Handover date

When will Azizi Venice be handed over?

Azizi Venice

How this page was made: figures from the DLD project register and the developer and portal pages listed under Sources, as at 28 October 2026. Text drafted with AI assistance from those sources. Every figure matched the fact records at the build on 12 November 2026. Not yet reviewed line by line by a person. How facts are checked

Short answer

There is no firm date yet. In October 2025 Azizi said Venice 1 to 3 would hand over in Q1 2026. By April 2026 the first 14 buildings were 39% complete and Azizi gave no dates. In September 2026 it said handovers run through 2026 and into 2027. Ask for your building's date in writing in the SPA, the sale and purchase agreement you sign with the developer.

First 14 buildings, complete

39%

Azizi, 28 Apr 2026

Most advanced building, Venice 3

74%

Azizi, 28 Apr 2026

Date given in Oct 2025 for Venice 1 to 3

Q1 2026

Azizi via MENAFN

Latest guidance

2026 into 2027

Azizi via GDN, 15 Sep 2026

Every date Azizi has given

Azizi’s guidance has moved from one specific quarter to a range that runs into 2027. Here is each date in order.

Date What Azizi said Source
27 Sep 2023 At launch, the CEO said the first handovers would come “well before 2027, if possible”. Gulf News
17 Oct 2025 Venice 1 to 3 scheduled for handover in Q1 2026. Azizi via MENAFN
28 Apr 2026 First 14 buildings 39% complete overall. Venice 3 at 74%, Venice 1 at 64%. No handover dates given. Azizi via Zawya
15 Sep 2026 Handovers across Azizi projects run “through 2026 and into 2027”. Azizi via GDN

What the numbers show

The Q1 2026 date was not met for the first buildings. Q1 2026 has passed, and in April 2026 the building furthest along, Venice 3, was 74% complete.

For you as a buyer, the date that matters is the one for your building, not the headline date for the whole community. Venice is a large community built in phases, and each building is at a different stage.

Progress by building

Azizi publishes its own construction percentages for individual buildings, most recently in April 2026. Portals such as Propsearch do not publish a construction percentage for each building, only an estimated handover date drawn from Land Department and developer data. The DLD register, as republished by Continental Club, gives inspection figures for some buildings, such as Venice 12. The table below combines both, so you can see what is confirmed and what is only an estimate.

Building Complete, Oct 2025 Complete, Apr 2026 Portal-estimated handover
Venice 1 54% 64% Dec 2025 (Propsearch, updated 9 Apr 2026)
Venice 2 46% 57% Dec 2025 (Propsearch, updated 3 May 2026)
Venice 3 66% 74% Dec 2025 (Propsearch, updated 9 Apr 2026)
Venice 4 50% 42% to 56%* Dec 2025 (Propsearch, updated 11 Jul 2026)
Venice 9 33% 42% to 56%* Not published
Venice 12 3% Not individually reported; DLD inspection 15 Oct 2026: 21.62% Sep 2027 (Propsearch, updated 6 Apr 2026); DLD registered completion date 25 Sep 2027
Venice 13 29% 42% to 56%* Sep 2027 (Propsearch, updated 19 May 2026)

*Azizi’s April 2026 update gave one range, not an individual figure, for these buildings. All are past their portal-estimated handover date of December 2025 except Venice 12 and Venice 13, which portals put later, in September 2027. The DLD register gives Venice 12 a registered completion date of 25 September 2027. Azizi itself has not confirmed a handover date for any of these buildings.

Azizi Venice: construction pace and Azizi's delivery record

Figures from DLD inspections in the fact record for Azizi Venice. Finish dates below are our calculation at the pace recorded so far: arithmetic on the inspection figures, not a forecast and not the developer's view. How it is worked out.

Conclusion: Of the 9 buildings or phases with a DLD reading, 3 have passed their registered completion date unfinished; 3 would finish after their registered date at the pace recorded so far; 1 is under 15% built, too early to work out a finish date from the pace; and 2 have no two DLD readings within the last 12 months, so no pace can be worked out yet.

