Prestige One Developments new projects in Dubai: 7 projects, 7 under construction. Each row gives the latest Dubai Land Department (DLD) construction figure and the handover date, with a link to prices, payment plan and the handover date history.
Newest Prestige One projects: launched or early construction
4 Prestige One projects are off-plan or less than 15% built at the last DLD inspection.
- Berkeley Square by Prestige One: handover Registered completion date 30 Mar 2028 (DLD); Prestige One says March 2028
- Parkway by Prestige One: handover Registered completion date 31 Jan 2028 (DLD); January 2028 (Prestige One)
- The Boulevard by Prestige One: handover Q1 2028 (Prestige One, via Propsearch and Continental Club); DLD registered completion date 30 Nov 2027
- The One by Prestige One: handover June 2027 (Prestige One); DLD registered completion 30 Jun 2027
All Prestige One projects in Dubai: construction progress and handover dates
| Project | Area | Status | Construction (DLD) | Handover date |
|---|---|---|---|---|
| Berkeley Square by Prestige One Berkeley Square by Prestige One handover date | Jumeirah Village Circle (JVC) | under construction | 3% complete (DLD inspection, 25 Jun 2026) | Registered completion date 30 Mar 2028 (DLD); Prestige One says March 2028 |
| Golf Residences by Prestige One Golf Residences by Prestige One handover date | Dubai Sports City | under construction | 35.74% complete (DLD inspection, 10 Aug 2026) | February 2028 (Prestige One); registered completion date 16 Feb 2028 (DLD) |
| Luxury Canal Residences Luxury Canal Residences handover date | Dubai Islands | under construction | 17.71% complete (DLD inspection, 30 Jun 2026) | Q1 2028 (Prestige One); registered completion date 30 Nov 2027 (DLD) |
| Parkway by Prestige One Parkway by Prestige One handover date | Meydan Horizon | under construction | 10.89% complete (DLD inspection, 17 Aug 2026) | Registered completion date 31 Jan 2028 (DLD); January 2028 (Prestige One) |
| Seaside by Prestige One Seaside by Prestige One handover date | Dubai Islands | under construction | 43.03% complete (DLD inspection, 30 Jul 2026) | December 2026 (Prestige One); DLD registered completion date 25 Dec 2026 |
| The Boulevard by Prestige One The Boulevard by Prestige One handover date | Dubailand Residence Complex (DLRC) | under construction | 10.57% complete (DLD inspection, 23 Sep 2026) | Q1 2028 (Prestige One, via Propsearch and Continental Club); DLD registered completion date 30 Nov 2027 |
| The One by Prestige One The One by Prestige One handover date | Barsha Heights (TECOM) | under construction | 7.03% complete (DLD inspection, 16 Sep 2026) | June 2027 (Prestige One); DLD registered completion 30 Jun 2027 |