
Azizi Venice handovers now run through 2026 and into 2027
Azizi originally said Venice 1 to 3 would hand over in Q1 2026. In April, the first 14 buildings were 39% complete overall, with Venice 3 at 74%.
Read more
Research
Projects, prices, payment plans, handovers, rents and market activity.

Azizi originally said Venice 1 to 3 would hand over in Q1 2026. In April, the first 14 buildings were 39% complete overall, with Venice 3 at 74%.
Read more
Binghatti Ghost, Phoenix, Phantom, Azure, Onyx, Avenue and Crest are complete. The other 20 are not yet handed over. Several, including Elite, Hills, Starlight, Haven and Ruby, have already passed their published 2026 dates.
Read more
Azizi Riviera has handed over 53 of its 75 buildings. Azizi Venice, promised for Q1 2026, now has no fixed handover date.
Read more
The DLD register records three DAMAC Lagoons clusters as finished, the last in August 2026. Portofino and Nice are past their 2025 dates and at least 83.88% built, and the later clusters point to dates in 2027.
Read more
Sobha Crest Grande received its Building Completion Certificate in March 2026. Sobha Hartland 2, Verde and Reserve are next, all named in Sobha's 2026 handover plan, though Verde's DLD registered completion date is 30 June 2027. Orbis, Solis, Elwood and SeaHaven run into 2027 and 2028.
Read more
On a AED 2.7 million DAMAC Islands 2 entry unit, that means about AED 648,000 at booking once the 4% DLD fee is added, before the 25% due at handover in 2030.
Read more
Sobha has not given a tower by tower date. It named Sobha One as part of a record 6,819 unit handover plan for 2026, and the structure was 97.8% complete in Q1 2026.
Read more
Danube says every project has been delivered as promised, and some, including Pearlz and Opalz, handed over early. Eleven more projects are due within 12 months of August 2026.
Read more
The Central Bank of the UAE sets a flat 50% loan to value limit for off-plan property, for residents, nationals and non-residents alike. Mashreq, Dubai Islamic Bank, Arab Bank and Emirates NBD lend before completion, usually once construction passes about 30% to 35% and the buyer has already covered roughly half the price.
Read more
Danube publishes a 10/59/1/30 split on its current launches, with the last 30% paid at 1% a month for 30 months after handover. Other developers publish different splits, so the figure in your sale contract is the one that counts.
Read more
The Dubai Land Department's project register lists the DAMAC Islands clusters as under construction, with no units delivered yet. DAMAC Islands 2, launched a year later, is due about 18 months after phase 1.
Read more
Developers only issue the resale No Objection Certificate once a minimum share of the price is paid, commonly 30% to 40%, and Emaar requires at least 50% under its Preferred Access Programme. The Dubai Land Department then charges its 4% transfer fee again, on the resale.
Read more
The final AED 330,000 is due at completion on 31 December 2027, taking the total to AED 1.144M before admin fees.
Read more
Dubailand villas averaged AED 1,609 per sq ft in H1 2026, up 1.7% from 2025. At DAMAC Islands, 40% of the payment plan is due at handover in 2028.
Read more
The Heights is at AED 1,489 per sq ft, with its latest phases handing over in 2030. The Oasis is at AED 1,724 per sq ft, with average listings around AED 18.7M.
Read more
Azizi Venice recorded 3,479 registered off-plan sales. DAMAC Islands recorded 3,388, worth AED 24.6bn. The Heights recorded 898 and The Oasis 518.
Read more
Alaya's registered completion date was 20 July 2026. DLD's last inspection put it at 91.45% on 14 August, and the status changed to finished on 30 September 2026, then back to under construction by 18 October 2026 (Mitchells).
Read more
Emaar has built Arabian Ranches 3 in named clusters. Townhouse clusters such as Sun, Ruba, Raya, Anya and May have 3 and 4 bedroom homes of about 1,900 to 2,500 sq ft. June, Caya and Elie Saab are villas of about 3,000 to 5,900 sq ft.
Read more
Most of Arabian Ranches 3 is already handed over. Anya, Anya 2 and May are now recorded 100% complete and Ready on the DLD register, Anya at its inspection of 7 October 2026.
Read more
The registered completion date of 2 February 2025 and Azizi's later Q1 2026 target have both passed. The DLD recorded 82.06% complete on 24 June 2026, and Azizi reported 94% on 3 September 2026.
Read more
Each Azizi Milan tower has its own DLD registered completion date. Seven of the eight checked fall between March and June 2027, yet the last DLD inspections on record, all from 2025, recorded 0%. Property Finder lists June 2028 for the district.
Read more
Most of Riviera is handed over. Rêve, first due in October 2024, is now due in Q4 2026, and the newer numbered towers carry registered completion dates in March and May 2027.
Read more
The Q2 2027 target has held since Nakheel's February 2024 launch. Construction progress is well behind what that date needs.
Read more
The Dubai Land Department holds 31 December 2029 for Danube's 102 storey Business Bay tower. Danube's own page gives June 2029, and its own site check put the build at 16% on 31 August 2026.
Read more
The DLD register and Prestige One both give March 2028 for the JVC building. The 24 September 2026 inspection recorded 3%.
Read more
The DLD register gives Binghatti Cullinan a registered completion date of 30 June 2027. Its only published DLD inspection, in November 2025, came before construction formally started.
Read more
The DLD register still holds a completion date of 30 June 2026. Its last inspection, on 20 April 2026, recorded the tower at 53.25% complete, and no newer reading had been filed by late September.
Read more
The registered completion date of 31 March 2026 has passed and Binghatti has not published a new one. The last DLD inspection, on 7 May 2026, put the tower at 76.13% complete.
Read more
Binghatti's own date for Binghatti Hills was Q2 2026. The DLD inspection on 24 July 2026 recorded 90% complete, and no handover had been announced by 1 October 2026.
Read more
Binghatti, Property Finder and the Dubai Land Department all give 31 December 2026. The last published DLD inspection, on 23 April 2026, put the three towers at 22.4% complete.
Read more
The Dubai Land Department holds 31 March 2027 as the completion date for the 1,572 home tower in Majan. Its only published inspection, on 23 September 2025, recorded 0% before construction started.
Read more
Azizi says the 725 metre tower is scheduled for completion in 2029. The DLD register gives 30 August 2030, and the tower was still at foundation and basement stage in mid 2026.
Read more
The registered completion date on the DLD register has passed without a handover. The DLD site inspection of 31 August 2026 recorded the tower 52.05% complete, and Binghatti has not published a new date.
Read more
DAMAC's project page gives Q2 2027 for the 70 storey Cavalli branded tower. The DLD recorded it 85.08% complete on 15 July 2026, while the register still holds a completion date of 30 September 2025.
Read more
The DLD register still shows 27 March 2027. Nakheel's main construction contract, awarded in September 2024, set completion for Q2 2028, and the tower was 24.77% built in October 2026.
Read more
Sobha sold the tower in 2022 with a July 2025 handover. It finished about seven months early, and the DLD register now lists it as completed.
Read more
The three Cavalli towers in Dubai Harbour were 33.76% complete at the DLD inspection of 18 August 2026. DAMAC has given July 2027 or Q3 2027 since 2024.
Read more
DAMAC now lists Q2 2028 as the project handover for its Al Sufouh tower, while its unit listings show Q4 2028. The DLD inspection of 18 August 2026 recorded the building 33.55% complete.
Read more
Most of DAMAC Hills 2 is built and handed over. Eight clusters remain on the DLD register, from Violet, whose registered date has passed, to Violet 4, the last one due.
Read more
DAMAC gives one date, Q2 2027, for its Lagoon Views apartments. The DLD register tracks 13 phases, which were 5.96% to 55.58% built at their latest inspections.
Read more
The first owners in Santorini report good finishing and bright layouts. The main complaints are unfinished amenities, construction traffic and dust, and a large supply of homes still to come.
Read more
The DLD register gives 31 December 2027 for the Ivy, Lush and Sage townhouse clusters, June 2028 for Olive, and May 2028 to March 2029 for the Riverside Views apartment buildings.
Read more
Danube has kept the November 2027 date since the May 2024 launch. The DLD register holds no completion date for the tower, and its inspection of 20 July 2026 recorded 16.32% complete against Danube's own 30% at the end of August.
Read more
Danube's own date for Sportz has been Q2 2027 since its November 2023 launch. The DLD inspection of 8 October 2026 recorded 80.22% complete, against Danube's own figure of 90% from 31 August 2026.
Read more
The Cove II and Creek Palace were recorded as finished in 2026. Creek Waters is next, at just over 81% built. The last towers on the DLD register, Creek Haven, Creek Bay and Valia, are due in 2030, and Dubai Creek Tower still has no construction tender.
Read more
Emaar handed over the first villas in 2016. Lime Gardens, Hills Park, Golf Grand and Parkside Views were among those recorded as finished between September 2025 and May 2026. The last phases on the DLD register are due in 2029.
