Handover date

When is the DAMAC Lagoons handover date?

DAMAC Lagoons

How this page was made: figures from the DLD project register and the developer and portal pages listed under Sources, as at 28 October 2026. Text drafted with AI assistance from those sources. Every figure matched the fact records at the build on 12 November 2026. Not yet reviewed line by line by a person. How facts are checked

Short answer

DAMAC Lagoons hands over cluster by cluster, not on one date. On the Dubai Land Department (DLD) register, Santorini, Costa Brava and Malta are finished, the last phase being Costa Brava 2 on 4 August 2026. Portofino was 97.14% complete on 16 July 2026 and Nice 1 93.71% on 10 August 2026, both past registered dates in mid-2025. The other villa clusters were 65% to 87% complete in July to September 2026, with DLD records pointing to dates between December 2026 and October 2027. DAMAC handed over 513 homes in 2025 and targets about 6,300 in 2026. The date in the SPA for your cluster is the one that applies.

Clusters finished on the DLD register

3 of 11

Santorini, Costa Brava, Malta; last phase 4 Aug 2026

Most advanced unfinished cluster

Portofino, 97.14%

DLD inspection 16 Jul 2026

Homes handed over in 2025

513

DAMAC, 4 Sep 2026

Homes targeted for 2026

About 6,300

DAMAC, 4 Sep 2026

DAMAC Lagoons handover date: the latest position

DAMAC Lagoons, the Mediterranean-themed community opposite DAMAC Hills in Dubailand, is handed over cluster by cluster. DAMAC handed over 513 homes there in 2025 and targets about 6,300 more in 2026, with community infrastructure over 80% complete (DAMAC, 4 September 2026). Handovers began at Santorini in November 2025. Prices, payment plans and service charges for the whole community are on the DAMAC Lagoons page.

DAMAC has not published a cluster by cluster schedule, so the Dubai Land Department (DLD) register is the clearest record. It shows Santorini, Costa Brava and Malta as finished, with the last phase recorded on 4 August 2026. Portofino, Nice, Monte Carlo, Marbella, Mykonos, Ibiza and Venice have all passed their registered completion dates and are still under construction, as is Morocco. No DAMAC Lagoons project was recorded finished in September or October 2026 (Real Estate Club Dubai, DLD register).

DAMAC Lagoons handover date by cluster

Cluster Homes (DLD) DLD progress (inspection date) Registered completion date Finished on DLD register
Santorini 943 100% 29 Jul 2025 Santorini 1 30 Jul 2025; Santorini 2 9 Feb 2026; Santorini 3 9 Apr 2026
Costa Brava 1,052 100% 29 Jul 2025 Costa Brava 1 10 Apr 2026; Costa Brava 2 4 Aug 2026
Malta 1,127 100% 29 Sep 2025 Malta 2 8 Apr 2026; Malta 1 19 Jun 2026
Portofino 867 97.14% (16 Jul 2026) 29 Jun 2025 Not yet
Nice 943 Nice 1 93.71% (10 Aug 2026); Nice 2 83.88% (17 Aug 2026) 29 Jul 2025 Not yet
Monte Carlo 424 86.38% (9 Jul 2026) 31 Dec 2025; DLD records now 31 Dec 2026 Not yet
Marbella 609 87.32% (30 Sep 2026) 31 Dec 2025 Not yet
Mykonos 575 81.06% (30 Sep 2026) 31 Dec 2025; DLD records now 28 Feb 2027 Not yet
Morocco 1,024 Morocco 1 76.94%; Morocco 2 65.34% (17 Jul 2026) Not shown; DLD records 30 Apr 2027 (Morocco 1), 31 Oct 2027 (Morocco 2) Not yet
Ibiza 823 78.88% (30 Sep 2026) 31 Dec 2025; DLD records now 30 Jun 2027 Not yet
Venice 424 74.43% (17 Jul 2026) 29 Sep 2025 Not yet
Andalucia (Lagoon Views 1) 162 55.58% (15 May 2026) Not shown; DAMAC gives Q2 2027 Not yet
Lagoon Views (phases 1 to 13) 3,287 5.96% to 55.58% (May to Sep 2026) 31 Mar 2027 to 31 Dec 2027 (phases 9 to 13) Not yet

Sources: DLD register via Continental Club, Real Estate Club Dubai and Propsearch; later DLD project records via damaclagoonsproperty.ae, 6 September 2026. The Marbella and Mykonos figures are from the DLD inspection of 30 September 2026 (Continental Club, accessed 12 October 2026). The Lagoon Views row includes Andalucia.

