Handover date

When is the Seaside by Prestige One handover date?

Updated 11 October 2026 Seaside by Prestige One

Short answer

Seaside by Prestige One has a registered completion date of 25 December 2026, and Prestige One gives a December 2026 handover. The DLD inspection on 30 July 2026 recorded 43.03% complete. Progress between April and July 2026 was about 3.2 points a month, so finishing by December would need the pace to more than treble.

Registered completion date (DLD)

25 Dec 2026

DLD project register via Continental Club

Latest construction progress

43.03%

DLD inspection, 30 Jul 2026

Developer's stated date

December 2026

Prestige One, accessed 11 Oct 2026

Progress, April to July 2026

+9.71 points

DLD inspections, 30 Apr and 30 Jul 2026

Seaside by Prestige One handover date: the latest position

Seaside by Prestige One has a registered completion date of 25 December 2026 in the DLD project register, and Prestige One gives a December 2026 handover. Prices, sizes and the payment plan are on the Seaside by Prestige One page.

The latest DLD inspection, on 30 July 2026, recorded the building 43.03% complete. That left about 57 points of work for the five months to the registered date. The previous three months had added 9.71 points.

Seaside by Prestige One handover date by building

Seaside is one residential building with 121 units, registered as DLD project number 3119 with its escrow account at ADCB.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Seaside By Prestige One 43.03%, 30 Jul 2026 25 Dec 2026 December 2026 (Prestige One); Q4 2026 (Equity Edge, ezre)

How the Seaside by Prestige One handover date has changed

Date What happened Source
2024 Project launched Prestige One
25 Jul 2024 Construction start recorded DLD register
30 Apr 2026 Inspection records about 33.3% DLD register (derived from the 30 Jul change)
30 Jul 2026 Inspection records 43.03% DLD register
11 Oct 2026 Prestige One still gives December 2026 Prestige One

The published date has not moved. The question is pace. Two years after the registered start, the building was under half complete. Continuing at the April to July 2026 rate of about 3.2 points a month, the remaining work would take until about early 2028.

Prestige One’s two 2026 completions give some reference. Vista in Dubai Sports City was estimated for 2025 and was recorded finished in the DLD register on 2 April 2026. The Residence in JVC was recorded finished on 27 March 2026 (Real Estate Club Dubai; Gulf News).

What the Seaside by Prestige One handover date means for payments

The plan is 20% on booking, 45% during construction and 35% on handover, with nothing after handover. Prestige One lists the construction share as 5% every quarter, and some agent listings show it as three payments of 15% within nine months of booking. In both versions the construction instalments run by date. For units booked in 2024 or 2025 they are largely paid already, so most buyers’ remaining payment is the 35% handover balance. A later handover moves that payment back but does not reduce it.

What to check before relying on the Seaside by Prestige One date

  1. The completion date and grace period in the SPA, and what the SPA says about delay beyond them.
  2. The next DLD inspection, which should show whether the pace has picked up since July 2026.
  3. Whether quarterly instalments are still due by date while the building is behind schedule.

Questions buyers also ask

When will Seaside by Prestige One be completed?

The DLD register holds a registered completion date of 25 December 2026, and Prestige One gives December 2026. The building was 43.03% complete on 30 July 2026.

Is Seaside by Prestige One on schedule?

The published date has not changed, but progress is behind it. About 57% of the work remained at the end of July 2026, and the building added 9.71 points in the three months before that inspection (DLD project register via Continental Club).

Has the Seaside by Prestige One handover date been delayed?

Not officially. Prestige One and the DLD register both still give December 2026 (accessed 11 Oct 2026). Construction started on 25 July 2024.

How much is due at handover at Seaside by Prestige One?

35% of the price is due on handover under the 20/45/35 plan, with nothing after it. On a unit at AED 2,550,000 that is AED 892,500 (Equity Edge).

Sources

  1. Propsearch, Vista by Prestige One (opens in a new tab)propsearch.ae · accessed 11 Oct 2026