DAMAC Properties new projects and handover dates

DAMAC Properties new projects in Dubai: 29 projects, 18 under construction, 3 partly handed over, 5 off-plan, 3 handed over. Each row gives the latest Dubai Land Department (DLD) construction figure and the handover date, with a link to prices, payment plan and the handover date history.

Newest DAMAC projects: launched or early construction

10 DAMAC projects are off-plan or less than 15% built at the last DLD inspection.

All DAMAC projects in Dubai: construction progress and handover dates

ProjectAreaStatusConstruction (DLD)Handover date
Cavalli Tower
Cavalli Tower handover date
Dubai Media City (Al Sufouh)under construction85.08% complete (DLD inspection, 15 Jul 2026)Q2 2027 (DAMAC); DLD registered completion date 30 Sep 2025, passed
DAMAC Bay by Cavalli
DAMAC Bay by Cavalli handover date
Dubai Harbourunder construction33.76% complete (DLD inspection, 18 Aug 2026)Q3 2027 (DAMAC); DLD registered completion date 15 Jan 2027
DAMAC Casa
DAMAC Casa handover date
Al Sufouh 2, Dubai Media Cityunder construction33.55% complete (DLD inspection, 18 Aug 2026)Q2 2028 (DAMAC project page); unit listings show Q4 2028
DAMAC District
DAMAC District handover date
DAMAC Hillsunder construction4.07% complete (DLD inspection, 22 Sep 2026)Q3 2029 (DAMAC, via Bayut); DLD registered completion date 30 Mar 2029
DAMAC Lagoon Views
DAMAC Lagoon Views handover date
DAMAC Lagoons, Dubailandunder construction5.96% to 55.58% by phase (DLD inspections, May to Sep 2026)DAMAC gives Q2 2027; DLD-based dates run from 31 Mar 2027 to 31 Dec 2027 by phase
DAMAC Lagoons AndaluciaDAMAC Lagoons, Dubailandunder constructionLagoon Views 1 at 55.58% (DLD, 15 May 2026)Launch brochure gave January 2027; DAMAC now gives Q2 2027 for Lagoon Views
DAMAC Lagoons IbizaDAMAC Lagoons, Dubailandunder construction74.86% complete (DLD inspection, 10 Jul 2026)Registered for 31 Dec 2025; DLD records now show 30 Jun 2027
DAMAC Lagoons MarbellaDAMAC Lagoons, Dubailandunder construction87.32% complete (DLD inspection, 30 Sep 2026)Registered for 31 Dec 2025; portals said Q2 2026; no new date published
DAMAC Lagoons Monte CarloDAMAC Lagoons, Dubailandunder construction86.38% complete (DLD inspection, 9 Jul 2026)Registered for 31 Dec 2025; DLD records now show 31 Dec 2026
DAMAC Lagoons MoroccoDAMAC Lagoons, Dubailandunder constructionMorocco 1 76.94%, Morocco 2 65.34% (DLD inspections, 17 Jul 2026)Portals say Q4 2026; DLD records show 30 Apr 2027 (Morocco 1) and 31 Oct 2027 (Morocco 2)
DAMAC Lagoons MykonosDAMAC Lagoons, Dubailandunder construction81.06% complete (DLD inspection, 30 Sep 2026)Registered for 31 Dec 2025; DLD records now show 28 Feb 2027
DAMAC Lagoons NiceDAMAC Lagoons, Dubailandunder constructionNice 1 at 93.71% (DLD, 10 Aug 2026); Nice 2 at 83.88% (DLD, 17 Aug 2026)Registered date 29 Jul 2025 has passed; broker listings give Q3 to Q4 2026
DAMAC Lagoons Valencia
DAMAC Lagoons Valencia handover date
DAMAC Lagoons, Dubailandunder construction5.21% complete (DLD inspection, 20 May 2026)DAMAC gives Q1 2029 (Q3 2029 on its project banner); DLD registered completion 28 Feb 2028
DAMAC Lagoons VeniceDAMAC Lagoons, Dubailandunder construction74.43% complete (DLD inspection, 17 Jul 2026)Registered date 29 Sep 2025 has passed; portals give Q2 to Q3 2027