Read more
Beach Walk by Imtiaz became the first residential project handed over on Dubai Islands in March 2026. At least 68 more projects from more than 30 developers are on the DLD register with completion dates from 2026 to October 2029, and several 2026 dates have already passed.
Read more
No Dubai Lagoon building has been handed over. The DLD register changed the project to under cancellation on 22 October 2024, and refunds wait on that process.
Read more
Anwa by Omniyat has stood since 2022, and the DLD register recorded Riva Residence 100% built in December 2025. Nautica One and Two were above 85% built in September 2026. Chelsea Residences and Prestige One are registered for 31 December 2029.
Read more
Deyaar has given Q2 2027 since the launch in February 2024. The DLD register holds no completion date for the tower, and its September 2026 inspection recorded 20.01% complete.
Read more
The DLD register holds no completion date for Elitz 3. Its inspection of 18 September 2026 recorded 37.99%, and Danube's own inspection on 31 August 2026 put the towers at 48%.
Read more
Elitz 1 launched for Q4 2025 and its registered completion date has passed. Elitz 2 launched for Q3 2026 and Danube now shows December 2027.
Read more
The DLD recorded Ellington House in Dubai Hills Estate 100% complete on 29 July 2025, five months after its registered completion date of 28 February 2025. Ellington said on 29 September 2025 that handover was progressing.
Read more
Ellington Views is in Al Hamra Village, Ras Al Khaimah, so it is not on the Dubai Land Department register. Property Finder lists 1 March 2027 for Views I and Views II, and Ellington was still posting monthly site updates in September 2026.
Read more
The DLD recorded Elora's 430 townhouses 100% built on 10 March 2026 and complete on 13 March 2026. Emaar's launch schedule had set completion for September 2026.
Read more
Beachgate by Address reached 100% in September 2026. Address Residences The Bay is registered for 31 December 2026 at 70% built, Address Bayview for July 2028, The Bristol for September 2029 and Palace by the Beach for November 2031.
Read more
Golf Links, Golf Views, Urbana, Parkside 3, Greenview 3 and Expo Golf Villas are complete. The villa releases are 30% to 49% built, and most golf apartment releases are under 5%.
Read more
The Dubai Land Department registered the Maha, Yasmina and Shamsa homes for completion on 31 January 2026. Its inspection of 19 August 2026 recorded 66%, and no new date has been published.
Read more
Danube's dates for its FashionTV tower in JVT have ranged from July 2026 to July 2027. The DLD register holds no completion date.
Read more
Majid Al Futtaim is building Ghaf Woods in separate phases, each with its own date. Serra and Cilia were about 42% to 44% built in August 2026; Capria East and West had barely started.
Read more
IRTH's Business Bay office tower launched in February 2026. The register gives a later date and conflicting progress figures.
Read more
Aldar now gives Q4 2027, a quarter later than at launch. DLD inspections on 28 July 2026 put the three registered phases at 40.02%, 44.15% and 57.62%.
Read more
The 25-home Palm Jumeirah building gained half a point between July and October 2026. It needs about 94 more points in under 18 months.
Read more
Binghatti's Downtown Dubai tower still carries its launch date of Q4 2026 on the DLD register. It was 65.25% built at the April 2026 inspection.
Read more
Shamal Holding's island off Jumeirah is scheduled to open in 2029. No DLD registered completion date or construction percentage has been published, and the latest progress figure is for land reclamation.
Read more
Frond M's 146 villas are registered to complete on 8 October 2027, alongside Frond N. Progress rose from under 10% in October 2025 to just over 40% in August 2026.
Read more
Nakheel says phased villa handovers run from late 2026 through 2027. The DLD register gives each frond its own date, and the leading fronds were 35% to 56% built in August 2026.
Read more
Wasl's two Wasl 1 towers are in their last stage of construction. Tower B was 98.84% complete at its DLD inspection on 6 October 2026 and Tower A 95.54% on 8 September 2026.
Read more
Seagate is complete and Sunridge was recorded 100% built in March 2026. The other towers carry registered completion dates from 30 November 2026 to 30 June 2030, and the towers due from 2028 were below 18% built at their latest DLD inspections.
Read more
Bay Residences, the first phase, has a registered completion date of 15 October 2026. Beach Residences, the second, has none on file. At the June 2026 DLD inspections neither phase was half built.
Read more
The DLD recorded Rosewater 100% built on 7 November 2024 and its project record gives a handover date of 1 June 2025, matching the Q2 2025 date Emaar set in 2019. All three buildings share that date.
Read more
DAMAC has said since 2023 that its de GRISOGONO tower on Sheikh Zayed Road will complete in 2027. The DLD inspection on 12 April 2026, the latest on the register, recorded 31.35%.
Read more
The Dubai Land Department holds 31 December 2028 for the Dubai Land Residence Complex tower. Propsearch and some agents still show earlier 2027 dates that the register does not support.
Read more
Select Group gives July 2028 for the 122 storey tower, and Bayut gives 2029. The Dubai Land Department register holds no completion date, and its September 2026 inspection recorded 26.66%.
Read more
HRE Development began handing over Skyhills Residences, including Tower 1 - West, in April 2026. The RERA brochure had set an October 2026 completion date, and the DLD recorded 100% in July 2026.
Read more
Danube's Arjan tower obtained its Building Completion Certificate by 31 October 2025, a year after the 1 November 2024 completion date on the DLD register. Owners were still collecting keys in May 2026.
Read more
Sobha gives a date for each of the six towers. The DLD register files Sobha Central as three projects, with registered completion dates of 30 June 2030 and 31 December 2031.
Read more
Sobha Hartland 2 is a phased community with no single date. The villas are listed for December 2026, Sobha gives June to December 2027 for Riverside Crescent, and the registered completion dates for Skyscape and Skyvue run to 2029 and 2030.
Read more
Sobha Realty lists a separate handover date for each of the 18 clusters on its website. The first villas and beach residences are due in December 2027, the date Sobha gave for phase one in 2024. No construction percentage has been published.
Read more
The two dates are a year apart. The DLD inspection on 22 October 2026 recorded the Motor City project at 17.92% complete.
Read more
The tower was sold with a Q3 2025 date. It reached 100% at a DLD inspection on 4 August 2026, and Sobha announced the handover on 1 September 2026.
Read more
The Acres is three separate projects on the Dubai Land Department register. The first phase was 25.15% built in August 2026, and the two later phases were at 14.87% (30 Sep 2026) and 14.92% (30 Sep 2026).
Read more
Emaar gives December 2027 for Palmiera, the first cluster, which the DLD recorded 81.72% complete on 20 July 2026. Registered dates for later clusters run from 31 October 2028 for Palmiera 3 to 28 February 2030 for Mareva 2.
Read more
DLD recorded the two Emaar towers 76.05% complete on 2 June 2026.
Read more
Tilal Al Ghaf hands over cluster by cluster. The DLD register shows six clusters between 32% and 95% built in August and September 2026, with the last ones listed for Q4 2027.
Read more
Binghatti launched its first villa community in May 2026 but has not published a handover date. Propsearch estimates Q3 2028; Property Finder now lists Q4 2029. The DLD register shows the project's escrow account as still pending.
Read more
The DLD register holds 31 July 2028 for the 43 storey Silicon Oasis tower. Danube's own page now says Q2 2028, a quarter earlier than the Q3 2028 it gave at launch, and the DLD inspection of 9 September 2026 recorded 21.45% complete.
Read more
Deyaar announced on 6 October 2026 that it had handed over Tria's 711 homes and 6 retail units. The registered completion date on the DLD register was 30 June 2025.
Read more
Kamdar still gives Q1 2027. The DLD register holds 28 February 2027, but its October 2026 inspection found the building only 12.45% complete.
Read more
Tiger's JVT District 1 tower reached 100% at the DLD inspection of 19 October 2026, and the register changed its status to Ready. That was after both its registered completion date and the early July 2026 target the developer set in April.
Read more
Palladium Development's Al Jaddaf Waterfront building was 1.35% complete at the DLD inspection of 13 October 2026, about a year before its registered completion date.
Read more
The Al Furjan building rose from 53.40% in January 2026 to 80.15% in October 2026. Earlier marketed dates of Q4 2025 and Q1 2026 have passed.
Read more
The DLD register, ADE Properties and Property Finder all point to Q4 2028. The first DLD inspection since the January 2026 construction start recorded 1.67%.
Read more
The first building was the first residential handover on Dubai Islands, in March 2026. Beach Walk 3 passed its June 2026 registered date and was 97% built in October 2026.
Read more
The two phases are at very different stages. Phase 1 was 92.56% built at the DLD inspection in September 2026; Phase 2 was 51% built in October 2026 and has a registered completion date of 19 November 2027.
Read more
Takmeel gives a Q2 2028 handover. The DLD register has an earlier completion date of 31 March 2028, and the tower was 20.32% complete at its last inspection.
