Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Passo by Beyond handover date?

Updated 11 October 2026 Passo by Beyond

Short answer

Passo by Beyond has a registered completion date of 31 December 2029, a quarter later than the Q3 2029 date Beyond gave at launch in July 2025. The DLD inspection on 24 March 2026 recorded 0% complete, and Beyond reported in April 2026 that excavation and shoring were done with foundation piling next. Both towers share one DLD project and one date.

Registered completion date (DLD)

31 Dec 2029

DLD project register via Mitchells, as at 4 Oct 2026

Latest construction progress

0%

DLD inspection, 24 Mar 2026

Developer's date at launch

Q3 2029

Beyond via Gulf News, 1 Aug 2025

Portal date

December 2029

Property Finder, accessed 11 Oct 2026

Passo by Beyond handover date: the latest position

The DLD register holds a registered completion date of 31 December 2029 for Passo by Beyond. Beyond’s launch release in July 2025 gave Q3 2029. Prices, sizes and the payment plan are on the Passo by Beyond page.

The last published DLD inspection, on 24 March 2026, recorded 0% complete. Beyond’s own update on 3 April 2026 put the site at the end of excavation and shoring, with foundation piling next. More than three years of construction remained at that point.

Passo by Beyond handover date by building

Passo is registered as one DLD project, number 3886, with two G+14 towers and six G+2 villas over a shared two level basement. DLD sales are recorded against Tower A and Tower B; Beyond markets the towers as Avita and Bella.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Avita (Tower A) 0%, 24 Mar 2026 (whole project) 31 Dec 2029 Q3 2029 (Beyond at launch); Dec 2029 (Property Finder)
Bella (Tower B) 0%, 24 Mar 2026 (whole project) 31 Dec 2029 Q3 2029 (Beyond at launch); Dec 2029 (Property Finder)
Beach mansions (6 villas) 0%, 24 Mar 2026 (whole project) 31 Dec 2029 Not published separately

How the Passo by Beyond handover date has changed

Date What happened Source
28 Jul 2025 Project registered with DLD DLD register via Dubricks
31 Jul 2025 Beyond launches Passo, completion Q3 2029 Beyond; Gulf News, 1 Aug 2025
31 Dec 2025 Registered construction start DLD register via Mitchells
24 Mar 2026 Inspection records 0% DLD register via Mitchells
3 Apr 2026 Beyond reports excavation, shoring and dewatering phase 1 complete Beyond on LinkedIn
15 Jun 2026 DLD project file still lists status as not started DLD register via Keyva
4 Oct 2026 Registered completion date 31 Dec 2029 DLD register via Mitchells

The registered date sits one quarter after the launch target. Mitchells’ project brief also cites December 2029 as Beyond’s published expected completion. A DLD file dated 15 June 2026 still showed the status as not started, while the later register extract shows under construction, so registry snapshots differ by date.

What the Passo by Beyond handover date means for payments

Passo is sold on a 60/40 plan. After 10% on booking and 10% a month later, eight instalments of 5% fall due every six months from December 2025 to June 2029, by date rather than by progress. The remaining 40% is due on completion. If completion moves from Q3 2029 to the registered 31 December 2029, or later, the dated instalments do not move but the 40% payment does. On the DLD median price of AED 9.17 million, that final payment is about AED 3.67 million.

What to check before relying on the Passo by Beyond date

  1. Which date the SPA uses, Q3 2029 or 31 December 2029, and the grace period after it.
  2. The DLD inspection figure after foundation piling, since the only published inspection is from March 2026.
  3. Whether the unit is in Avita, Bella or a beach mansion, as the villas are separate structures within the same project.

Questions buyers also ask

When will Passo by Beyond be completed?

The registered completion date in the DLD project register is 31 December 2029. Beyond gave Q3 2029 at launch, and some sales sites still use that date.

How far along is construction at Passo by Beyond?

The DLD inspection on 24 March 2026 recorded 0%. On 3 April 2026 Beyond reported 88,000 cubic metres excavated, a 650 metre shoring wall, 131 secant piles and dewatering phase 1 complete, with foundation piling next.

Has the Passo by Beyond handover date been delayed?

The registered date of 31 December 2029 is one quarter later than the Q3 2029 date in Beyond's July 2025 launch release. Beyond has not announced a delay, and Property Finder shows December 2029.

Do the Avita and Bella towers hand over at the same time?

The DLD register lists Passo as one project with two buildings and one completion date. Beyond has not published separate dates for Avita and Bella.