When will Sobha One be handed over?
Short answer
Sobha has not published one handover date for Sobha One's five towers. Property Finder and Bayut list Q4 2026, with a completion date of 31 December 2026, but an earlier Propsearch estimate showed June 2026. Sobha itself has said only that Sobha One is part of its record 6,819-unit handover programme for 2026, without giving a specific date (Business Today Middle East, 20 Jul 2026). Construction was 86.21% complete at the DLD inspection on 24 August 2026, up from 78.51% overall in Q1 2026, when the structure was 97.8% done, so check the completion date for your tower in your SPA.
Overall construction, Q1 2026
78.51%
Construction tracker via topluxuryproperty.com
Structure complete, Q1 2026
97.8%
Construction tracker via topluxuryproperty.com
Handover listed by portals
Q4 2026
31 Dec 2026. Property Finder, Bayut
Sobha's 2026 handover programme
6,819 units
Across 5 projects including Sobha One
What Sobha has said
Sobha Realty launched Sobha One at Cityscape Dubai in November 2022, describing five interconnected towers next to Sobha Hartland in Mohammed Bin Rashid City. Since then Sobha has not published a completion date for the project on its own site.
The closest Sobha has come to a date is in July 2026, when it said it planned a record 6,819 handovers across five Dubai projects in 2026, worth about AED 21.6 billion. Sobha One was one of the five named, alongside Sobha Hartland, Sobha Hartland 2, Sobha Reserve and Verde by Sobha. No tower-by-tower date was given.
Construction progress by tower element
A construction tracker covering Sobha’s Dubai projects put Sobha One at the following stage in Q1 2026.
| Element | Progress, Q1 2026 |
|---|---|
| Structure | 97.80% |
| Facade | 38.50% |
| Internal finishes | 56.10% |
| Overall | 78.51% |
The tracker described this as an “advanced” stage, with progressive handovers expected within 2026. No more recent tower-level figures were found published as of September 2026.
What the portals list
| Source | Date | Handover listed |
|---|---|---|
| Property Finder | Accessed 28 Sep 2026 | Q4 2026, completion 31 Dec 2026 |
| Bayut | Accessed 28 Sep 2026 | Q4 2026 |
| Propsearch | Updated 15 Sep 2026 | June 2026 (an earlier estimate) |
Portal dates are estimates built from developer guidance and DLD-style registers, not a promise from Sobha. Where they disagree, the completion date in your sale and purchase agreement, the SPA, is the one that applies to your unit.
Sobha One: construction pace and Sobha's delivery record
Figures from DLD inspections in the fact record for Sobha One. Finish dates below are our calculation at the pace recorded so far: arithmetic on the inspection figures, not a forecast and not the developer's view. How it is worked out.
Conclusion: At about 2.6 points a month, Sobha One would reach 100% around January 2027 (our calculation at the pace recorded so far). There is no registered completion date on record to compare it with.
DLD inspections on record: 4.88% on 13 Feb 2024; 17.31% on 25 Jul 2024; 25.55% on 4 Nov 2024; 32.76% on 10 Feb 2025; 41.13% on 19 May 2025; 58.44% on 9 Oct 2025; 67.14% on 9 Feb 2026; 80.1% on 18 May 2026; 86.21% on 24 Aug 2026.
Sobha delivery record from DLD data
None of the 16 Sobha projects we track from DLD data had passed its registered completion date unfinished, against 177 of 1,294 projects (14%) across all developers. Data as at 22 October 2026. All developers compared.
Register changes we recorded
No change to the registered completion date since 13 October 2026, the earliest date in our records.
Questions buyers also ask
Do property portals agree on the Sobha One handover date?
Mostly. Property Finder and Bayut both list Q4 2026, with a completion date of 31 December 2026. A Propsearch listing, last updated 15 September 2026, still shows an earlier estimate of June 2026. The completion date in your SPA is the one that applies to your unit.
How many towers does Sobha One have?
Five. Propsearch lists them at 66, 54, 36, 36 and 48 storeys. The project was launched at Cityscape Dubai in November 2022.
What has Sobha said about handovers in 2026?
In July 2026 Sobha Realty said it planned a record 6,819 handovers across five Dubai projects in 2026, worth about AED 21.6 billion. Sobha One was named as one of the five, without a specific date (Business Today Middle East, 20 Jul 2026).
What construction stage was Sobha One at in 2026?
As of Q1 2026, overall progress stood at 78.51%. The structure was 97.8% complete, the facade 38.5% complete and internal finishes 56.1% complete.