Building or phaseLast DLD readingPace (points a month)Registered completionAt the pace recorded so far
Venice 376.04% (15 Jun 2026)1.130 Dec 2025 (passed)date passed
Azizi Venice 611.58% (8 May 2026)0.731 Dec 2027too early (11.58% built)
Azizi Venice 729.19% (22 Jun 2026)1.628 Jan 2026 (passed)date passed
Azizi Venice 1125.92% (9 Sep 2026)1.930 Aug 2027Dec 2029, 28 months after
Azizi Venice 1221.62% (15 Oct 2026)1.125 Sep 2027Sep 2032, 60 months after
Azizi Venice 1345.87% (14 Oct 2026)1.916 Sep 2027Mar 2029, 18 months after
Azizi Venice 1430.29% (22 Jun 2026)1.830 May 2026 (passed)date passed
Azizi Venice 150% (6 May 2025)one reading30 May 2027needs 4.0 a month
Azizi Venice 160% (3 Jun 2025)one reading2 Jun 2027needs 4.2 a month

Azizi delivery record from DLD data

6 of the 48 Azizi projects we track from DLD data (13%) had passed their registered completion date unfinished, by a median of 10 months, against 177 of 1,294 projects (14%) across all developers. Data as at 22 October 2026. All developers compared.

Register changes we recorded

No change to the registered completion date of any building since 13 October 2026, the earliest date in our records.

Register change log · Handover calendar

Questions buyers also ask

Do property portals agree on the Azizi Venice handover date?

No. Property Finder and Bayut listings show Q4 2026. Propsearch shows December 2025 for Venice 1 to 4 and September 2027 for Venice 12 and 13. Azizi's own update in April 2026 gave no date. The date in the SPA for your building is the one that counts.

What happens if an off-plan project in Dubai is delayed?

Your SPA sets the completion date and any grace period, which is extra time the contract allows after that date. DLD publishes construction progress for registered projects through its project status enquiry service. Check both before you pay the next instalment.

How many homes has Azizi delivered?

Azizi says it has delivered more than 45,000 homes. It reports 7 projects handed over in 2026, with 10 more targeted by the end of the year, and more than 150,000 units under construction (GDN, 15 Sep 2026).

Is Azizi Venice sold out?

No, not as a whole. In March 2024 Azizi said several buildings were between 75% and 97% sold, with new units still being released (Azizi, 18 Mar 2024). Property Finder still listed properties for sale in Azizi Venice as of 28 Sep 2026, mostly resales rather than new developer stock.

How many units are there in Azizi Venice?

Sources disagree. At launch in 2023, Azizi described more than 30,000 residential units across about 100 apartment buildings, plus over 400 villas and mansions (Azizi, 18 Mar 2024 sales update). Bayut's area guide gives a lower count of 15,057 apartments and 400 villas across 100 buildings (Bayut, accessed 28 Sep 2026). Azizi has not published a single reconciled total.

What is the current status of construction at Azizi Venice?

The first 14 buildings were 39% complete overall as of 28 April 2026, Azizi's last published figure (Zawya, 28 Apr 2026). In August 2026 Azizi moved Azizi Venice to 24/7 construction to keep to its schedule (Azizi via Middle East Construction News, 18 Aug 2026). No newer overall percentage has been published since.

Sources

  1. Propsearch.ae, Azizi Venice 1 (opens in a new tab)propsearch.ae · updated 9 Apr 2026, accessed 28 Sep 2026
  2. Propsearch.ae, Azizi Venice 2 (opens in a new tab)propsearch.ae · updated 3 May 2026, accessed 28 Sep 2026
  3. Propsearch.ae, Azizi Venice 3 (opens in a new tab)propsearch.ae · updated 9 Apr 2026, accessed 28 Sep 2026
  4. Propsearch.ae, Azizi Venice 9 (opens in a new tab)propsearch.ae · updated 9 Apr 2026, accessed 28 Sep 2026
  5. Propsearch.ae, Azizi Venice 12 (opens in a new tab)propsearch.ae · updated 6 Apr 2026, accessed 28 Sep 2026
  6. Propsearch.ae, Azizi Venice 13 (opens in a new tab)propsearch.ae · updated 19 May 2026, accessed 28 Sep 2026