Sobha Realty new projects and handover dates

Sobha Realty new projects in Dubai: 14 projects, 10 under construction, 2 off-plan, 2 handed over. Each row gives the latest Dubai Land Department (DLD) construction figure and the handover date, with a link to prices, payment plan and the handover date history.

Newest Sobha projects: launched or early construction

4 Sobha projects are off-plan or less than 15% built at the last DLD inspection.

All Sobha projects in Dubai: construction progress and handover dates

ProjectAreaStatusConstruction (DLD)Handover date
350 Riverside Crescent
350 Riverside Crescent handover date
Sobha Hartland 2, Bukadraunder construction57.85% complete (DLD inspection, 18 Aug 2026)December 2027 (Sobha); 1 Mar 2027 (Property Finder); no DLD registered completion date filed
Sobha Elwood
Sobha Elwood handover date
Dubailand (Dubai Al Ain Road)under construction14.35% complete (DLD inspection, 20 Jul 2026)Q2 2028 (30 Jun 2028, DLD registered completion date)
Sobha Hartland 2
Sobha Hartland 2 handover date
Bukadraunder constructionRiverside Crescent towers 50.23% to 60.37% (DLD, Jul to Sep 2026); villa Series 1 89.59% (Sobha, Q1 2026)Phased: villas 31 Dec 2026 (Property Finder; named in Sobha's 2026 handover plan); Riverside Crescent Jun to Dec 2027 (Sobha); Skyscape Dec 2028 (Sobha) and registered for 31 Dec 2029; Skyvue registered for 31 Mar 2030
Sobha One
Sobha One handover date
Ras Al Khorunder construction86.21% complete (DLD inspection, 24 Aug 2026)Q4 2026 (DLD registered completion date); Jun 2026 estimate, passed (Propsearch)
Sobha Orbis
Sobha Orbis handover date
Motor Cityunder construction18.20% complete (DLD inspection, 13 Aug 2026)Q4 2028 (31 Dec 2028)
Sobha Reserve
Sobha Reserve handover date
Wadi Al Safa 2under construction75.01% complete (DLD inspection, 5 Aug 2026)Listed Q2 2026, now passed; some portals give Q4 2026
Sobha SeaHaven
Sobha SeaHaven handover date
Dubai Harbourunder constructionTowers 37% to 40.2% complete (DLD, Aug to Sep 2026)Tower A 30 Apr 2028; Towers B and C 31 Oct 2028 (DLD registered completion dates)
Sobha Siniya Island
Sobha Siniya Island handover date
Umm Al Quwain (not Dubai)under constructionVillas Phase 2 started 6 Apr 2026 (Property Finder)Dec 2027 to Jun 2030 by cluster (Sobha); villas Dec 2027 and Jun 2028 (Sobha), Dec 2028 (Property Finder)
Sobha Solis
Sobha Solis handover date
Motor Cityunder construction13.22% complete (DLD inspection, 5 May 2026)Dec 2027 (Sobha) or 31 Dec 2028 (DLD registered completion date)
Sobha Verde
Sobha Verde handover date
Jumeirah Lake Towersunder construction85% complete (DLD inspection, 24 Aug 2026)Q4 2026 (named in Sobha's plan); DLD registered completion date 30 Jun 2027
Sobha Central
Sobha Central handover date
Sheikh Zayed Roadoff-planPhase I 7.08% complete (DLD inspection, 29 Sep 2026)Dec 2029 for four towers, Dec 2030 for The Mirage and The Pinnacle (Sobha); DLD registered 30 Jun 2030 and 31 Dec 2031
Sobha Sanctuary
Sobha Sanctuary handover date
Al Ain Road, Dubailandoff-planNot started, 0% (DLD, 15 Jul 2026; register as at 4 Oct 2026)First villas from Q3 2029 (Sobha); DLD registered completion 31 Aug 2030 (villas), 30 Dec 2030 (The Woods)
Creek Vistas Grande
Creek Vistas Grande handover date
Sobha Hartland, Mohammed Bin Rashid Cityhanded over100% complete (DLD inspection, 27 Dec 2024)Handed over. Sobha announced handover on 30 Jan 2025; DLD registered completion date 31 Jul 2025
Sobha Waves Opulence
Sobha Waves Opulence handover date
Sobha Hartland, Mohammed Bin Rashid Cityhanded over100% complete (DLD inspection, 4 Aug 2026; status finished 6 Aug 2026)Handed over. DLD completion recorded 6 Aug 2026; Sobha announced handover on 1 Sep 2026