Read more
Danube, its launch statements and the DLD register all point to the end of 2029. The DLD inspection of 14 October 2026 recorded 0.10%, up from 0% in March 2026.
Read more
LIV Developers has given Q4 2026 for LIV Lux since its 2022 launch, and the DLD register shows 30 December 2026. The pace between the June and October 2026 inspections points to a finish a few months later.
Read more
The DLD register and Marquis Developers both point to December 2028 for the 489 unit Arjan tower. The October 2026 inspection recorded 0.29%, the first progress above 0%.
Read more
The Dubai Land Department holds 31 October 2028 for Barari Heights, six months later than Property Finder's April 2028. Barari Views and Barari Lagoons are separate Samana towers with their own dates.
Read more
The tower was 16.52% built in October 2026. Samana's own handover date has moved from April 2028 to Q3 2028.
Read more
The first building was 27.49% complete a month before its May 2026 target. Ivy Gardens 2 was 20.03% complete in October 2026 against a registered 31 December 2027.
Read more
The DLD register and Samana agree on Q3 2028 for the 428 unit DLRC tower. The target has moved one quarter since launch, and Property Finder still shows an earlier date.
Read more
Waves 1 was 90.61% complete and Waves 2 52.09% complete at DLD inspections in October 2026. Both buildings have passed their registered completion dates.
Read more
The 23 townhouse cluster in Saih Shuaib 2 is far ahead of its registered completion date. Agent listings have advertised handover as early as Q4 2026.
Read more
The 18 JVC villas have one registered date. The DLD recorded 28.45% in October 2026, up from 0% in November 2025.
Read more
Aldar gives Q2 2030 for its six apartment buildings at The Wilds. The DLD register lists construction starting on 1 June 2026 and completion on 30 June 2030.
Read more
Gutti Development now states Q4 2027 for its DLRC building, six months later than the Q2 2027 first promised. The October 2026 DLD inspection recorded 21.66%.
Read more
The 22 villas in MBR City District 11 were 62.07% complete in October 2026, up 11 points since July.
Read more
Wadan launched Weston in June 2026 with a Q4 2028 handover. The DLD register now holds 31 December 2028, moved earlier from 28 April 2029, and the first inspection recorded 0%.
Read more
Tiger's twin towers in Motor City, also listed as Ananda Towers, have gained about 0.3 points a month since December 2025. Almost all of the build is still ahead.
Read more
Tiger's 63 floor tower in JVC showed no recorded progress until 2026. Its registered date has not changed since sales began in May 2025.
Read more
The Dubai Land Department holds 27 March 2027 as the completion date for the 31 home Meraas tower on Jumeirah Bay Island. Its inspection of 8 October 2026 recorded 80.01%, and Meraas reported the superstructure complete in July 2026.
Read more
Tiger's twin towers in JVT were registered for completion on 28 February 2025 but were 72% built that month. The DLD recorded completion in October 2025.
Read more
The Dubai Studio City building missed its DLD completion date, and progress slowed to under one point a month in the three months to October 2026.
Read more
Tiger's twin towers in JVT District 1 added only 0.34 points between the July and October 2026 inspections. The registered completion date has not changed since launch.
Read more
LMD's Culture Village building is due by the end of 2026. At the pace recorded since June 2026, the DLD figure would not reach 100% until late 2027.
Read more
The building was 28.88% complete at the October 2026 DLD inspection. The developer's date is already a quarter later than the launch promise and the registered date.
Read more
The 60 unit building in Nad Al Hamar Gardens was 85.88% complete in October 2026. Listings point to late 2026, and the recent pace on the DLD register points to around the end of 2026.
Read more
The DLD register recorded the Dubai Maritime City project 17.64% complete on 7 October 2026, up from 8.61% in May. Beyond's own target for the ground slab was June 2026.
Read more
Tiger's twin towers in JVT were 26.71% complete at the last DLD inspection in March 2026. Agent dates range from Q4 2026 to Q2 2027.
Read more
The Liwan building was 70.35% complete at the DLD's October 2026 inspection. At the pace recorded since July, it would not be finished by the end of 2026.
Read more
Roz Real Estate Development's three Rose Gardens buildings in Arjan, Jumeirah Garden City and JVC have all passed their registered completion dates without finishing.
Read more
The DLD register still shows 30 April 2026 for the 300 unit Arjan building. It was 86.00% built at the inspection of 12 October 2026, and Samana's own page now says Q1 2027.
Read more
The DLD register holds 15 August 2028 for this Dubai Islands building. Imtiaz announced Q1 2028 at the June 2026 groundbreaking, and the October 2026 inspection put it at 7.70%.
Read more
Tiger's JVT District 4 tower has kept the Q1 2028 date it launched with. The build added about 3.1 points of progress in the six months to October 2026.
Read more
Vision Developments promised a Q4 2026 handover when it launched Soul in May 2025, and the DLD register still carries 31 December 2026. In October 2026 inspectors recorded the building 77.03% complete.
Read more
Tiger's 122 floor tower in Business Bay launched in May 2024 with a Q2 2029 completion target. Listings now say Q4 2028, while the build has averaged about a third of a point a month.
Read more
First marketed for Q2 2027, Verde by Vision is registered with the DLD for completion at the end of September 2027. In October 2026 inspectors recorded 11.97% of the work done.
Read more
Vista by Vision is registered with the DLD for completion on 1 September 2027, matching the Q3 2027 date it was sold with. Construction started in January 2026, and the October 2026 inspection recorded 12.20% of the work done.
Read more
Tiger's 40 floor tower in JVT gained 13 points of progress between June and October 2026. The DLD register holds no completion date.
Read more
Nshama's 80-home Address tower in Downtown Dubai holds a DLD completion date of 10 June 2028. At the DLD inspection of 7 October 2026 it was 10.76% built.
Read more
Alder's first progress figure came at a DLD inspection on 30 September 2026: 6.07% complete. Deyaar has given December 2027 since the September 2025 launch.
Read more
Binghatti announced the JVC tower's delivery on 12 December 2024, and the DLD register recorded it 100% complete the next day. Its registered completion date was 1 October 2024.
Read more
The first two phases, Crestlane 2 and 3, are registered for completion on 10 December 2028 and were under 7% built at their latest DLD inspections. Crestlane 4 and 5 are registered for 25 April 2030.
Read more
The DLD register, Imtiaz and Property Finder agree on December 2027. In July 2026 the foundations were still under way and the tower had not started rising.
Read more
Residents on Reddit in 2026 praise the value, the pools and the family feel. The most common complaints are build quality in older clusters, small rooms and a 35 to 45 minute drive to central Dubai.
Read more
Deyaar's June 2027 date has held since the October 2024 launch. In September 2026 the two towers still had 84% of the work to go.
Read more
Deyaar's date has held at Q4 2027 since launch. The building gained 4.24 points of progress between the June and September 2026 DLD inspections.
Read more
The Waterway and Future Residence are registered first, for 30 June 2027. Rove Home is registered last, for 31 August 2029. The most advanced tower, Ayaan Heights, was 20.3% built in July 2026.
Read more
The DLD register holds 15 May 2028 for the original phase and 31 August 2028 for phases 2 and 3. The original phase was 12.12% built at its 28 September 2026 inspection, and phases 2 and 3 were at 5.26% and 4.60% in June 2026.
Read more
Tria was handed over in October 2026, so there are no resident reviews yet. Buyers point to steady resale demand, while the delay, slower price growth than the area and Silicon Oasis traffic are the main concerns.
Read more
The International City Phase 2 building missed its DLD completion date. Progress rose about 17 points between April and August 2026.
Read more
Construction started in November 2025 and reached 6.84% at the August 2026 inspection. The developer's quarter is earlier than the registered date.
Read more
TownX, the DLD register and Propsearch all point to Q1 2027. The tower went from 41% to 80% complete between October 2025 and April 2026.
Read more
The DLD date has not moved, but the building was a third complete with under seven months left. At its recorded pace, Continental Club projects completion in 2028.
Read more
The first 1WOOD building missed its Q3 2025 target and was 93.67% complete in July 2026. 1wood Residence 2 started in March 2026.
Read more
The developer says the building reached 60% in September 2026. The DLD register's last reading, five weeks earlier, was 40.26%.
Read more
Beyond's office tower in Dubai Maritime City is registered to complete on 30 December 2028. In June 2026 it was 0.51% built.
Read more
The Dubai Islands building was 2.54% complete at its June 2026 DLD inspection. The sales agent gave Q4 2027 in January 2026; the register and portals say Q2 2028.
Read more
The 260-unit DLRC tower started construction in November 2024. By March 2026 the DLD register showed less than 3% of the work done.
Read more
Dugasta has three Al Haseen buildings under construction in Dubai Industrial City. All three were between 4% and 12% complete in mid 2026.
