Prestige One Developments new projects and handover dates

Prestige One Developments new projects in Dubai: 7 projects, 7 under construction. Each row gives the latest Dubai Land Department (DLD) construction figure and the handover date, with a link to prices, payment plan and the handover date history.

Newest Prestige One projects: launched or early construction

4 Prestige One projects are off-plan or less than 15% built at the last DLD inspection.

All Prestige One projects in Dubai: construction progress and handover dates

ProjectAreaStatusConstruction (DLD)Handover date
Berkeley Square by Prestige One
Berkeley Square by Prestige One handover date
Jumeirah Village Circle (JVC)under construction3% complete (DLD inspection, 25 Jun 2026)Registered completion date 30 Mar 2028 (DLD); Prestige One says March 2028
Golf Residences by Prestige One
Golf Residences by Prestige One handover date
Dubai Sports Cityunder construction35.74% complete (DLD inspection, 10 Aug 2026)February 2028 (Prestige One); registered completion date 16 Feb 2028 (DLD)
Luxury Canal Residences
Luxury Canal Residences handover date
Dubai Islandsunder construction17.71% complete (DLD inspection, 30 Jun 2026)Q1 2028 (Prestige One); registered completion date 30 Nov 2027 (DLD)
Parkway by Prestige One
Parkway by Prestige One handover date
Meydan Horizonunder construction10.89% complete (DLD inspection, 17 Aug 2026)Registered completion date 31 Jan 2028 (DLD); January 2028 (Prestige One)
Seaside by Prestige One
Seaside by Prestige One handover date
Dubai Islandsunder construction43.03% complete (DLD inspection, 30 Jul 2026)December 2026 (Prestige One); DLD registered completion date 25 Dec 2026
The Boulevard by Prestige One
The Boulevard by Prestige One handover date
Dubailand Residence Complex (DLRC)under construction10.57% complete (DLD inspection, 23 Sep 2026)Q1 2028 (Prestige One, via Propsearch and Continental Club); DLD registered completion date 30 Nov 2027
The One by Prestige One
The One by Prestige One handover date
Barsha Heights (TECOM)under construction7.03% complete (DLD inspection, 16 Sep 2026)June 2027 (Prestige One); DLD registered completion 30 Jun 2027