Handover date

When will Sobha One be handed over?

Updated 28 September 2026

Short answer

Sobha has not published one handover date for Sobha One's five towers. Property Finder and Bayut list Q4 2026, with a completion date of 31 December 2026, but an earlier Propsearch estimate showed June 2026. Sobha itself has said only that Sobha One is part of its record 6,819-unit handover programme for 2026, without giving a specific date (Business Today Middle East, 20 Jul 2026). Construction was 78.51% complete overall in Q1 2026, with the structure 97.8% done, so check the completion date for your tower in your SPA.

Overall construction, Q1 2026

78.51%

Construction tracker via topluxuryproperty.com

Structure complete, Q1 2026

97.8%

Construction tracker via topluxuryproperty.com

Handover listed by portals

Q4 2026

31 Dec 2026. Property Finder, Bayut

Sobha's 2026 handover programme

6,819 units

Across 5 projects including Sobha One

What Sobha has said

Sobha Realty launched Sobha One at Cityscape Dubai in November 2022, describing five interconnected towers next to Sobha Hartland in Mohammed Bin Rashid City. Since then Sobha has not published a completion date for the project on its own site.

The closest Sobha has come to a date is in July 2026, when it said it planned a record 6,819 handovers across five Dubai projects in 2026, worth about AED 21.6 billion. Sobha One was one of the five named, alongside Sobha Hartland, Sobha Hartland 2, Sobha Reserve and Verde by Sobha. No tower-by-tower date was given.

Construction progress by tower element

A construction tracker covering Sobha’s Dubai projects put Sobha One at the following stage in Q1 2026.

Element Progress, Q1 2026
Structure 97.80%
Facade 38.50%
Internal finishes 56.10%
Overall 78.51%

The tracker described this as an “advanced” stage, with progressive handovers expected within 2026. No more recent tower-level figures were found published as of September 2026.

What the portals list

Source Date Handover listed
Property Finder Accessed 28 Sep 2026 Q4 2026, completion 31 Dec 2026
Bayut Accessed 28 Sep 2026 Q4 2026
Propsearch Updated 15 Sep 2026 June 2026 (an earlier estimate)

Portal dates are estimates built from developer guidance and DLD-style registers, not a promise from Sobha. Where they disagree, the completion date in your sale and purchase agreement, the SPA, is the one that applies to your unit.

What to check before booking

  1. The completion date and grace period in your SPA for your exact tower. Sobha One has five towers of different heights, so they are unlikely to complete on the same day.
  2. Whether a Building Completion Certificate has been issued for your tower. Sobha’s Crest Grande at Sobha Hartland received its certificate in March 2026, with handovers commencing shortly after, so a certificate is the clearest sign a tower is actually ready.
  3. The DLD project status for your building through Dubai Land Department’s project status enquiry service.
  4. How many units in your tower hand over at the same time. A large batch of similar units reaching completion together can affect how quickly you can rent or resell.

Questions buyers also ask

Do property portals agree on the Sobha One handover date?

Mostly. Property Finder and Bayut both list Q4 2026, with a completion date of 31 December 2026. A Propsearch listing, last updated 15 September 2026, still shows an earlier estimate of June 2026. The completion date in your SPA is the one that applies to your unit.

How many towers does Sobha One have?

Five. Propsearch lists them at 66, 54, 36, 36 and 48 storeys. The project was launched at Cityscape Dubai in November 2022.

What has Sobha said about handovers in 2026?

In July 2026 Sobha Realty said it planned a record 6,819 handovers across five Dubai projects in 2026, worth about AED 21.6 billion. Sobha One was named as one of the five, without a specific date (Business Today Middle East, 20 Jul 2026).

What construction stage was Sobha One at in 2026?

As of Q1 2026, overall progress stood at 78.51%. The structure was 97.8% complete, the facade 38.5% complete and internal finishes 56.1% complete.

Sources

  1. Property Finder, Sobha One project page (opens in a new tab)propertyfinder.ae · accessed 28 Sep 2026
  2. Propsearch, Sobha One (opens in a new tab)propsearch.ae · updated 15 Sep 2026