Read more
The DLD register gives the Jumeirah Garden City tower a June 2028 date, two quarters later than the Q4 2027 still shown in listings.
Read more
Object 1 still markets a Q4 2028 handover. The DLD register and Object 1's own brochure brief give 30 June 2029. The tower was 5.82% complete in September 2026.
Read more
The 24 villa private island on The World Islands was 16.37% complete in June 2026. Amali Properties gave Q1 2027 at launch and the end of 2027 in December 2025.
Read more
DLD recorded the Dubai Sports City tower 0.06% complete on 14 April 2026, six months after the registered construction start.
Read more
The DLD register still shows 31 January 2026. Omniyat's page now says Q4 2027, while the September 2026 pace would finish construction in early 2027.
Read more
The first cluster of Beyond's The Yards in City of Arabia was registered with DLD on 1 June 2026. Construction is registered to start on 30 October 2026, and the register shows 0% complete.
Read more
The four building Studio City project was 34.04% complete in August 2026. Meeting October 2027 needs about three times the recent pace.
Read more
Select Group gives Q1 2029 for both Artistry towers in d3. The DLD register holds 9 February 2029 for each, with no progress recorded yet.
Read more
TownX says Ashley Hills is on track for Q1 2027. DLD inspections show the Arjan project gaining about 5.6 points a month over the past year.
Read more
Danube's launch date of Q4 2028 matches the DLD register. The DLD recorded 5.08% in July 2026; Danube's own count was 11% by the end of September.
Read more
The DLD register gives Scope Properties' Wasl Gate project a 15 March 2028 completion date. The only published inspection, from January 2026, recorded 0%.
Read more
Nshama has kept the January 2028 date it gave at the April 2025 launch. The DLD register shows construction moving slowly in 2026.
Read more
The DLD register still carries a 1 November 2026 completion date for the Dubai Silicon Oasis building. A month earlier, inspectors recorded it 40.06% complete, so the date will pass with most of the work still to do.
Read more
The JVT tower was 30.07% complete at the September 2026 inspection. At its 2026 pace, it would finish after both dates.
Read more
The DLD register gives 4 August 2027 and Property Finder 30 June 2027. Construction was registered as starting in August 2025.
Read more
The DLD register gives Azizi Amir a two year build ending 17 June 2027. Its March 2026 inspection found 2.35% progress.
Read more
Azizi gave no date at the August 2025 launch. Listings settled on Q4 2027, while the register holds 30 September 2028. The last DLD inspection, in March 2026, found the tower 2% built.
Read more
Marketed for June 2027 at launch, Azizi's Dubai Healthcare City office tower is now registered for February 2028. The last DLD reading, in March 2026, was 3%.
Read more
The DLD register date is earlier than the Q4 2028 shown on Bayut and Propsearch. The only published DLD inspection, two weeks after the November 2025 launch, found no progress.
Read more
The Al Jaddaf tower was 2% complete at its last DLD inspection in March 2026. Propsearch still carries an earlier Q4 2027 estimate.
Read more
Broker pages listed Q4 2027 after launch. The DLD register and Property Finder now show 30 September 2028.
Read more
The DLD register and Property Finder agree on July 2027. Progress rose from 17.05% to 38.53% between the April and October 2026 inspections.
Read more
The Downtown Jebel Ali tower had no recorded progress at its only DLD inspection, in November 2025. The register's construction start is 4 July 2026.
Read more
Azizi launched Raffi in December 2024 for completion in September 2026. The DLD register now says 15 January 2028, and the last inspection, in March 2026, found it 2% built.
Read more
Azizi launched Rose in January 2026. Its registered construction start was 4 July 2026, and the only published DLD inspection, from February, shows 0% complete.
Read more
Azizi launched Ruby in JVC in January 2025 with a Q4 2026 target. In March 2026, DLD recorded the building 3% complete.
Read more
The DLD register holds 4 March 2028 for the Downtown Jebel Ali building. Portals showed Q4 2027 soon after the August 2025 launch.
Read more
Shamal Holding announced a 2026 opening in February 2023. The register still shows December 2026, but the developer now gives Q2 2027 and Property Finder Q4 2027 for the second tower.
Read more
The DLD register, Emaar and Property Finder all point to the end of 2029. The project was six months into construction at its June 2026 inspection.
Read more
The DLD register still shows the date Ellington gave at launch. The 4 June 2026 inspection recorded 3.08%, with 27 months to go.
Read more
The Dubai Silicon Oasis building moved from 1% to 11% between May and September 2026. It needs to roughly double that pace to finish on time.
Read more
The DLD register still holds a 31 December 2026 completion date for Reportage's 653 townhouses in Dubailand. At the 3 June 2026 inspection the community was 56.13% complete.
Read more
The DLD register still shows a completion date that passed in February 2026. No revised date has been filed or published.
Read more
The DLD register still holds 31 October 2026 for Binghatti Aquarise. Binghatti says Q1 2027, and one portal now shows Q2 2027.
Read more
Binghatti, Property Finder and the DLD register all give Q2 2027 for the JVC tower. The last published inspection put it at 10.33% complete.
Read more
Binghatti's own date is five months ahead of the DLD registered completion date. The tower was 7.24% complete in September 2026.
Read more
The twin JVT towers carry separate DLD records. Both were about one fifth built at the 19 June 2026 inspection.
Read more
The Arjan building has kept the date it launched with in October 2025. Progress rose by almost 10 points between July and September 2026.
Read more
The DLD register holds a completion date of 30 June 2026 for Binghatti Hillside. At the inspection on 17 September 2026 the tower was 80% complete, and Binghatti has not published a new date.
Read more
The DLD register still shows 1 April 2026. Binghatti now says Q4 2026, while another record shows Q2 2027. The tower was 32.6% built in June.
Read more
The DLD register holds 30 July 2027 as the completion date for the JVT tower, matching Binghatti's Q3 2027. The 17 September 2026 inspection recorded 7.04%.
Read more
The DLD register and Binghatti both gave June 2026. The tower was 19.24% complete at its last inspection on 29 June 2026, and no new date has been published.
Read more
Binghatti still lists Q1 2026 for its JVC District 16 tower. The DLD register shows less than half of the building complete, and Propsearch now estimates Q4 2027.
Read more
Binghatti gives Q4 2027 and the DLD register holds 30 November 2027. The tower was 17.06% built at the 21 April 2026 inspection.
Read more
Binghatti gives Q3 2026 and Property Finder 30 November 2026. The DLD recorded the Business Bay tower 31.14% complete on 30 April 2026.
Read more
The DLD register gives 31 October 2027 for the Motor City tower. Its only published inspection, on 7 January 2026, recorded 0% at the start of construction.
Read more
The DLD register holds a completion date of 28 February 2027 for Binghatti Titania. Its only published inspection, on 23 September 2025, recorded 0%.
Read more
Binghatti still lists Q1 2026 for its Al Jaddaf tower. The DLD register shows it just over half built, five months after the registered completion date.
Read more
The DLD register gives 30 December 2027 for the Al Jaddaf tower, launched in June 2026. Its only published inspection, in May 2026, recorded 0%.
Read more
The DLRC tower moved from about 65% to 92.52% complete between the May and September 2026 DLD inspections, with its registered completion date unchanged since registration.
Read more
Al Sayyah Group's twin towers in Arjan have held the same Q1 2029 date since launch in November 2024. The DLD has published two inspections so far.
Read more
The five-storey Dubai South building had its groundbreaking in early 2026. The last DLD reading, in May 2026, left almost the whole build to do in 16 months.
Read more
Golden Woods gave Q2 2026 and the DLD register 30 June 2026. On 8 October 2026 the register still listed the JVC building as active, with no completion recorded.
Read more
DAMAC's newest Lagoon Views apartment release has one DLD record for its four buildings. Construction started on the register on 15 July 2026.
Read more
Alaia's Jumeirah Garden City building was 10.3% complete at the DLD inspection of 23 September 2026, five months before its registered completion date. Portals give Q1 or Q2 2027.
Read more
The DLD register says 30 October 2028. Imtiaz's own page estimates Q2 2028, about four months earlier.
Read more
The International City building was 0.34% complete at its July 2026 DLD inspection. Agency listings still show Q1 2028, but the register and Property Finder say December 2028.
Read more
Wadan's Q4 2027 handover target and the DLD registered completion date agree. Construction started on 30 December 2025 and was 2.03% complete at the last DLD inspection.
Read more
Construction on the three DAMAC Hills towers started in February 2026. The DLD register recorded 4.07% complete on 22 September 2026.
Read more
DAMAC's June 2028 date and the DLD register agree. The June 2026 inspection put the build at 0.56%, ten months after its registered start.
Read more
DAMAC's 288-apartment Lilac building in DAMAC Hills holds a DLD completion date of 31 January 2030. The last inspection found no construction.
Read more
Valencia launched in February 2026. The DLD inspection on 20 May 2026 put it at 5.21% complete, and the handover date depends on which source is read.
