When will Azizi Venice be handed over?
Short answer
There is no firm date yet. In October 2025 Azizi said Venice 1 to 3 would hand over in Q1 2026. By April 2026 the first 14 buildings were 39% complete and Azizi gave no dates. In September 2026 it said handovers run through 2026 and into 2027. Ask for your building's date in writing in the SPA, the sale and purchase agreement you sign with the developer.
First 14 buildings, complete
39%
Azizi, 28 Apr 2026
Most advanced building, Venice 3
74%
Azizi, 28 Apr 2026
Date given in Oct 2025 for Venice 1 to 3
Q1 2026
Azizi via MENAFN
Latest guidance
2026 into 2027
Azizi via GDN, 15 Sep 2026
Every date Azizi has given
Azizi’s guidance has moved from one specific quarter to a range that runs into 2027. Here is each date in order.
| Date | What Azizi said | Source |
|---|---|---|
| 27 Sep 2023 | At launch, the CEO said the first handovers would come “well before 2027, if possible”. | Gulf News |
| 17 Oct 2025 | Venice 1 to 3 scheduled for handover in Q1 2026. | Azizi via MENAFN |
| 28 Apr 2026 | First 14 buildings 39% complete overall. Venice 3 at 74%, Venice 1 at 64%. No handover dates given. | Azizi via Zawya |
| 15 Sep 2026 | Handovers across Azizi projects run “through 2026 and into 2027”. | Azizi via GDN |
What the numbers show
The Q1 2026 date was not met for the first buildings. Q1 2026 has passed, and in April 2026 the building furthest along, Venice 3, was 74% complete.
For you as a buyer, the date that matters is the one for your building, not the headline date for the whole community. Venice is a large community built in phases, and each building is at a different stage.
Progress by building
Azizi publishes its own construction percentages for individual buildings, most recently in April 2026. Portals such as Propsearch do not publish a construction percentage for each building, only an estimated handover date drawn from Land Department and developer data. The DLD register, as republished by Continental Club, gives inspection figures for some buildings, such as Venice 12. The table below combines both, so you can see what is confirmed and what is only an estimate.
| Building | Complete, Oct 2025 | Complete, Apr 2026 | Portal-estimated handover |
|---|---|---|---|
| Venice 1 | 54% | 64% | Dec 2025 (Propsearch, updated 9 Apr 2026) |
| Venice 2 | 46% | 57% | Dec 2025 (Propsearch, updated 3 May 2026) |
| Venice 3 | 66% | 74% | Dec 2025 (Propsearch, updated 9 Apr 2026) |
| Venice 4 | 50% | 42% to 56%* | Dec 2025 (Propsearch, updated 11 Jul 2026) |
| Venice 9 | 33% | 42% to 56%* | Not published |
| Venice 12 | 3% | Not individually reported; DLD inspection 15 Oct 2026: 21.62% | Sep 2027 (Propsearch, updated 6 Apr 2026); DLD registered completion date 25 Sep 2027 |
| Venice 13 | 29% | 42% to 56%* | Sep 2027 (Propsearch, updated 19 May 2026) |
*Azizi’s April 2026 update gave one range, not an individual figure, for these buildings. All are past their portal-estimated handover date of December 2025 except Venice 12 and Venice 13, which portals put later, in September 2027. The DLD register gives Venice 12 a registered completion date of 25 September 2027. Azizi itself has not confirmed a handover date for any of these buildings.
Azizi Venice: construction pace and Azizi's delivery record
Figures from DLD inspections in the fact record for Azizi Venice. Finish dates below are our calculation at the pace recorded so far: arithmetic on the inspection figures, not a forecast and not the developer's view. How it is worked out.
Conclusion: Of the 9 buildings or phases with a DLD reading, 3 have passed their registered completion date unfinished; 3 would finish after their registered date at the pace recorded so far; 1 is under 15% built, too early to work out a finish date from the pace; and 2 have no two DLD readings within the last 12 months, so no pace can be worked out yet.
| Building or phase | Last DLD reading | Pace (points a month) | Registered completion | At the pace recorded so far |
|---|---|---|---|---|
| Venice 3 | 76.04% (15 Jun 2026) | 1.1 | 30 Dec 2025 (passed) | date passed |
| Azizi Venice 6 | 11.58% (8 May 2026) | 0.7 | 31 Dec 2027 | too early (11.58% built) |
| Azizi Venice 7 | 29.19% (22 Jun 2026) | 1.6 | 28 Jan 2026 (passed) | date passed |
| Azizi Venice 11 | 25.92% (9 Sep 2026) | 1.9 | 30 Aug 2027 | Dec 2029, 28 months after |
| Azizi Venice 12 | 21.62% (15 Oct 2026) | 1.1 | 25 Sep 2027 | Sep 2032, 60 months after |
| Azizi Venice 13 | 45.87% (14 Oct 2026) | 1.9 | 16 Sep 2027 | Mar 2029, 18 months after |
| Azizi Venice 14 | 30.29% (22 Jun 2026) | 1.8 | 30 May 2026 (passed) | date passed |
| Azizi Venice 15 | 0% (6 May 2025) | one reading | 30 May 2027 | needs 4.0 a month |
| Azizi Venice 16 | 0% (3 Jun 2025) | one reading | 2 Jun 2027 | needs 4.2 a month |
Azizi delivery record from DLD data
6 of the 48 Azizi projects we track from DLD data (13%) had passed their registered completion date unfinished, by a median of 10 months, against 177 of 1,294 projects (14%) across all developers. Data as at 22 October 2026. All developers compared.
Register changes we recorded
No change to the registered completion date of any building since 13 October 2026, the earliest date in our records.
Questions buyers also ask
Do property portals agree on the Azizi Venice handover date?
No. Property Finder and Bayut listings show Q4 2026. Propsearch shows December 2025 for Venice 1 to 4 and September 2027 for Venice 12 and 13. Azizi's own update in April 2026 gave no date. The date in the SPA for your building is the one that counts.
What happens if an off-plan project in Dubai is delayed?
Your SPA sets the completion date and any grace period, which is extra time the contract allows after that date. DLD publishes construction progress for registered projects through its project status enquiry service. Check both before you pay the next instalment.
How many homes has Azizi delivered?
Azizi says it has delivered more than 45,000 homes. It reports 7 projects handed over in 2026, with 10 more targeted by the end of the year, and more than 150,000 units under construction (GDN, 15 Sep 2026).
Is Azizi Venice sold out?
No, not as a whole. In March 2024 Azizi said several buildings were between 75% and 97% sold, with new units still being released (Azizi, 18 Mar 2024). Property Finder still listed properties for sale in Azizi Venice as of 28 Sep 2026, mostly resales rather than new developer stock.
How many units are there in Azizi Venice?
Sources disagree. At launch in 2023, Azizi described more than 30,000 residential units across about 100 apartment buildings, plus over 400 villas and mansions (Azizi, 18 Mar 2024 sales update). Bayut's area guide gives a lower count of 15,057 apartments and 400 villas across 100 buildings (Bayut, accessed 28 Sep 2026). Azizi has not published a single reconciled total.
What is the current status of construction at Azizi Venice?
The first 14 buildings were 39% complete overall as of 28 April 2026, Azizi's last published figure (Zawya, 28 Apr 2026). In August 2026 Azizi moved Azizi Venice to 24/7 construction to keep to its schedule (Azizi via Middle East Construction News, 18 Aug 2026). No newer overall percentage has been published since.