Prescott Development new projects and handover dates

Prescott Development new projects in Dubai: 3 projects, 2 under construction, 1 off-plan. Each row gives the latest Dubai Land Department (DLD) construction figure and the handover date, with a link to prices, payment plan and the handover date history.

Newest Prescott projects: launched or early construction

1 Prescott projects are off-plan or less than 15% built at the last DLD inspection.

All Prescott projects in Dubai: construction progress and handover dates

ProjectAreaStatusConstruction (DLD)Handover date
Legado by Prescott
Legado by Prescott handover date
Jumeirah Village Circle (JVC)under construction23.31% complete (DLD inspection, 30 Sep 2026)Q4 2027 (Prescott); registered completion date 31 August 2027 (DLD)
Verano by Prescott
Verano by Prescott handover date
Dubai Studio Cityunder construction41.07% complete (DLD inspection, 29 Sep 2026)Prescott states Q3 2027; DLD registered completion date 31 Dec 2026
The Caden by Prescott
The Caden by Prescott handover date
Meydan Horizonoff-plan0.47% complete (DLD inspection, 2 Jun 2026)Q3 2028 (Prescott); DLD registered completion date 15 May 2028

Payments around handover

Handover dates for other developers