Read more
The developer, Property Finder and the DLD register all give the end of June 2027. The building went from 0% to 20.78% between January and August 2026.
Read more
The DLD register still shows a December 2026 completion date for H&H Development's villa community. H&H's own phase 2 date is Q1 2028.
Read more
The register shows building work barely started by August 2026. Dates given for the villas have ranged from June 2027 to December 2027.
Read more
The seven canal-side buildings gained about 20 points between March and July 2026. Keeping to the date needs the same pace through to February.
Read more
Zoya still markets Q3 2027. The DLD register's completion date is six months later, and the only inspection so far recorded 0% progress.
Read more
The DLD register's completion date is one quarter earlier than Object 1's marketed handover. In August 2026 the tower was 0.19% built.
Read more
The 42 unit Jumeirah Garden City building gained more than 10 points of progress between DLD inspections in April and July 2026. The date has not changed since launch.
Read more
The launch target was Q3 2027. The register still carries a 0% inspection from September 2025, taken before construction formally started.
Read more
The DLD register gives both Ellington Sands phases the same completion date. In June 2026 each was 0.4% complete, eight months after work started.
Read more
Ellington markets Q4 2029 for both towers. The DLD register still shows 0% from an inspection taken before works started in April 2026.
Read more
Deyaar's summer 2027 promise and the DLD registered date still match. Progress on site has not caught up with them.
Read more
The DLD register and Empire Developments both point to the end of 2028. Registered work started in April 2026 and reached 0.04% by July.
Read more
Listings in 2024 quoted Q4 2027. Empire Developments now gives Q2 2028, and the latest DLD inspection, in March 2026, found the tower 2.05% built.
Read more
The Marasi Bay office tower was 7.25% complete at its June 2026 DLD inspection. Omniyat's own target has moved into 2028.
Read more
GRID launched the Arjan project in May 2026 and broke ground in July. The only DLD inspection so far, in April, recorded 0%.
Read more
The 170 unit Dubai South building was 14.63% complete at the DLD inspection of 28 July 2026, about five months after construction started.
Read more
The DLD register still carries 1 April 2027 and Elysian Developments still gives Q2 2027. The latest DLD inspection, on 3 September 2026, found the building 14.42% complete.
Read more
The DLD completion date for the 60 apartment Majan building has passed. Sales pages now give Q4 2026, but no new date is on the register.
Read more
The DLD register gave 30 September 2026. The developer later said December 2026. DLD inspections show progress flat at about 41% from August 2025 to June 2026.
Read more
The Dubai Maritime City tower sold out in December 2025. The only DLD inspection on file, from March 2026, recorded 0% progress.
Read more
Baron Development's 61 unit Al Furjan building has nine months to its registered completion date and has recorded less than 2% progress.
Read more
The DLD register still showed 14 October 2026 four days before that date. The last published inspection, from April 2026, recorded 89.05% complete.
Read more
The DLD register and the developer's sales material are about ten months apart. The building was 30.05% complete at the last DLD inspection in June 2026.
Read more
The DLD register gives Golf Grove a completion date of 2 January 2028. The building was 8.74% complete at the 10 June 2026 inspection.
Read more
Prestige One and the DLD register agree on February 2028. At the pace of the past year, the tower would reach 100% around August 2028.
Read more
The DLD register gives Emaar's Golf Vale a completion date of 31 March 2030. Its only published inspection, on 24 February 2026, recorded 0% before the registered construction start of 5 April 2026.
Read more
The DLD register gives LEOS's Hadley Heights 2 in Dubai Sports City a completion date of 20 October 2027. Phase 1, Hadley Heights in JVC, was completed in late 2025.
Read more
Construction was registered to start on 30 June 2026. The last DLD inspection, two weeks before that, recorded 0.01% complete.
Read more
DLD recorded Nshama's Town Square building 35.33% complete on 10 September 2026, with under six months left to its registered date.
Read more
IRTH's office tower on Marasi Bay was 0.7% complete at the 6 July 2026 DLD inspection. The developer date and the registered date match.
Read more
Mered's Pininfarina designed tower in Dubai Internet City carries a registered completion date of 28 February 2028. Mered's website still shows Q3 2027, and site progress points later than both.
Read more
The completion date in the DLD register passed more than five months ago. The last published inspection, from January 2026, recorded the building 43% complete, and no new date has been published.
Read more
The Zaha Hadid Architects tower started in December 2025. The registered date and Imtiaz's Q2 2029 have not changed since launch.
Read more
The JVC building's only published DLD inspection, from May 2025, recorded 56.68% complete. No newer figure has appeared since.
Read more
The three building Jumeirah Garden City project was 1.88% complete at its July 2026 DLD inspection. Foundation works were underway in September 2026.
Read more
Tiger's 28 floor tower in Majan has added about 3.4 points of progress in six months. Its registered completion date is less than six months away and has not been updated.
Read more
DLD recorded Arada's Jumeirah Golf Estates community 78.47% complete on 5 October 2026, three months after its registered completion date of 30 June 2026.
Read more
Beyond launched the Dubai Maritime City tower on 25 November 2025. The register shows construction due to start on 30 June 2026, with no inspection published since August 2025.
Read more
MAG launched Keturah Reserve in November 2022 for completion in Q2 2025. The date has moved twice, and the DLD inspection on 3 August 2026 put construction at 10.02%.
Read more
The DLD registered completion date for the 708-unit Arjan tower has passed. Progress more than doubled between March and September 2026, but most of the tower is still to be built.
Read more
The Al Furjan building was 34.57% complete at the June 2026 DLD inspection, after its fastest quarter so far.
Read more
Dubai Properties gives Q3 2028 for La Tilia. At the DLD inspections on 5 October 2026, Phase 1 was 13.75% complete and Phase 2 10.57%.
Read more
The DLD register gives Grand Signature's Lateral One in DLRC a completion date of 31 December 2026. Its pace between November 2025 and May 2026 points to a finish around that date.
Read more
The DLD register gives Laya Courtyard in Dubai Studio City a completion date of 26 December 2026. The September 2026 inspection put construction at just over half, which points to a later finish.
Read more
The DLD register and the developer both still point to December 2026. Inspectors recorded just over a quarter of the building done on 3 September 2026.
Read more
The JVC tower gained 3.18 points between July and September 2026, reaching 23.31% complete. Prescott's launch date was Q4 2027.
Read more
The DLD register still shows the 48 unit Dubai South building under construction. Its last published inspection, in February 2026, recorded 47.21% complete.
Read more
Construction began in February 2026 and stood at 0.69% at the 27 July 2026 DLD inspection. Holm's date is a quarter earlier than the registered one.
Read more
The two apartment phases under construction in the Dubailand golf community have separate developers, DLD records and dates.
Read more
Lucky Aeon launched the JVC building in May 2024 for a Q3 2026 handover. Both that date and the DLD registered date have now passed, and no new date has been filed.
Read more
The DLD register gives 30 December 2029. Two DLD inspections, in May 2025 and March 2026, found no recorded progress.
Read more
Zaya says handover will be phased from Q1 2029. The DLD register recorded 1.31% progress in June 2026, three months after works started.
Read more
Ermax Development's 57 unit building in International City Phase 1 has a registered completion date of 15 December 2026. The last DLD inspection found it 35.03% complete.
Read more
Emaar's Palace-branded tower at Green Gate, Dubai Creek Harbour, has a registered completion date of 31 July 2029. The only DLD progress figure so far is 4.77%, from March 2026.
Read more
MAG promised completion by the end of 2025 when it launched the Dubai Sports City tower in October 2024. The registered date has passed and no new date has been filed.
Read more
Pantheon and the portals still give Q4 2027. DLD inspections show the 28 floor tower rising at about 0.28 points a month.
Read more
DLD recorded the JVC tower 27.17% complete on 20 August 2026. The developer's date and the register's date are six months apart.
Read more
The Majan office building's registered completion date has passed. Its last DLD inspection, in August 2026, put it at 37.75%.
Read more
The DLD register holds 20 June 2027 for Sharafi Development's Dubai Islands building. It was 5.33% complete at the June 2026 inspection.
Read more
The DLD register still shows 21 November 2026 for the Al Barsha 1 building. The August 2026 inspection found it 26.34% complete, and Propsearch now shows Q3 2027.
Read more
The DLD register gives the JLT office tower a 20 September 2029 completion date. Its last published inspection, from November 2024, recorded 24.47%.
Read more
The DLD register carries an earlier date than Green Horizon's own Q1 2028. The last DLD inspection, in April 2026, recorded 1.37%.
Read more
The 76 unit JVC building was 19.09% complete at its last DLD inspection, in August 2025. No newer reading had been published by October 2026.
Read more
The DLD register still shows 1 April 2027 for the DLRC building, and portals say Q2 2027. The latest inspection, on 22 April 2026, recorded 0.44%.
