Tiger Properties new projects and handover dates
Tiger Properties new projects in Dubai: 10 projects, 8 under construction, 2 handed over. Each row gives the latest Dubai Land Department (DLD) construction figure and the handover date, with a link to prices, payment plan and the handover date history.
Track record: none of the 6 Tiger Properties projects we track from DLD data had passed its registered completion date unfinished (DLD data as at 22 October 2026). How Tiger Properties compares with other Dubai developers. See also the register change log and the handover calendar.
Newest Tiger Properties projects: launched or early construction
6 Tiger Properties projects are off-plan or less than 15% built at the last DLD inspection.
- Ananda Residences: handover Registered completion date 31 May 2028; Tiger says Q2 2028; 3.2% built in October 2026, so the date is very likely to move
- Auresta Tower: handover Registered completion date 31 December 2028; developer date Q4 2028; 4.44% built in October 2026
- Guzel Towers: handover Registered completion date 25 December 2027; Tiger says Q4 2027; 7.3% built in October 2026, so the date is very likely to move
- Jade Tower: handover Registered completion date 31 March 2027; 11% built in October 2026, so the date is very likely to move
- Sky Gate Tower: handover Registered completion date 29 February 2028; Tiger announced Q1 2028 at launch
- Tiger Sky Tower: handover Developer date Q4 2028 (December 2028 on Property Finder); no completion date in the DLD register; 10.24% built in September 2026
All Tiger Properties projects in Dubai: construction progress and handover dates
| Project | Area | Status | Construction (DLD) | Handover date |
|---|---|---|---|---|
| Ananda Residences Ananda Residences handover date | Motor City | under construction | 3.2% complete (DLD inspection, 7 Oct 2026) | Registered completion date 31 May 2028; Tiger says Q2 2028; 3.2% built in October 2026, so the date is very likely to move |
| Auresta Tower Auresta Tower handover date | Jumeirah Village Circle (JVC) | under construction | 4.44% complete (DLD inspection, 8 Oct 2026) | Registered completion date 31 December 2028; developer date Q4 2028; 4.44% built in October 2026 |
| Guzel Towers Guzel Towers handover date | Jumeirah Village Triangle (JVT) | under construction | 7.3% complete (DLD inspection, 7 Oct 2026) | Registered completion date 25 December 2027; Tiger says Q4 2027; 7.3% built in October 2026, so the date is very likely to move |
| Jade Tower Jade Tower handover date | Majan, Dubailand | under construction | 11% complete (DLD inspection, 2 Oct 2026) | Registered completion date 31 March 2027; 11% built in October 2026, so the date is very likely to move |
| Red Square Tower Red Square Tower handover date | Jumeirah Village Triangle (JVT) | under construction | 26.71% complete (DLD inspection, 27 Mar 2026) | No registered completion date on the DLD register; Property Finder lists Q2 2027 and some agents Q4 2026; 26.71% built in March 2026, so both dates look unlikely |
| Sky Gate Tower Sky Gate Tower handover date | Jumeirah Village Triangle (JVT) | under construction | 4.68% complete (DLD inspection, 7 Oct 2026) | Registered completion date 29 February 2028; Tiger announced Q1 2028 at launch |
| Tiger Sky Tower Tiger Sky Tower handover date | Business Bay | under construction | 10.24% complete (DLD inspection, 10 Sep 2026) | Developer date Q4 2028 (December 2028 on Property Finder); no completion date in the DLD register; 10.24% built in September 2026 |
| Volga Tower Volga Tower handover date | Jumeirah Village Triangle (JVT) | under construction | 51.1% complete (DLD inspection, 5 Oct 2026) | No registered completion date on the DLD register; Property Finder lists December 2026 (Q4 2026); 51.1% built in October 2026, so a 2026 handover is not realistic |
| Altai Tower Altai Tower handover date | Jumeirah Village Triangle (JVT) | handed over | 100% complete (DLD inspection, 19 Oct 2026); DLD status Ready from 19 Oct 2026 | Handover began in the week of 21 September 2026 (Tiger Group); construction complete per the DLD register (100%, status Ready, 19 Oct 2026); registered completion date was 31 January 2026; Tiger targeted early July 2026 |
| Cloud Tower Cloud Tower handover date | Jumeirah Village Triangle (JVT) | handed over | Completed (DLD 100%, inspection 20 Oct 2025) | Handed over 29 October 2025 (Tiger Properties); registered completion date 28 February 2025 |