When do Sobha Orbis, Solis, Reserve and other Sobha projects hand over?
Short answer
Sobha Crest Grande is complete. It received its Building Completion Certificate in March 2026 and handovers are commencing. Sobha Hartland 2, Verde and Reserve are listed for 2026, though the DLD register gives Verde a completion date of 30 June 2027 and holds no registered date for Reserve. Sobha lists Sobha Solis for December 2027, while its DLD registered completion date is 31 December 2028. Sobha Orbis is registered for 31 December 2028 and Elwood for 30 June 2028. Sobha SeaHaven is registered for 30 April 2028 for Tower A and 31 October 2028 for Towers B and C. Sobha lists the first Sobha Central towers for December 2029 and the first Sobha Sanctuary villas from Q3 2029, while the DLD register gives both 2030 or later.
Already complete
3
Crest Grande (BCC 25 Mar 2026), Creek Vistas Grande, Waves Opulence
Named for 2026
3
Hartland 2, Verde, Reserve. Verde registered for 30 Jun 2027 (DLD)
Due 2027 to 2028
4
Solis, Orbis, Elwood, SeaHaven
Due 2029 and later
2
Central's first towers, Sanctuary
Every Sobha project, side by side
| Project | Location | Launch | Published handover / completion date | Latest construction status |
|---|---|---|---|---|
| Crest Grande | Sobha Hartland | Not published | Complete. BCC issued 25 Mar 2026, handovers commencing | Building Completion Certificate issued |
| Creek Vistas Grande | Sobha Hartland | 2022 | Handed over Jan 2025, ahead of its Jul 2025 date; DLD registered completion 31 Jul 2025 | 100% (DLD inspection, 27 Dec 2024) |
| Sobha Waves Opulence | Sobha Hartland | First traced Nov 2022 | Handover announced 1 Sep 2026; DLD completion 6 Aug 2026, against Q3 2025 at launch | 100% (DLD inspection, 4 Aug 2026) |
| 350 Riverside Crescent | Sobha Hartland 2, Bukadra | Booking from May 2024 | Dec 2027 (Sobha); 1 Mar 2027 (Property Finder); no DLD registered completion date filed | 57.85% built (DLD inspection, 18 Aug 2026) |
| Sobha Reserve | Wadi Al Safa 2 | Sales launched May 2023 | Q2 2026 (Propsearch, Property Finder), now passed; Q4 2026 (Data Habibi, Binayah); no DLD registered completion date filed; named in Sobha’s 2026 handover plan | 75.01% built (DLD inspection, 5 Aug 2026) |
| Sobha Hartland 2 | Bukadra | Booking from Nov 2021 | Q4 2026, 31 Dec 2026; named in Sobha’s 2026 handover plan | Series 1: 89.59%. Series 2: 44.60%. Series 3: 21.06%, Q1 2026 |
| Verde by Sobha | Jumeirah Lake Towers | Launched Apr 2023 | Q4 2026 at launch; named in Sobha’s 2026 handover plan; DLD registered completion 30 Jun 2027 | 85% built (DLD inspection, 24 Aug 2026) |
| Sobha Solis | Motor City | Booking from Oct 2024, launched Jan 2025 | Dec 2027 (Sobha, Propsearch); DLD registered completion 31 Dec 2028, matching Property Finder | 17.92% built (DLD inspection, 22 Oct 2026) |
| Sobha Orbis | Motor City | Booking from Jun 2024 | Q4 2028; DLD registered completion 31 Dec 2028 | 18.20% built (DLD inspection, 13 Aug 2026) |
| Sobha SeaHaven | Dubai Harbour | Tower A sales from 2022; Tower B pre-launched Jul 2023 | Apr 2028 (Property Finder); DLD registered completion 30 Apr 2028 (Tower A) and 31 Oct 2028 (Towers B and C) | Towers B and C 40.2% built (DLD inspection, 18 Sep 2026); Tower A 37% (DLD inspection, 6 Aug 2026) |
| Sobha Elwood | Dubailand, near Jebel Ali | Launched Jul 2025 | Q2 2028; DLD registered completion 30 Jun 2028 | 14.35% built (DLD inspection, 20 Jul 2026) |
| Sobha Central | Sheikh Zayed Road | Launched May 2025 | Dec 2029 for The Horizon, The Serene and The Tranquil, Dec 2030 for The Mirage and The Pinnacle (Sobha); DLD registered completion 30 Jun 2030 (Phase I and II) and 31 Dec 2031 (project 4328) | Phase I 7.08% and Phase II 6.42% built (DLD inspection, 29 Sep 2026) |
| Sobha Sanctuary | Dubai-Al Ain Road | Launched Jan 2026 | First villas from Q3 2029 (Sobha, Khaleej Times) or from 2030 (Zawya); DLD registered completion 31 Aug 2030 (villa clusters) and 30 Dec 2030 (The Woods) | Not started, 0% (DLD inspection, 15 Jul 2026) |
Already complete
Sobha Crest Grande, three residential towers at Sobha Hartland, received its Building Completion Certificate on 25 March 2026. Sobha said customer handovers were “scheduled to commence shortly” within the timeline it committed to under RERA, the Real Estate Regulatory Agency. No specific handover date for individual units was given in the announcement.