Read more
The DLD register gives 31 August 2027 for Zoya's 60 unit building in Dubai South. It was 16.12% complete at the July 2026 inspection.
Read more
The DLD register and Mira Developments both point to the end of 2026. The July 2026 inspection recorded 31.8%, with roofs and early services still under way in August.
Read more
The DLD register, Emaar's payment plan and Property Finder all give September 2029 for the Green Gate tower in Dubai Creek Harbour.
Read more
The City Walk tower was first scheduled for completion in December 2026. The DLD register now holds 27 January 2027, and the August 2026 inspection recorded 73.23%.
Read more
The DLD register and Muraba both give December 2028 for the 380 metre Al Wasl tower. Four inspections in 2026 show progress rising from 5.45% to 7.6%.
Read more
The International City Phase 2 building started construction in September 2025. Listings already give dates from Q4 2026 to Q4 2027.
Read more
The DLD register gives Riviera Group's 19 villa community a completion date of 12 February 2027. The last inspection, on 25 June 2026, recorded 34.06% complete.
Read more
Al Ansari's Dubai Science Park tower carried a two year schedule from its December 2024 launch. Portals now give June 2027, and the DLD pace points later still.
Read more
Every published date for Wadan's first Dubai project points to September 2027. The DLD recorded 24.87% in July 2026; Wadan later showed 33.40%.
Read more
The DLD register recorded the DLRC building 0.79% complete on 20 July 2026. Construction started in April 2026, a month after launch.
Read more
The register date is about three months later than the developer's own Q1 2027. Progress of 3.4 points a month points to early 2028 unless the pace rises.
Read more
Danube and the DLD register both give November 2027 for its second Oasiz tower. Danube reported 33% on 31 August 2026, and said in July that both Oasiz towers would hand over within 12 months.
Read more
The DLD register still holds 31 March 2027, but its September 2026 inspection put the Dubai Islands project at 23.3% complete. Samana's own page now says Q4 2027.
Read more
The developer's Q3 2027 and the DLD date agree. Progress on the 112 unit Dubai Islands building reached 6.24% at the inspection of 1 September 2026.
Read more
The DLD register still shows 30 April 2027 for Segrex Development's 78 unit building. Construction was 5.45% complete in April 2026, and the developer's page has moved to Q3 2027.
Read more
The DLD register gives 31 July 2028 for Innovate Living's Dubai Islands building. Its February 2026 inspection recorded 0.04% progress.
Read more
Kasco first promised a Q2 2027 handover. The DLD register now shows 31 August 2027, and inspectors recorded the tower 61.1% complete on 19 August 2026.
Read more
The DLD register still holds 30 May 2026 for One by Binghatti. The tower was 50.21% complete two weeks before that date, and Binghatti has moved its own date to Q4 2026.
Read more
The DLD register and Preston Development both point to December 2027. The only published DLD inspection shows 0%, and an older portal date of September 2026 has passed.
Read more
DLD recorded Iman's JVC tower 20.05% complete on 22 September 2026, 21 months after the registered construction start.
Read more
DLD recorded Ellington and Dutco's Business Bay tower 35.43% complete on 21 July 2026. At the past year's pace, completion would fall in 2029.
Read more
The Dubai South building was 48.47% complete at the last DLD inspection in May 2026. Its registered completion date has not been updated since it passed.
Read more
The DLD register and Emaar agree on Q1 2029. The project was 20.52% complete at the last published inspection in June 2026.
Read more
Nakheel gives Q4 2026. In August 2026 the towers were between 74.27% and 82.83% complete, and each had gained only 2 to 3 points since May.
Read more
Every source gives January 2028 for the Meydan Horizon tower, launched in October 2024. Progress since May 2026 has been about 1 point a month.
Read more
The Palm Jumeirah towers were at 0% on the DLD's March 2026 inspection. Beyond reported excavation and shoring complete in April 2026, with foundation piling next.
Read more
The DLD register gives a completion date 13 months later than the developer's own project page. Construction was 3.52% complete in September 2026.
Read more
IGO promised a Q1 2026 handover at launch. The registered date has passed, and the last DLD inspection, in April 2026, recorded the tower 84.23% complete.
Read more
Tower 1 was 5.6% complete in September 2026 and Tower 2 was 6% complete in August 2026. H&H's Q1 2029 target matches the register.
Read more
Wasl's townhouses at Jumeirah Golf Estates are registered for completion in November 2028. The latest published DLD reading is from March 2026.
Read more
Zoya Developments has marketed its Al Furjan building for Q1 2027 since launch. With 42% of the work left in late August 2026, the registered date leaves little room.
Read more
The DLD register holds 30 June 2027 for this JVC building. Inspections show 7.64% in December 2025 and 7.7% in July 2026, and Property Finder already shows Q4 2027.
Read more
Launch material gives Q2 2029, the DLD register 1 December 2029. The site was at 0% in July 2026, with a registered construction start of 1 December 2026.
Read more
REEF Luxury Developments has five buildings in the DLD register. Only REEF 1000 is past the halfway mark, and its pace since July 2026 points to completion around the turn of the year.
Read more
The DLD register sets a completion date six months earlier than the developer's target. At the last published inspection, in June 2026, construction stood at 0.39%.
Read more
The Q4 2027 date given at launch in 2023 has not changed. DLD and the developer report different progress figures.
Read more
The register date and the developer's target match. The building was 7.03% complete at the DLD inspection of 6 August 2026, with the main contractor due on site from April.
Read more
The DLD register gives 31 December 2027 for Samana's 42 unit building in Majan, listed as Rome By Sd. It was 38.71% complete in September 2026.
Read more
The DLD register holds 31 March 2028 for the 682 unit tower. The developer still says Q4 2027, and the July 2026 inspection put progress at 7.8%.
Read more
The DLD register holds a completion date three months earlier than the one Al Seeb Developers announced at launch. The tower was 56.18% complete in August 2026.
Read more
The DLD register holds 10 November 2027 for this Dubai Islands project. The June 2026 inspection put it at 14.69%, after 11.54 points of progress in a year.
Read more
The DLD register still carries 31 March 2027 for SAAS Hills. The May 2026 inspection found the two towers 12.98% complete, and the developer's date is now Q4 2027.
Read more
HRE broke ground in May 2026 with a Q4 2028 target. The DLD register holds 30 June 2029, and the project was 3.58% built in September 2026.
Read more
The DLRC building was 31.79% complete at its DLD inspection on 1 October 2026, with progress speeding up through 2026.
Read more
The Majan office and retail tower was 6.01% complete at the DLD inspection of 23 September 2026, about 25 months before its registered completion date.
Read more
Samana promised Q1 2027 at launch in late 2023, and the DLD register still says 31 March 2027. Samana's own page now gives Q2 2028, and the tower was 26.81% built in May 2026.
Read more
The Downtown Jebel Ali office tower was 0.8% complete at the DLD's 28 September 2026 inspection, seven months after the registered construction start.
Read more
The first building was 12.83% complete at its DLD inspection on 24 September 2026. The second, larger building was 2.96% complete in April.
Read more
Samana now gives Q2 2028, later than the Q1 2028 shown at launch. DLD inspections show progress of about 0.3 points a month over the past year.
Read more
The Arjan building launched in October 2025 with a March 2029 target. The DLD register carries a date one quarter earlier, and the June 2026 inspection put it at 3.76%.
Read more
Samana promised July 2025 at launch in February 2023. The DLD register date of 30 April 2026 has also passed, and Samana now gives February 2027.
Read more
The DLRC building reached 38.03% at the DLD inspection of 1 October 2026. Its register date is seven months earlier than the handover Samana announced in October 2024.
Read more
Both towers of Samana Resorts share one registered completion date of 30 May 2028. Construction was 5.85% complete in June 2026, and the developer's date has moved from Q4 2026 at launch.
Read more
The Dubai Production City tower was 2.23% complete at its DLD inspection on 16 June 2026, nine months after the registered construction start.
Read more
Neither South Haven building had recorded construction progress at its last DLD inspection. South Haven 2's registered date moved back three months in September 2026.
Read more
The DLD register still shows a 15 October 2026 completion date for Samha's JVC building. The 14 August 2026 inspection recorded 52.07%.
Read more
The DLD register gives 15 December 2026 for Dar Al Karama's JVC tower. It was 62.28% built in July 2026, up only 0.41 points from March.
Read more
Unique Saray has marketed Q4 2027 since launch. Three DLD inspections in ten months show the building moving from 0% to 2.22%.
Read more
The Dubai Maritime City tower was 30.99% complete on 1 October 2026, exactly a year before its registered completion date. Beyond already points to Q1 2028.
Read more
The DLD register still shows 30 November 2026 for this Dubai Islands building, but the August 2026 inspection put it at 22.2%. A June 2025 report already gave 30 June 2027.
Read more
Prestige One gives December 2026. The Dubai Islands building was 43.03% complete on 30 July 2026, adding about 3 points a month since April.
