When is The Caden by Prescott handover date?
Short answer
The Caden by Prescott has a registered completion date of 15 May 2028 with DLD, and Prescott gives Q3 2028. The last published DLD inspection, on 2 June 2026, recorded 0.47% complete. Nearly the whole tower remains to be built, so the next inspections will show whether either date is realistic.
Registered completion date (DLD)
15 May 2028
DLD project register via Continental Club
Latest construction progress
0.47%
DLD inspection, 2 Jun 2026
Developer's stated date
Q3 2028
Prescott, accessed 11 Oct 2026
Date change since launch
None
Q3 2028 since launch on 18 Nov 2025
The Caden by Prescott handover date: the latest position
The Caden by Prescott has a registered completion date of 15 May 2028 in the DLD project register, and Prescott says completion is scheduled for Q3 2028. Prices, sizes and the payment plan are on The Caden by Prescott page.
The last published DLD inspection, on 2 June 2026, recorded 0.47% complete. Construction is registered as starting on 15 November 2025, so the full tower, two basements, three podium levels and 20 residential floors, has to be built in about two years from mid 2026.
Sales have run ahead of the site. The DLD register shows 107 deals since launch, almost all from the developer, including five 1 bedrooms sold for AED 1,802,000 to AED 1,953,000 on 22 and 29 September 2026 (Continental Club, register updated 4 October 2026). Each of those buyers is relying on the same completion date.
The Caden by Prescott handover date by building
The Caden is one tower, registered as DLD project 4215 with 229 units.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| The Caden by Prescott | 0.47%, 2 Jun 2026 | 15 May 2028 | Q3 2028 (Prescott; Propsearch; ezre.ae) |
For the other towers in the community, see the Meydan Horizon completion date table.
How The Caden by Prescott handover date has changed
| Date | What happened | Source |
|---|---|---|
| 11 Nov 2025 | First DLD inspection | DLD register |
| 15 Nov 2025 | Registered construction start | DLD register |
| 18 Nov 2025 | Launch at Prescott’s Dubai Hills experience centre; Q3 2028 completion | Prescott |
| 2 Jun 2026 | Inspection records 0.47% | DLD register |
| 11 Oct 2026 | Prescott’s site still shows Q3 2028 | Prescott |
Neither date has changed since launch. The difference is in the detail: the registered date of 15 May 2028 sits in Q2, while Prescott’s marketing uses Q3 2028, up to four and a half months later. No inspection figure after 2 June 2026 had been published by 11 October 2026.
What The Caden by Prescott handover date means for payments
On the launch plan, 40% of the price is due on handover, after 20% on booking and 40% during construction (Propsearch). Some buyers are on other plans with 60% at handover, or 20% at handover and 40% after it (ezre.ae). For a 1 bedroom at the DLD median of AED 1,889,560, a 40% handover payment is about AED 756,000. A later completion moves that payment back.
What to check before relying on The Caden by Prescott date
- The completion date and grace period in the SPA, since 15 May 2028 and Q3 2028 are both in use.
- Whether construction instalments are linked to progress or to dates. With progress below 1% in June 2026, this decides how much is paid before the frame rises.
- The next DLD inspection figure, the first that should show foundation and basement work.
Questions buyers also ask
When will The Caden by Prescott be completed?
The DLD register holds a registered completion date of 15 May 2028. Prescott says completion is scheduled for Q3 2028.
Has The Caden by Prescott handover date been delayed?
No change has been published. Prescott has given Q3 2028 since the launch on 18 November 2025, and the registered date is 15 May 2028.
Has construction started at The Caden by Prescott?
Yes, on paper. The DLD register records a start on 15 November 2025, and the project was 0.47% complete at the inspection on 2 June 2026.
Is The Caden by Prescott finished?
No. It was 0.47% complete at the last published DLD inspection, on 2 June 2026.