Tiger Properties new projects and handover dates

Tiger Properties new projects in Dubai: 10 projects, 8 under construction, 2 handed over. Each row gives the latest Dubai Land Department (DLD) construction figure and the handover date, with a link to prices, payment plan and the handover date history.

How this page was made: figures from the Tiger Properties project pages on this site, which use the DLD project register and the developer's own pages, latest update 26 October 2026. Text drafted with AI assistance from those sources. Every figure matched the fact records at the build on 12 November 2026. Not yet reviewed line by line by a person. How facts are checked

Track record: none of the 6 Tiger Properties projects we track from DLD data had passed its registered completion date unfinished (DLD data as at 22 October 2026). How Tiger Properties compares with other Dubai developers. See also the register change log and the handover calendar.

Newest Tiger Properties projects: launched or early construction

6 Tiger Properties projects are off-plan or less than 15% built at the last DLD inspection.

All Tiger Properties projects in Dubai: construction progress and handover dates

ProjectAreaStatusConstruction (DLD)Handover date
Ananda Residences
Ananda Residences handover date
Motor Cityunder construction3.2% complete (DLD inspection, 7 Oct 2026)Registered completion date 31 May 2028; Tiger says Q2 2028; 3.2% built in October 2026, so the date is very likely to move
Auresta Tower
Auresta Tower handover date
Jumeirah Village Circle (JVC)under construction4.44% complete (DLD inspection, 8 Oct 2026)Registered completion date 31 December 2028; developer date Q4 2028; 4.44% built in October 2026
Guzel Towers
Guzel Towers handover date
Jumeirah Village Triangle (JVT)under construction7.3% complete (DLD inspection, 7 Oct 2026)Registered completion date 25 December 2027; Tiger says Q4 2027; 7.3% built in October 2026, so the date is very likely to move
Jade Tower
Jade Tower handover date
Majan, Dubailandunder construction11% complete (DLD inspection, 2 Oct 2026)Registered completion date 31 March 2027; 11% built in October 2026, so the date is very likely to move
Red Square Tower
Red Square Tower handover date
Jumeirah Village Triangle (JVT)under construction26.71% complete (DLD inspection, 27 Mar 2026)No registered completion date on the DLD register; Property Finder lists Q2 2027 and some agents Q4 2026; 26.71% built in March 2026, so both dates look unlikely
Sky Gate Tower
Sky Gate Tower handover date
Jumeirah Village Triangle (JVT)under construction4.68% complete (DLD inspection, 7 Oct 2026)Registered completion date 29 February 2028; Tiger announced Q1 2028 at launch
Tiger Sky Tower
Tiger Sky Tower handover date
Business Bayunder construction10.24% complete (DLD inspection, 10 Sep 2026)Developer date Q4 2028 (December 2028 on Property Finder); no completion date in the DLD register; 10.24% built in September 2026
Volga Tower
Volga Tower handover date
Jumeirah Village Triangle (JVT)under construction51.1% complete (DLD inspection, 5 Oct 2026)No registered completion date on the DLD register; Property Finder lists December 2026 (Q4 2026); 51.1% built in October 2026, so a 2026 handover is not realistic
Altai Tower
Altai Tower handover date
Jumeirah Village Triangle (JVT)handed over100% complete (DLD inspection, 19 Oct 2026); DLD status Ready from 19 Oct 2026Handover began in the week of 21 September 2026 (Tiger Group); construction complete per the DLD register (100%, status Ready, 19 Oct 2026); registered completion date was 31 January 2026; Tiger targeted early July 2026
Cloud Tower
Cloud Tower handover date
Jumeirah Village Triangle (JVT)handed overCompleted (DLD 100%, inspection 20 Oct 2025)Handed over 29 October 2025 (Tiger Properties); registered completion date 28 February 2025