Read more
Beyond promised Q1 2029 at launch in February 2025, and the DLD register holds 30 March 2029. Inspectors recorded the tower 17.54% complete on 1 October 2026.
Read more
Before launch, agents gave Q4 2027. The DLD register now puts completion at 1 April 2028, with construction registered to start on 1 August 2026.
Read more
The DLD register and Wadan Developments both point to the end of 2027. The DLD inspection of 22 July 2026 recorded 11.12%, while Wadan's own tracker shows a higher 18.42%.
Read more
The DLD register holds 31 December 2029 for the JVC tower. The DLD recorded 0.08% in July 2026, and Danube reported 3% at the end of September, with piling under way.
Read more
Danube gives 2029 and the DLD register 30 June 2029 for the Sheikh Zayed Road office tower. Work was at foundation stage at the August 2026 inspection.
Read more
Iman Developers and the DLD register agree on mid-2029 for its Motor City tower. The August 2026 inspection recorded 3.74%, and Property Finder alone shows January 2029.
Read more
The JVC building launched in June 2026 and was 12.6% complete at its DLD inspection on 10 September 2026.
Read more
The DLD register holds 30 May 2030 for this DLRC tower, about 18 months after the Q4 2028 date in November 2025 launch reports. No progress above 0% is on record yet.
Read more
SOL Properties has given Q3 2028 since 2025, and the register agrees. Progress so far has averaged under one point a month.
Read more
The DLRC building has kept its three year schedule since its May 2025 launch, and its recent pace is slightly ahead of what the date needs.
Read more
SOL Properties promised Q3 2027 when it launched Fairmont Residences Solara Tower in July 2024. The DLD register holds 15 August 2027, and the tower was 20.73% built in June 2026.
Read more
The DLD register dates the construction start to 30 March 2026. Its only inspection, from September 2025, shows an empty plot at 0%.
Read more
Dubai South Properties scheduled South Bay handovers for 2026. The DLD register shows South Bay 1 and 2 past their registered dates and none of the six phases finished.
Read more
The DLD register gives 10 November 2029 for Al Helal Al Zahaby's 128 unit building in International City Phase 2. It was 13.35% complete in August 2026.
Read more
The 41 unit Meydan building gained about 18 points between February and June 2026. Just over half the work remained six months before the registered date.
Read more
The developer and the register give dates six weeks apart. In August 2026 the Dubai Islands building was 16.29% complete.
Read more
The Al Furjan building has been sold with a Q2 2027 handover since June 2025, and the DLD register carries 15 June 2027. In April 2026, inspectors recorded 2.12% of the work done.
Read more
The DLD register and Property Finder say June 2028. Propsearch, Engel & Völkers and several agents say Q1 2029. Three DLD inspections have recorded 0%.
Read more
Phase 1 was 20.4% built at its DLD inspection in June 2026. Phase 2, registered separately, had not started when last inspected.
Read more
The JVC tower started construction on 1 November 2025. Property Finder's Q1 2028 matches the register; some brokers quote Q3 2028.
Read more
Listings once gave June 2027, and Q2 2027 was the date when the contractor was appointed in July 2025. The register now holds the last day of 2027.
Read more
Dugasta's 366 unit tower in Dubailand Residence Complex was 7.43% built in July 2026. Its registered completion date of 30 April 2027 no longer matches the developer's own date.
Read more
Green Group's date has moved from Q4 2027 in early listings to Q3 2028. The last published DLD inspection, in April 2026, found the 272-unit tower 3.97% complete.
Read more
The DLRC tower was 10.57% complete at its DLD inspection on 23 September 2026. Listings in 2025 promised Q3 2027.
Read more
The Meydan Horizon tower was 0.47% complete at its last published DLD inspection on 2 June 2026, about seven months after construction started.
Read more
The four Arjan towers were 10.48% complete at the last DLD inspection. Completion was expected by 2026 when sales opened in 2024.
Read more
DLD recorded the Sheikh Zayed Road tower 2.61% complete on 8 September 2026. Al Seeb appointed its main contractor a month earlier.
Read more
AQUA's date has not changed since December 2024. The only DLD progress reading on the register, 22.42%, is from October 2024.
Read more
The DLD register and Meraas's own sales sheets give dates up to seven months apart. Construction was 0.24% complete in August 2026.
Read more
Emaar's Serro, Serro 2, Salva, Faro and Faro 2 clusters carry registered completion dates from 31 March 2030 to 31 July 2030. None was more than 0.5% built at its latest DLD inspection.
Read more
Beyond launched The Mural in April 2025 with completion by Q2 2028. The DLD register now carries 10 July 2028, and the 1 October 2026 inspection recorded 16.64% of the work done.
Read more
Launch material in 2024 quoted Q4 2026. Prestige One now gives June 2027, and the building gained 0.49 points between the June and September 2026 inspections.
Read more
Towers A and B were 42.68% complete at the last DLD inspection and their registered date has passed. Tower C was 13% built in May 2026.
Read more
The 38 Crown Garden Villas on Palm Jumeirah got their main contractor in December 2025. Earlier listings had given 2026 dates.
Read more
AMIS Development promised completion by April 2028 at launch in November 2025. The DLD register holds the same date, with construction registered to start on 30 April 2026.
Read more
The JVT tower was 80.42% complete at its last published DLD inspection in April 2026. Metrical has given November 2026 since launch.
Read more
Aldar's villa phases at The Wilds carry DLD completion dates of 31 January, 28 February and 31 May 2029. In September 2026 the most advanced was 7.48% built.
Read more
Agents marketed a Q1 2027 handover for this six storey building in MBR City District 11. The DLD register holds 30 June 2027, and the only inspection on record found 0.74% complete.
Read more
The register's completion date moved from 2021 to 2026 in August. The September 2026 DLD inspection recorded 60%, and most listings now say Q1 2027.
Read more
Fakhruddin's 65 home Dubai Islands tower launched in February 2026. The only DLD inspection so far, in January, recorded 0%.
Read more
Fakhruddin Properties markets Q4 2027 for its two Dubai Islands towers, matching the DLD register. The last recorded progress was 5.24%.
Read more
The JVC tower launched in February 2026. The DLD register recorded 0% in March 2026, and Wadan's own figure was 1.43% by October.
Read more
The DLD register has not moved the 1 April 2026 completion date, but the July 2026 inspection put the tower at about two thirds built. Portals now show Q4 2026.
Read more
Kasco has kept the Q4 2026 date it gave at launch in November 2024. Inspectors recorded the building 72.55% complete on 19 August 2026, with about four months to go.
Read more
The Al Furjan building reached its registered completion date just short of 100%. A developer-supplied date of Q3 2027 also appears on the DLD-based record.
Read more
The DLD register still shows 31 December 2026, a date the building cannot meet. Prescott's own date since launch is Q3 2027, and the 2026 pace points later still.
Read more
Reportage's newer Verdana phases in Dubai Investments Park have three registered dates. At their last DLD inspections none had passed 0.14%.
Read more
Emaar's 500-home Vida project in Dubai Hills Estate started construction on 30 June 2025. Progress doubled between January and May 2026, from 5.01% to 10%.
Read more
The registered completion date passed with no newer inspection published. The developer's site says Q2 2026 and portals say Q3 2026.
Read more
The DLD register sets 15 February 2030 as the completion date, about eight months after the Q2 2029 target reported at launch. The July 2026 inspection still showed 0% progress.
Read more
The DLD register still shows 30 September 2026 for the Dubai South building. Listings have moved to 2027 without a new registered date.
Read more
DLD recorded the JVC tower 68.21% complete on 27 August 2026. The developer now gives Q4 2026, while the recent pace points to early 2027.
Read more
The DLD register and HRE Development agree on early 2028. Progress has picked up since June 2026 but is still well below the pace the date needs.
Read more
The developer's Q4 2027 matches the DLD register. Property Finder still shows December 2026, the date quoted when sales opened.
Read more
The 79-apartment Dubai Islands building was 15.9% complete at the DLD inspection of 27 July 2026. The two dates are a year apart.
Read more
The DLD register gives Ellington's Dubai South project a 31 July 2029 completion date. The 17 June 2026 inspection recorded 3.08%.
Read more
Imtiaz gives Q3 2027 for its Dubai Islands building, and the DLD register carries 30 September 2027. The 6 October 2026 inspection found it just over a quarter built.
Read more
The tower was 57.85% built at the DLD inspection of 18 August 2026. It has no registered completion date on the DLD register, and the published dates run from March to December 2027.
Read more
The registered completion date of 1 April 2020 has passed with the project at 32.82% on the DLD register figure. Inspectors declared it on hold in January 2018, The Times reported.
Read more
Azizi gave Q4 2025 for its Al Furjan building through 2025, then Q1 2026. The DLD recorded completion in June 2026 and handover began in July.
