Handover date

When is the DAMAC Islands 2 handover date?

Updated 1 October 2026 DAMAC Islands 2

Short answer

DAMAC Islands 2 has a registered completion date of 30 June 2030 for nine of its ten clusters and 31 December 2030 for Antigua 1, in line with DAMAC's own Q2 2030 target for the community (DLD register via Cresco Real Estate and Dubai Handover; DAMAC, 14 Nov 2025). The latest DLD inspection, of Antigua 1 on 16 September 2026, recorded 0.32% complete, and the other nine clusters were between 0.18% and 0.33% at inspections in May and June 2026. Antigua 1 is registered six months later than the rest, so the cluster a unit sits in decides which date applies.

Registered completion date (DLD), nine clusters

30 Jun 2030

DLD register via Cresco and Dubai Handover, Sep 2026

Latest construction progress, Antigua 1

0.32%

DLD inspection, 16 Sep 2026

DAMAC's stated handover

Q2 2030

DAMAC Islands 2 guide, 14 Nov 2025

Antigua 1, registered completion date

31 Dec 2030

Six months after the other nine clusters

DAMAC Islands 2 handover date: the latest position

DAMAC Islands 2 is registered for completion on 30 June 2030 for nine of its ten clusters, and on 31 December 2030 for Antigua 1. DAMAC’s own guide, published the day after the 13 November 2025 launch, gives Q2 2030, which matches the registered date for the first nine. More on the community: DAMAC Islands 2.

Construction has barely started. The most recent DLD inspection, of Antigua 1 on 16 September 2026, recorded 0.32% complete. The other nine clusters were between 0.18% and 0.33% at their last inspections in May and June 2026.

DAMAC Islands 2 handover date by cluster

DAMAC markets eight island themes. The DLD register holds ten clusters with 4,659 villas and townhouses, all filed by DAMAC Prime Development.

Cluster (homes) Construction progress (DLD, date) Registered completion date Developer or portal date
Bahamas 1 (544) 0.33%, 14 May 2026 30 Jun 2030 Q2 2030 (DAMAC)
Bahamas 2 (666) 0.33%, 14 May 2026 30 Jun 2030 Q2 2030 (DAMAC)
Tahiti 1 (306) 0.32%, 2 Jun 2026 30 Jun 2030 Q2 2030 (DAMAC)
Tahiti 2 (484) 0.32%, 2 Jun 2026 30 Jun 2030 Q2 2030 (DAMAC)
Bermuda (469) 0.22%, 10 Jun 2026 30 Jun 2030 Q2 2030 (DAMAC)
Cuba (544) 0.18%, 10 Jun 2026 30 Jun 2030 Q2 2030 (DAMAC)
Maui (434) 0.18%, 10 Jun 2026 30 Jun 2030 Q2 2030 (DAMAC)
Barbados 1 (382) 0.18%, 10 Jun 2026 30 Jun 2030 Q2 2030 (DAMAC)
Barbados 2 (362) 0.18%, 10 Jun 2026 30 Jun 2030 Q2 2030 (DAMAC)
Antigua 1 (468) 0.32%, 16 Sep 2026 31 Dec 2030 Jun 2030 (DAMAC Antigua guide)

Progress figures and home counts are from the DLD register via Mitchells Commercial Realty; Dubai Handover rounds the same inspections to 0.2% and 0.3%. Completion dates are from Cresco Real Estate and Dubai Handover. DAMAC also markets a Mauritius cluster, which Cresco did not find on the register as of September 2026.

How the DAMAC Islands 2 handover date has changed

Date What happened Source
13 Nov 2025 Launch, from AED 2.7 million. DAMAC via ANI News
14 Nov 2025 DAMAC’s guide gives handover in Q2 2030. DAMAC
28 Feb 2026 Antigua cluster released. Zeyad Eid
2 May 2026 Registered construction start for nine clusters, completion 30 June 2030. DLD register via Mitchells, Cresco
14 May to 10 Jun 2026 First DLD inspections: 0.18% to 0.33%. DLD register via Mitchells
15 Jul 2026 Antigua 1 registered start, completion 31 December 2030. DLD register via Dubai Handover
16 Sep 2026 Antigua 1 at 0.32%. DLD register via Mitchells

No registered date has moved since the clusters were filed. Antigua 1’s later date reflects its later registration, not a revision. DAMAC’s Antigua guide still states June 2030 for that cluster, six months earlier than the register.

What the DAMAC Islands 2 handover date means for payments

DAMAC’s Antigua guide lists 20% at booking, 55% during construction and 25% on handover, and earlier DAMAC material for the same cluster described 75% during construction and 25% on handover. Under either version, 25% falls due at handover in 2030. On a townhouse listed from AED 2.99 million, that is about AED 747,500. With construction under 1% in 2026, most of the construction instalments fall during the four years of building.

What to check before relying on the DAMAC Islands 2 date

  1. Which registered cluster the unit is in. Antigua 1 is filed for 31 December 2030, six months after the other nine, and Bahamas, Barbados and Tahiti are each split into two registered clusters.
  2. The date in the SPA against the register. For Antigua, DAMAC’s guide says June 2030 while the register says 31 December 2030.
  3. Whether instalments follow dates or construction stages. With nine clusters last inspected in May and June 2026, check the latest figure through DLD’s project status enquiry before each payment.
  4. Whether the unit is in DAMAC Islands or DAMAC Islands 2. Sub-phases of the original community, such as Bora Bora Phase 2, carry a Q4 2028 date, not 2030.

Questions buyers also ask

What is the DAMAC Islands 2 handover date?

The DLD register gives 30 June 2030 for Bahamas 1 and 2, Barbados 1 and 2, Bermuda, Cuba, Maui and Tahiti 1 and 2, and 31 December 2030 for Antigua 1 (Cresco Real Estate and Dubai Handover, September 2026). DAMAC's own guide gives Q2 2030.

What is the DAMAC Islands phase 2 handover date?

DAMAC Islands phase 2 usually means DAMAC Islands 2, the community launched on 13 November 2025, which is registered for 30 June 2030 (31 December 2030 for Antigua 1). Sub-phases inside the original DAMAC Islands, such as Bora Bora Phase 2 or Bali Phase 2, are different projects with a Q4 2028 date on Property Finder.

When will the Antigua cluster at DAMAC Islands 2 be ready?

Antigua 1 has a registered completion date of 31 December 2030, the latest of the ten clusters. Its registered construction start was 15 July 2026, and it was 0.32% complete at the DLD inspection of 16 September 2026. DAMAC's Antigua guide states June 2030.

Has construction started at DAMAC Islands 2?

Only enabling work. Nine clusters have a registered construction start of 2 May 2026, and DLD inspections in May and June 2026 recorded 0.18% to 0.33%. No cluster had a newer inspection figure than June 2026 except Antigua 1, at 0.32% on 16 September 2026.

Has the DAMAC Islands 2 handover date been delayed?

No. DAMAC gave Q2 2030 at launch in November 2025, and the registered dates for nine clusters are 30 June 2030. Dubai Handover's daily snapshots of the register show no change to any cluster's date from August to late September 2026.

Sources

  1. DAMAC, Antigua at DAMAC Islands 2 guide (opens in a new tab)damacproperties.com · accessed 28 Sep 2026
  2. Propsearch, DAMAC Islands 2 (opens in a new tab)propsearch.ae · accessed 28 Sep 2026
Request a Unit Review