Developers

H&H Development new projects and handover dates

H&H Development new projects in Dubai: 4 projects, 4 under construction. Each row gives the latest Dubai Land Department (DLD) construction figure and the handover date, with a link to prices, payment plan and the handover date history.

Newest H&H projects: launched or early construction

3 H&H projects are off-plan or less than 15% built at the last DLD inspection.

All H&H projects in Dubai: construction progress and handover dates

ProjectAreaStatusConstruction (DLD)Handover date
Eden Hills
Eden Hills handover date
Mohammed Bin Rashid City (next to Dubai Hills Estate)under construction3.54% complete (DLD inspection, 22 Sep 2026)DLD registered completion date 25 Dec 2026; developer and portal dates range from Q4 2026 to Q1 2028
Eden House Dubai Hills
Eden House Dubai Hills handover date
Dubai Hills Estate, Mohammed Bin Rashid Cityunder construction0.07% complete (DLD inspection, 13 Aug 2026)DLD registered completion 1 Dec 2027; Property Finder October 2027; June 2027 given in 2024
Eden House The Park
Eden House The Park handover date
Al Wasl, Jumeirah (Dubai Water Canal)under construction63.56% complete (DLD inspection, 30 Jul 2026)DLD registered completion 25 Feb 2027; developer Q1 2027
Peninsula Dubai Residences
Peninsula Dubai Residences handover date
Jumeirah 2 (Dubai Peninsula)under constructionTower 1 5.6% (DLD, 10 Sep 2026); Tower 2 6% (DLD, 13 Aug 2026)DLD registered completion date 8 Jan 2029 for both towers; developer Q1 2029

Payments around handover