DAMAC Riverside
DAMAC Riverside handover date
Dubai Investments Parkunder constructionVillas 5.46% to 41.69%, apartments 8.18% to 21.17% complete (DLD inspections Apr to Sep 2026; register as at 4 Oct 2026)Registered: Ivy, Lush, Sage 31 Dec 2027; Olive 30 Jun 2028; apartments 31 May 2028 to 31 Mar 2029 (DLD)
DAMAC Seacrest
DAMAC Seacrest handover date
Dubai Maritime Cityunder construction5.19% complete (DLD inspection, 7 Aug 2026)Registered completion date 31 Dec 2029; DAMAC gives December 2029
DAMAC Sun City
DAMAC Sun City handover date
Dubailandunder construction36.54% complete (DLD inspection, 24 Sep 2026)Due March 2028 (DLD registered completion date 30 Mar 2028)
Safa Two by de GRISOGONO
Safa Two by de GRISOGONO handover date
Business Bayunder construction31.35% complete (DLD inspection, 12 Apr 2026)30 Dec 2027 (DLD registered completion date)
DAMAC Hills 2
DAMAC Hills 2 handover date
Dubailandpartly handed overRemaining clusters 6.36% to 95.19% complete (DLD inspections, Apr to Sep 2026)Established clusters complete; remaining clusters registered for 27 Feb 2027 to 30 Aug 2027; Violet's Jan 2026 registered date has passed
DAMAC Lagoons
DAMAC Lagoons handover date
Dubailandpartly handed overInfrastructure over 80% complete (DAMAC, Sep 2026)Clusters from Nov 2025, about 6,300 more homes due in 2026
DAMAC Lagoons PortofinoDAMAC Lagoons, Dubailandpartly handed over97.14% complete (DLD inspection, 16 Jul 2026)Registered date 29 Jun 2025 has passed; not yet recorded finished on the DLD register
Cetara at DAMAC Lagoons
Cetara at DAMAC Lagoons handover date
DAMAC Lagoons (Lagoon Views), Dubailandoff-plan0.25% complete (DLD inspection, 8 Sep 2026)31 Jan 2030 (DLD registered completion date); marketed as Q1 2030
DAMAC Islands
DAMAC Islands handover date
Dubailandoff-planClusters 3% to 14% complete (DLD, May to Jul 2026)Phase 1 due Q4 2028 (registered 31 Dec 2028 for Maldives); DAMAC Islands 2 due Q2 2030
DAMAC Islands 2
DAMAC Islands 2 handover date
Dubailandoff-plan0.32% at Antigua 1 (DLD inspection, 16 Sep 2026)DLD registered completion dates 30 Jun 2030 (nine clusters) and 31 Dec 2030 (Antigua 1)
Ivory at DAMAC Hills
Ivory at DAMAC Hills handover date
DAMAC Hillsoff-plan0.56% complete (DLD inspection, 29 Jun 2026)June 2028 (DAMAC and Property Finder); registered completion date 30 Jun 2028 (DLD)
Lilac at DAMAC Hills
Lilac at DAMAC Hills handover date
DAMAC Hills, Dubailandoff-plan0% complete (DLD inspection, 24 Apr 2026)Registered completion date 31 Jan 2030 (DLD); Q1 2030 on broker pages
DAMAC Lagoons Costa BravaDAMAC Lagoons, Dubailandhanded overBoth phases finished on the DLD register, the last on 4 Aug 2026Costa Brava 1 finished 10 Apr 2026, Costa Brava 2 on 4 Aug 2026 (DLD)
DAMAC Lagoons MaltaDAMAC Lagoons, Dubailandhanded overBoth phases finished on the DLD register, the last on 19 Jun 2026Malta 2 finished 8 Apr 2026, Malta 1 on 19 Jun 2026 (DLD)
DAMAC Lagoons SantoriniDAMAC Lagoons, Dubailandhanded overAll three phases finished on the DLD register, the last on 9 Apr 2026Handovers began Nov 2025; Santorini 2 finished 11 Feb 2026, Santorini 3 on 9 Apr 2026 (DLD)

Payments around handover