When is the Soul by Vision handover date?
Short answer
Soul by Vision has a registered completion date of 31 December 2026, matching the Q4 2026 handover Vision Developments gave at launch in May 2025. The last DLD inspection, on 17 July 2026, recorded the building 62.05% complete, up from 41.2% in April. About 38% of the work remained with five and a half months to go, so the next inspection will show whether the date holds.
Registered completion date (DLD)
31 Dec 2026
DLD register via Continental Club
Latest construction progress
62.05%
DLD inspection, 17 Jul 2026
Developer's stated date
Q4 2026
Vision Developments, 13 May 2025
Portal date
31 Dec 2026
Property Finder, accessed 11 Oct 2026
Soul by Vision handover date: the latest position
Soul by Vision is registered with the Dubai Land Department (DLD) for completion on 31 December 2026. Vision Developments gave a Q4 2026 handover when it launched the building on 13 May 2025, and Property Finder and Propsearch show the same date. Full project details are on the Soul by Vision page.
The building was 62.05% complete at the DLD inspection on 17 July 2026, the latest recorded when the register was updated on 4 October 2026. That left about 38% of the work for the five and a half months to the registered date.
Soul by Vision handover date by building
Soul by Vision is a single 11 storey building of 176 apartments, registered as DLD project 3680 under the name Soul By Vision, in the Me’aisem First district.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Soul by Vision | 62.05% (17 Jul 2026) | 31 Dec 2026 | Q4 2026 (Vision Developments); 31 Dec 2026 (Property Finder) |
How the Soul by Vision handover date has changed
| Date | What happened | Source |
|---|---|---|
| 16 Apr 2025 | First DLD inspection, 0% | DLD register via Dubai Data |
| 6 May 2025 | Registered with the DLD | DLD register via Dubai Data |
| 13 May 2025 | Launch, with handover by Q4 2026 and a 20/80 plan | Vision Developments |
| 31 May 2025 | Registered construction start | DLD register |
| 13 Jan 2026 | 30.2% complete | DLD register via Dubai Data |
| 17 Apr 2026 | 41.2% complete | DLD register via Dubai Data |
| 17 Jul 2026 | 62.05% complete; registered completion 31 Dec 2026 | DLD register via Continental Club |
The date has not moved. The launch promise, the registered completion date and the portal dates all point to the end of 2026. Progress picked up in 2026: about 11 percentage points from January to April, then about 21 points from April to July.
At the April to July pace, roughly 7 points a month, the remaining 38% would take about five and a half months from mid July, which lands at the end of December 2026. That is a calculation from DLD figures, not a developer forecast. Handover itself usually follows the completion certificate and utility connections, so keys can come a few weeks after the building reaches 100%.
What the Soul by Vision handover date means for payments
Soul is sold on a 20/80 plan: 20% during construction and 80% on completion (Vision Developments, 13 May 2025). Some agents show the 20% as 10% on booking and 10% during construction. Either way, 80% of the price is due at handover. For a 1 bedroom at the registered median of AED 942,000, that is about AED 754,000, due around the turn of 2026 and 2027 if the date holds.
What to check before relying on the Soul by Vision date
- The DLD inspection after 17 July 2026. A figure near 85% to 90% by October or November would match a December finish.
- The anticipated completion date and grace period in the SPA, which set when the 80% call can be made and what applies if the building runs late.
- Mortgage timing. Banks value the finished unit at handover, so a valuation below the purchase price would need to be covered in cash.
Questions buyers also ask
When will Soul by Vision be completed?
The DLD register gives 31 December 2026, and Property Finder lists the same date. Vision Developments said at launch in May 2025 that Soul would be handed over by Q4 2026.
Has the Soul by Vision handover date been delayed?
No change has been recorded. The registered completion date of 31 December 2026 sits inside the Q4 2026 handover promised at launch, and Vision Developments has not announced a new date.
How far along is Soul by Vision?
62.05% at the DLD inspection on 17 July 2026, up from 41.2% on 17 April 2026 and 30.2% on 13 January 2026 (Dubai Data; Continental Club). No later inspection had been published by 4 October 2026.
Is Soul by Vision on track for December 2026?
It is close. Progress rose by about 21 percentage points between April and July 2026. Keeping that pace would take the building to about 100% around the end of 2026, with no room for any slowdown.