28 Sep 2026
Progress at previous inspection
28.94%
DLD inspection, 6 Nov 2025
Binghatti Starlight handover date: the latest position
Binghatti Starlight was due to be completed in Q1 2026. Binghatti’s own project page still shows that quarter, and the Dubai Land Department (DLD) register holds a registered completion date of 31 March 2026. Both have passed, and the tower has not been handed over. More on prices, sizes and the building: Binghatti Starlight.
The last DLD site inspection, on 14 May 2026, recorded the tower at 63.11% complete. The register still showed 63.11% and the 31 March 2026 date on 29 September 2026 (Continental Club), and Mitchell’s listed the project as under construction on 23 September 2026. Binghatti has not published a revised date.
Binghatti Starlight handover date by building
Binghatti Starlight is a single 25 storey tower in Al Jaddaf, registered in the DLD’s Dubai Healthcare City Phase 2 area as project 3195. It has 511 units: 294 studios, 155 one bedroom and 61 two bedroom apartments, plus retail (Mitchell’s).
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Binghatti Starlight | 63.11% (14 May 2026) | 31 Mar 2026 | Binghatti: Q1 2026. Binayah: Mar 2026. Projects Scout: 30 Jun 2026 |
Portals disagree. Binayah repeats the Q1 2026 date, while Projects Scout lists 30 June 2026 as the expected completion. Both dates have passed.
How the Binghatti Starlight handover date has changed
| Date | Event | Source |
|---|---|---|
| Mar 2024 | Sales launch | Propsearch |
| 30 Jul 2024 | Registered construction start | DLD via Mitchell’s |
| 6 Nov 2025 | DLD inspection: 28.94% | DLD via Continental Club |
| 31 Mar 2026 | Registered completion date passes | DLD register |
| 14 May 2026 | DLD inspection: 63.11%, up 34.17 points since November | DLD via Continental Club |
| 29 Sep 2026 | Register unchanged: 63.11%, date still 31 Mar 2026 | Continental Club |
Neither Binghatti nor the register has moved the date, so both now show a date in the past. Between November 2025 and May 2026 the tower gained about 5.5 points a month. Binghatti delivered about 1,700 units in H1 2026, naming Binghatti Apex, Ghost and Ivory (Binghatti, 27 July 2026), and Starlight was not among them.
What the Binghatti Starlight handover date means for payments
Binghatti’s plan is 20% at booking, 50% during construction and 30% at completion. The 30% falls due when the tower is handed over, so it follows the real completion date, not the 31 March 2026 date on the register.
| Unit | Price (transactions, Sep 2026) | 30% due at completion |
|---|---|---|
| Studio | From AED 775,000 | From AED 232,500 |
| 1 bedroom | From AED 960,000 | From AED 288,000 |
| 2 bedroom | From AED 2,000,000 | From AED 600,000 |
Prices are from Propsearch, based on September 2026 transactions.
What to check before relying on the Binghatti Starlight date
- The grace period in your SPA. Q1 2026 has passed, so the grace period in the agreement decides when the delay becomes contractual.
- Whether the DLD has filed an inspection after 14 May 2026. At 63.11%, a newer reading on the DLD project status service would show whether the tower is nearing completion.
- A revised date in writing from Binghatti, since its page still shows Q1 2026.
- For resale buyers, the balance still owed to Binghatti, including the 30% due at completion.
Questions buyers also ask
What is the Binghatti Starlight handover date?
Binghatti lists Q1 2026, and the DLD registered completion date is 31 March 2026. Both have passed. Binghatti had not published a revised date by 1 October 2026.
Is Binghatti Starlight finished?
No. The last DLD inspection, on 14 May 2026, recorded 63.11% complete, and the project was still listed as under construction on the register on 23 September 2026 (Mitchell's).
Has the Binghatti Starlight handover been delayed?
Yes, against its published dates. Q1 2026 and the 31 March 2026 registered date have both passed. Portals disagree on the current date: Binayah still shows March 2026 and Projects Scout shows 30 June 2026, which has also passed.
How much is due at handover at Binghatti Starlight?
30% of the price is due on completion under Binghatti's 20/50/30 plan. On a studio at AED 775,000 that is AED 232,500.