Illustration: construction cranes on a residential tower at dusk
Updated 12 October 2026

Developers

Meraas new projects and handover dates

Meraas new projects in Dubai: 7 projects, 4 under construction, 1 partly handed over, 1 off-plan, 1 handed over. Each row gives the latest Dubai Land Department (DLD) construction figure and the handover date, with a link to prices, payment plan and the handover date history.

Newest Meraas projects: launched or early construction

3 Meraas projects are off-plan or less than 15% built at the last DLD inspection.

All Meraas projects in Dubai: construction progress and handover dates

ProjectAreaStatusConstruction (DLD)Handover date
Bulgari Lighthouse
Bulgari Lighthouse handover date
Jumeirah Bay Islandunder construction63.61% complete (DLD inspection, 9 Jul 2026)DLD registered completion date 27 Mar 2027; Propsearch estimate Q2 2027; not published by Meraas
City Walk Crestlane
City Walk Crestlane handover date
City Walk, Al Waslunder constructionCrestlane 2 at 6.83% (DLD inspection, 8 Oct 2026); Crestlane 3 at 4.59% (15 Sep 2026); Crestlane 4 and 5 at 0.01% (12 Jun 2026)DLD registered completion 10 Dec 2028 (Crestlane 2 and 3), 30 Sep 2029 (Crestlane), 25 Apr 2030 (Crestlane 4 and 5)
Jumeirah Asora Bay
Jumeirah Asora Bay handover date
La Mer, Jumeirahunder construction4.4% complete (DLD inspection, 12 Aug 2026)Q1 2029 (registered completion date 31 March 2029)
The Acres
The Acres handover date
Dubailandunder constructionPhase 1 25.15% (DLD inspection, 20 Aug 2026); The Acres 3 and Estates 14.87% (DLD, 30 Sep 2026); The Acres 2 and Estates 2 3.66% (DLD, 25 Jun 2026)Phase 1 Q4 2027 (Meraas target, no DLD date on file); The Acres 3 and Estates 19 Nov 2027; The Acres 2 and Estates 2 3 May 2028 (DLD registered completion dates)
Nad Al Sheba Gardens
Nad Al Sheba Gardens handover date
Nad Al Shebapartly handed overPhase 3 97.03% complete (DLD inspection, 30 Jul 2026)Phase 3 registered for 19 Apr 2026, overdue; Phase 7 registered for 15 Feb 2028 (Property Finder: 31 Aug 2028); last phase 1 Aug 2029
The Edit at d3
The Edit at d3 handover date
Dubai Design District (d3)off-plan0.24% complete (DLD inspection, 19 Aug 2026)DLD registered completion 31 Jan 2030; Meraas estimates June to August 2030
Cherrywoods
Cherrywoods handover date
Dubailand (Al Qudra Road)handed overCompleted, 100% (DLD inspection, 10 Oct 2023)Completed, sources give May 2022 or September 2023

Payments around handover

Handover dates for other developers