Two more Sobha Hartland towers are complete. Creek Vistas Grande reached 100% at the DLD inspection of 27 December 2024 and Sobha announced its handover on 30 January 2025, ahead of the July 2025 date given at launch. Sobha Waves Opulence reached 100% on 4 August 2026, and Sobha announced its handover on 1 September 2026, about 11 months after its Q3 2025 launch date (Data Habibi).
Due in 2026
Three projects are listed for 2026. All three were named, alongside Sobha One, in Sobha’s July 2026 statement that it planned a record 6,819 handovers across five Dubai projects in 2026.
Sobha Hartland 2 is listed for Q4 2026. Construction progress varies within the project itself. Its Series 1 buildings were 89.59% complete in Q1 2026, described as closest to handover, while Series 3 was only 21.06% complete at the same date.
Verde by Sobha launched in April 2023 with a Q4 2026 date. The DLD site inspection of 24 August 2026 put it at 85% complete, but its DLD registered completion date is 30 June 2027.
Sobha Reserve was listed for Q2 2026 by Propsearch and Property Finder, a quarter that has passed without a confirmed handover. Data Habibi and Binayah now list Q4 2026, and the DLD register holds no registered completion date for the project. The DLD inspection of 5 August 2026 put it at 75.01% complete.
Due from 2027
Sobha Solis, Orbis, Elwood and SeaHaven are listed between 2027 and 2028. Sobha gives December 2027 for Solis, while its DLD registered completion date is 31 December 2028. Orbis is registered for 31 December 2028 and Elwood for 30 June 2028. At their latest DLD inspections, Solis was 17.92% built (22 October 2026), Elwood 14.35% (20 July 2026) and Orbis 18.20% (13 August 2026).
Sobha SeaHaven, three towers at Dubai Harbour, has two registered completion dates: 30 April 2028 for Tower A and 31 October 2028 for Towers B and C. Property Finder lists April 2028. At the latest DLD inspections, Towers B and C were 40.2% complete on 18 September 2026 and Tower A 37% complete on 6 August 2026.
Sobha Central and Sobha Sanctuary are the newest launches, from May 2025 and January 2026. Sobha lists December 2029 for the first Sobha Central towers and Q3 2029 for the first Sanctuary villas. The DLD register gives Sobha Central completion dates of 30 June 2030 and 31 December 2031, and Sanctuary 31 August 2030 for its villa clusters and 30 December 2030 for The Woods.
What to check before booking
- The completion date and grace period stated in the SPA for your specific project, phase and building, not the headline date for the wider community.
- Whether a Building Completion Certificate has been issued. Crest Grande shows what that looks like: a dated certificate followed by handovers starting.
- The DLD project status for your building through Dubai Land Department’s project status enquiry service.
- Which source you are reading. Sobha Solis alone carries two different published completion dates a year apart, so match the figure to its source and date before you rely on it.
Questions buyers also ask
Which Sobha project is closest to handover?
Sobha Crest Grande at Sobha Hartland. It received its Building Completion Certificate on 25 March 2026, and Sobha said handovers were commencing within its RERA timeline.
How many homes is Sobha handing over in 2026?
Sobha Realty said it planned 6,819 handovers across five Dubai projects in 2026, worth about AED 21.6 billion. The five it named are Sobha Hartland, Sobha Hartland 2, Sobha Reserve, Sobha One and Verde by Sobha (Business Today Middle East, 20 Jul 2026).
Is Sobha Solis due in 2027 or 2028?
Sources differ. Sobha's own website and Propsearch list December 2027. The DLD registered completion date is 31 December 2028, and Property Finder's project page lists the same December 2028 (Sobha Realty, accessed 1 Oct 2026; Mitchells, Sep 2026). Check the completion date in your SPA.
Is Verde by Sobha due in 2026 or 2027?
Sobha named Verde in its July 2026 plan for handovers during 2026, and gave Q4 2026 at launch in April 2023. The DLD registered completion date is 30 June 2027 (DLD register, via Mitchells, 23 Sep 2026). The DLD site inspection of 24 August 2026 put the tower at 85% complete.
Which Sobha projects are still at an early construction stage?
At their latest DLD inspections, Sobha Solis was 17.92% complete (22 Oct 2026), Sobha Elwood 14.35% (20 Jul 2026) and Sobha Orbis 18.20% (13 Aug 2026). Sobha Central's Phase I was 7.08% complete and Phase II 6.42% on 29 September 2026, and Sobha Sanctuary's The Brooks and The Greens were at 0% on 15 July 2026.
Where is each of these Sobha projects located?
Orbis and Solis are in Motor City. Reserve is in Wadi Al Safa 2. Central is on Sheikh Zayed Road. Sanctuary is on Dubai-Al Ain Road. Hartland 2 is in Bukadra. Verde is in Jumeirah Lake Towers. Elwood is in Dubailand, near Jebel Ali. SeaHaven is at Dubai Harbour. Crest Grande is at Sobha Hartland.