Beyond Developments new projects and handover dates

Beyond Developments new projects in Dubai: 11 projects, 5 under construction, 6 off-plan. Each row gives the latest Dubai Land Department (DLD) construction figure and the handover date, with a link to prices, payment plan and the handover date history.

Newest Beyond projects: launched or early construction

8 Beyond projects are off-plan or less than 15% built at the last DLD inspection.

All Beyond projects in Dubai: construction progress and handover dates

ProjectAreaStatusConstruction (DLD)Handover date
Orise by Beyond
Orise by Beyond handover date
Dubai Maritime Cityunder construction8.61% complete (DLD inspection, 7 May 2026)Q1 2028 (Beyond, via Propsearch and Continental Club); DLD registered completion date 30 Nov 2027
Passo by Beyond
Passo by Beyond handover date
Palm Jumeirah (West Crescent)under construction0% complete (DLD inspection, 24 Mar 2026); excavation and shoring done (Beyond, Apr 2026)Q3 2029 (Beyond at launch); DLD registered completion date 31 Dec 2029
Saria by Beyond
Saria by Beyond handover date
Dubai Maritime Cityunder construction30.99% complete (DLD inspection, 1 Oct 2026)Q1 2028 (Beyond); DLD registered completion date 1 Oct 2027
Sensia by Beyond
Sensia by Beyond handover date
Dubai Maritime Cityunder construction17.54% complete (DLD inspection, 1 Oct 2026)Registered completion 30 Mar 2029 (DLD); Beyond states Q1 2029
The Mural by Beyond
The Mural by Beyond handover date
Dubai Maritime Cityunder construction16.64% complete (DLD inspection, 1 Oct 2026)Registered completion 10 Jul 2028 (DLD); Q2 2028 at launch; Q4 2028 (Propsearch)
31 Above by Beyond
31 Above by Beyond handover date
Dubai Maritime Cityoff-plan0.51% complete (DLD inspection, 18 Jun 2026)Q1 2029 (Beyond); registered completion date 30 Dec 2028 (DLD)
Arancia Yards by Beyond
Arancia Yards by Beyond handover date
City of Arabia, Dubailandoff-plan0% complete (DLD register via Data Dubai, data to 7 Oct 2026); construction start registered for 30 Oct 2026Q1 2029 (Beyond launch materials, 8 Jun 2026); DLD registered completion date 30 Oct 2028
Hado by Beyond
Hado by Beyond handover date
Siora, Dubai Islandsoff-plan0.01% complete (DLD inspection, 16 Jun 2026)Q3 2029 (Beyond); registered completion date 30 June 2029 (DLD)
Kanyon by Beyond
Kanyon by Beyond handover date
Dubai Maritime Cityoff-plan0% complete (DLD inspection, 27 Aug 2025); construction start registered for 30 Jun 2026Q2 2029 (Beyond, 25 Nov 2025); DLD registered completion date 30 Sep 2028
Soulever by Beyond
Soulever by Beyond handover date
Dubai Maritime Cityoff-plan0% complete (DLD inspection, 22 Sep 2025); construction start registered 30 Mar 2026Q1 2029 (Beyond); DLD registered completion date 30 Dec 2028
Talea by Beyond
Talea by Beyond handover date
Dubai Maritime Cityoff-plan0% at the last DLD inspection (24 Mar 2026); registered construction start 30 Mar 2026Registered completion 30 Jun 2028 (DLD); some listings say Q1 2029

Payments around handover

Handover dates for other developers

Request a Unit Review