  • Santorini handover: DAMAC began handing over Santorini in November 2025, and all three phases are now recorded finished, the last on 9 April 2026.
  • Costa Brava handover date: Costa Brava 1 was recorded finished on 10 April 2026 and Costa Brava 2 on 4 August 2026, about a year after the registered date.
  • Malta handover date: Malta 2 was recorded finished on 8 April 2026 and Malta 1 on 19 June 2026.
  • Portofino handover date: Portofino moved only 0.24 points between March and July 2026 and is not yet recorded finished, although registered leases show some homes are let.
  • Nice handover: Nice 1 is close to finished at 93.71%, while Nice 2 at 83.88% gained 11.14 points between April and August 2026.
  • Monte Carlo handover: Monte Carlo was 86.38% built in July 2026, close behind Marbella among the clusters registered for December 2025, and DLD records now point to 31 December 2026.
  • Marbella handover: Marbella was 87.32% built at the DLD inspection of 30 September 2026, after gaining 9.83 points between April and August 2026, and no new date has been published.
  • Mykonos handover: Mykonos was 81.06% built at the DLD inspection of 30 September 2026, with DLD records now pointing to 28 February 2027.
  • Morocco handover: the two Morocco phases are six months apart in the DLD records, and Morocco 2 is the least advanced villa phase.
  • Ibiza handover: Ibiza, with 823 homes, was 78.88% built in September 2026 and now points to 30 June 2027.
  • Venice handover: the villa-only Venice cluster was 74.43% built in July 2026, and portals estimate Q2 to Q3 2027.
  • Andalucia handover: the first Lagoon Views apartment release was 55.58% built in May 2026, and DAMAC gives Q2 2027.
  • Lagoon Views handover: the 13 apartment phases carry dates from March to December 2027.

How the DAMAC Lagoons handover dates have changed

  • Late 2021 to 2023: DAMAC launched the villa and townhouse clusters, starting with Santorini and Nice in late 2021 and ending with Mykonos and Morocco in 2023. Registered completion dates for all clusters except Morocco fell between 29 June 2025 (Portofino) and 31 December 2025 (Monte Carlo, Marbella, Mykonos and Ibiza).
  • January 2024: DAMAC launched Lagoon Views apartments, starting with Andalucia, with an anticipated completion date of January 2027.
  • November 2025: The first handovers began at Santorini. DAMAC handed over 513 homes in 2025.
  • February to August 2026: The DLD register recorded Santorini 2 and 3, Costa Brava 1 and 2, and Malta 1 and 2 as finished.
  • September 2026: Republished DLD project records gave new expected dates for Monte Carlo (31 December 2026), Mykonos (28 February 2027), Morocco 1 (30 April 2027), Ibiza (30 June 2027) and Morocco 2 (31 October 2027).

Some guides published in 2026 describe Portofino as handed over from Q4 2024 and Nice from Q1 2025 (Zurispace, 19 July 2026). The DLD figures above do not support either date.

What the DAMAC Lagoons handover date means for payments

The share due at handover depends on the cluster’s launch plan, so a later date moves a different amount for each buyer.

Cluster Due at handover (launch plan) Source
Santorini, Malta 10% Property Finder
Costa Brava, Nice, Monte Carlo, Marbella, Mykonos, Morocco, Ibiza, Venice 20% Property Finder, Bayut, Dubricks, DAMAC price sheets
Portofino 40% Property Finder
Andalucia 20% or 30% at launch; 40% on current listings Launch brochure; Property Finder

Later releases differ: portals show 20/40/40 plans for Monte Carlo, Mykonos, Ibiza and Marbella, and Property Finder shows a Venice release with 50% at handover. In the finished clusters, the final payment has fallen due. In the others it is still outstanding, and resale buyers usually take over that balance.