Read more
The DLD register recorded Azizi Mirage 1 100% complete on 14 October 2025. Its 762 homes in two buildings match Beach Oasis I, which Azizi began handing over on 24 December 2025.
Read more
The DLD register records Azizi Pearl in Al Furjan as 100% complete at an inspection on 5 June 2024, the same day as its registered completion date. Construction had started in July 2017.
Read more
The DLD register recorded Azizi Vista 100% built on 30 August 2025 and complete on 30 September 2025. Azizi began handing over keys on 22 October 2025.
Read more
Meraas launched its Al Qudra Road townhouses in January 2019 with handover set for June 2021. The DLD register holds a 31 May 2022 completion date and recorded the project 100% complete on 10 October 2023.
Read more
Seacrest launched in April 2025 and is now sold as Chelsea Residences by DAMAC. Its DLD completion date is 31 December 2029, and the final Chelsea tower carries June 2030.
Read more
Ithra Dubai first aimed to start handovers at the end of 2019. The first plaza followed in September 2020, and the last big Phase 1 piece, the Gold Souk Extension, opened in April 2022.
Read more
Majid Al Futtaim aimed to finish Elysian Mansions by mid-2026. DLD recorded 95.02% on 14 August 2026, and the registered date of 31 March 2025 has not been updated.
Read more
Emaar built its Emaar South villa community as six separately registered DLD projects, Parkside 1 to 3 and Greenview 1 to 3, now named Expo Golf Villas 1 to 6. The last, Expo Golf Villas 6, was completed in Q2 2025.
Read more
Emaar's payment plan puts Golf Lane's final payment at 100% completion in October 2028. The DLD recorded the villas 30.05% built on 18 June 2026, and no completion date is filed on the register yet.
Read more
Emaar launched Nara in July 2021 with a December 2024 completion date. The DLD recorded the 372 townhouses 100% built on 25 November 2024, against a declared completion date of 30 December 2024.
Read more
The DLD register records one completion date for both Opalz towers in Dubai Science Park. Danube promised 2025 at launch and finished in April of that year.
Read more
Frond P's 90 villas share the earliest registered date on Palm Jebel Ali with Frond O, but at its last DLD inspection it was the least built of Fronds K to P.
Read more
Deyaar announced the handover of Regalia's 913 units on 21 April 2026, and the DLD recorded the Business Bay tower 100% complete on 29 April 2026. The registered completion date had been 31 December 2024.
Read more
Samana's first private pool building in Dubai Studio City was completed in early 2023 on the DLD record and formally handed over at a ceremony on 7 December 2023.
Read more
The DLD register held a 30 April 2024 completion date for Samana's Arjan building. Its inspection reached 100% on 30 September 2024 and Samana held the handover in December 2024.
Read more
Samana launched its Dubai Studio City building in 2022 with handover set for April 2025. The DLD register recorded it 100% complete on 19 February 2026, and Samana held the handover in April 2026.
Read more
Emaar has handed over The Valley's early clusters and, in 2026, Elora, Farm Gardens and Lillia. More than 20 clusters remain on the DLD register, from Rivana at 93.82% to the Alva phases at 0%.
Read more
The DLD register records Westwood in Al Furjan as 100% complete on 27 November 2023, which is also its registered completion date. Construction had started in February 2018.
Read more
The Dubai Land Department holds 30 March 2028 as the completion date for all 770 Sun City townhouses and villas. Its latest inspection, on 24 September 2026, put construction at 36.54%.
Read more
The registered completion date for Samana's Arjan building passed five months ago without an update. The DLD inspection of 29 September 2026 recorded it 71.34% complete, and Samana has not published a revised date.
Read more
The Dubai Land Department holds 31 December 2028 as the completion date for the two Aman towers and four villas on Dubai Peninsula. H&H's website says 2029 and its sales documents say early 2030.
Read more
The Dubai Land Department holds 31 May 2028 for Athlon phase 1 and 30 September 2028 for phase 2. Its inspections of 23 July 2026 put them at 18.22% and 12.31% built. The Rise by Athlon apartments are registered for December 2029 and January 2030.
Read more
The Dubai Land Department holds 16 January 2028 as the completion date for the 555 home tower in Downtown Jebel Ali. Its only progress figure since work started, from 24 March 2026, is 2%.
Read more
Beach Oasis 1 began handing over in December 2025. Beach Oasis 2 was 53.22% built at the DLD inspection of 7 September 2026, more than four months after its registered completion date of 30 April 2026.
Read more
Nakheel awarded the main contract for phases 1 and 3 on 17 September 2026, with main works due to finish in late 2028. DLD inspections in July 2026 put both phases between 5% and 7% built.
Read more
Binghatti and the Dubai Land Department both give 31 December 2027 for the two Skyflame towers in Majan. The only published DLD inspection, on 17 February 2026, recorded 0%.
Read more
The DLD register still holds a completion date of 31 March 2026. Its last inspection, on 14 May 2026, recorded the Al Jaddaf tower at 63.11% complete.
Read more
The Dubai Land Department holds 30 June 2029 as the completion date for the Dubai Maritime City tower. Its July 2026 inspection recorded 0.14%, and Danube reported 3% at the end of August.
Read more
Both Emaar towers on Creek Island were about 81% complete at their DLD inspections in late July and early August 2026. Neither date has moved since sales opened in 2023.
Read more
DAMAC gives Q2 2030 for the whole community. The DLD register splits it into ten clusters, and none was above 0.33% complete at its latest inspection.
Read more
Emaar's Golf Fields building in Emaar South has a registered completion date of 28 February 2030. The DLD inspection of 4 August 2026 recorded 0% progress, and one broker's payment schedule puts handover in September 2030.
Read more
Emaar has not published a handover date. The DLD register gives each cluster its own completion date, from February 2029 for Chevalia Estate to August 2029 for Equiterra and Equestra, and the most advanced cluster was 11.08% built in August 2026.
Read more
The Dubai Land Department holds 31 March 2029 for the residences and hotel at La Mer. Meraas says marine works and piling are finished and foundation works come next.
Read more
Phases 1 and 2 are handed over. Phase 3 was 97.03% built at its DLD inspection of 30 July 2026, more than five months after its registered completion date. Phases 7 to 12 are registered for February 2028 to August 2029.
Read more
The Dubai Land Department holds 30 November 2027 as the completion date for the Oasiz tower in Dubai Silicon Oasis. Its July 2026 inspection recorded 30.36%, and Danube reported 33% a month later.
Read more
The Dubai Land Department holds 31 December 2026 as Orla's completion date. Omniyat's August 2026 update targets the Building Completion Certificate in early 2027, and the DLD recorded 70.01% on 21 August 2026.
Read more
The Dubai Land Department holds 30 June 2028 as the completion date for Elwood Estates, the registered villa project at Sobha Elwood. Its inspection of 20 July 2026 recorded 14.35%.
Read more
The Dubai Land Department holds 31 December 2028 as the completion date for all seven Orbis towers. Its site inspection of 13 August 2026 put the project at 18.20% complete.
Read more
Sobha Reserve was listed for completion in June 2026. The DLD inspection on 5 August 2026 recorded 75.01%, and portals now list Q4 2026.
Read more
Sobha launched the AED 50 billion community in January 2026. Four clusters are on the DLD register, all at 0% at their latest inspections, with registered construction starts at the turn of 2027.
Read more
The DLD register splits SeaHaven into two projects with dates six months apart. Towers B and C were 40.2% built on 18 September 2026 and Tower A 37% on 6 August 2026.
Read more
Sobha launched Verde in April 2023 with a Q4 2026 completion date and named it in its 2026 handover plan. The Dubai Land Department register now holds 30 June 2027.
Read more
The DLD register, Property Finder and Propsearch all give May 2028 for Danube's Al Furjan project. Progress doubled between the May and August 2026 inspections, from 3.84% to 7.75%.
Read more
Omniyat gave Q3 2027 when it appointed ACC Group as main contractor in May 2025. The DLD inspection on 18 May 2026 recorded 21.81%, a year before the registered completion date.
Read more
Tenants praise the central Meydan location and the community feel. The most common complaints are small apartments, maintenance, construction noise and service charges of about AED 17 to 25 per sq ft.
Read more
Villas launched from AED 18 million in September 2023. Registered resales in 2026 range from about AED 18.5 million for a 6 bedroom villa on Frond M to AED 49 million for a 7 bedroom villa.
Read more
Residents rate the highway access and the amenity deck. The main complaints are the slow build, Arjan parking and traffic, and an 11.3% rise in the 2026 service charge.
Read more
Residents and local guides praise the quiet, the Golden Beach and the Sports Village. The common complaints are a 40 to 50 minute peak commute, no schools inside the community yet, limited shops and ongoing construction.
Read more
Residents quoted in The National praise the lagoon, schools and neighbourhood feel. A resident petition lists mosquitoes, cut-through traffic and construction dust, and later clusters are still being built.
Read more