Vision Developments new projects in Dubai: 5 projects, 4 under construction, 1 off-plan. Each row gives the latest Dubai Land Department (DLD) construction figure and the handover date, with a link to prices, payment plan and the handover date history.
Newest Vision projects: launched or early construction
3 Vision projects are off-plan or less than 15% built at the last DLD inspection.
- Verde by Vision: handover Registered completion 30 Sep 2027 (DLD); marketed as Q2 2027 at launch
- Vista by Vision: handover Registered completion 1 Sep 2027 (DLD); Q3 2027 (developer)
- Sera Gardens by Vision: handover Registered completion 1 Apr 2028 (DLD); Q4 2027 in early marketing
All Vision projects in Dubai: construction progress and handover dates
| Project | Area | Status | Construction (DLD) | Handover date |
|---|---|---|---|---|
| Reem by Vision Reem by Vision handover date | Liwan, Dubailand | under construction | 53.14% complete (DLD inspection, 23 Jul 2026) | Q4 2026 (Vision Developments); DLD registered completion date 31 Dec 2026 |
| Soul by Vision Soul by Vision handover date | Dubai Production City (IMPZ) | under construction | 62.05% complete (DLD inspection, 17 Jul 2026) | Registered completion 31 Dec 2026 (DLD); Q4 2026 at launch |
| Verde by Vision Verde by Vision handover date | Dubai Sports City | under construction | 1.59% complete (DLD inspection, 14 Apr 2026) | Registered completion 30 Sep 2027 (DLD); marketed as Q2 2027 at launch |
| Vista by Vision Vista by Vision handover date | Dubai Production City (IMPZ) | under construction | 3.38% complete (DLD inspection, 14 May 2026) | Registered completion 1 Sep 2027 (DLD); Q3 2027 (developer) |
| Sera Gardens by Vision Sera Gardens by Vision handover date | Dubai Production City | off-plan | 0% at the last DLD inspection (7 Apr 2026); registered construction start 1 Aug 2026 | Registered completion 1 Apr 2028 (DLD); Q4 2027 in early marketing |