What to check before relying on a DAMAC Lagoons handover date

  1. The DLD phase of your unit. Nice 1 and Nice 2 are ten points apart, and Morocco 1 and Morocco 2 have DLD dates six months apart.
  2. Finished on the register versus keys. Portofino homes are being let while the cluster is not yet recorded finished, so ask DAMAC for the handover notice for your unit.
  3. Which Lagoon Views phase you are buying. Apartment phases run from March to December 2027 and Lagoon Views 13 was under 6% built in July 2026.

DAMAC Lagoons: construction pace and DAMAC's delivery record

Figures from DLD inspections in the fact record for DAMAC Lagoons. Finish dates below are our calculation at the pace recorded so far: arithmetic on the inspection figures, not a forecast and not the developer's view. How it is worked out.

Conclusion: Of the 10 buildings or phases with a DLD reading, 8 have passed their registered completion date unfinished; and 2 have no two DLD readings within the last 12 months, so no pace can be worked out yet.

Building or phaseLast DLD readingPace (points a month)Registered completionAt the pace recorded so far
Portofino97.14% (16 Jul 2026)1.329 Jun 2025 (passed)date passed
Nice 193.71% (10 Aug 2026)1.829 Jul 2025 (passed)date passed
Nice 283.88% (17 Aug 2026)3.129 Jul 2025 (passed)date passed
Monte Carlo86.38% (9 Jul 2026)1.931 Dec 2025 (passed)date passed
Marbella87.32% (30 Sep 2026)2.431 Dec 2025 (passed)date passed
Mykonos81.06% (30 Sep 2026)2.031 Dec 2025 (passed)date passed
Morocco 176.94% (17 Jul 2026)2.8not on recordMar 2027
Morocco 265.34% (17 Jul 2026)2.4not on recordOct 2027
Ibiza78.88% (30 Sep 2026)2.231 Dec 2025 (passed)date passed
Venice74.43% (17 Jul 2026)1.529 Sep 2025 (passed)date passed

DAMAC delivery record from DLD data

14 of the 86 DAMAC projects we track from DLD data (16%) had passed their registered completion date unfinished, by a median of 13 months, against 177 of 1,294 projects (14%) across all developers. Data as at 22 October 2026. All developers compared.

Register changes we recorded

No change to the registered completion date of any building since 13 October 2026, the earliest date in our records.

Register change log · Handover calendar

Questions buyers also ask

Is Nice at DAMAC Lagoons handed over?

Not on the DLD register. Nice 1 was 93.71% complete on 10 August 2026 and Nice 2 83.88% on 17 August 2026, against a registered completion date of 29 July 2025 (Continental Club, DLD registry). Some guides describe Nice as handed over in 2025, which these figures do not support.

When is the Portofino at DAMAC Lagoons handover date?

Portofino was registered for completion on 29 June 2025 and was 97.14% complete at its DLD inspection on 16 July 2026. It is not yet recorded finished, although registered leases show some homes are already let (Continental Club).

What is the DAMAC Lagoons Costa Brava 2 handover date?

Costa Brava 2 was recorded finished on the DLD register on 4 August 2026, and Costa Brava 1 on 10 April 2026. Both had a registered completion date of 29 July 2025 (Real Estate Club Dubai, DLD data).

Has the DAMAC Lagoons handover date been delayed?

Yes, for every cluster with a registered date. Those dates, for all clusters except Morocco, fell between 29 June and 31 December 2025. The three finished clusters were recorded finished four to twelve months later, and DLD records republished in September 2026 give new dates between 31 December 2026 and 31 October 2027 for Monte Carlo, Mykonos, Ibiza and Morocco.

What is the Venice DAMAC payment plan?

Venice launched on 20% at booking, 60% during construction and 20% on completion (Bayut). Property Finder records a later release with 10% at booking, 40% during construction and 50% at handover.