Register change log

What changed on the Dubai off-plan register

Since 29 Sep 2026: 1 registered completion date move, 3 projects recorded at 100% built, 24 registered dates passed with the project unfinished, and 59 new DLD inspections. Updated 22 Oct 2026.

How this page was made: figures from 2 weekly snapshots of the Dubai Land Department project register as republished by Continental Club (CC BY 4.0), 13 Oct 2026 to 19 Oct 2026, compared row by row with our script, plus newer DLD inspections recorded on our project pages up to 22 Oct 2026. Text drafted with AI assistance from those sources. Every figure matched the fact records at the build on 12 November 2026. Not yet reviewed line by line by a person. How facts are checked

Registered completion date moves

1 project had the registered completion date changed since 29 Sep 2026. A moved date is the clearest early sign of a revised handover: the developer has asked the Dubai Land Department for a new date. Earlier moves recorded on our project pages are listed below for context.

SeenProjectWasNowDirectionSource
19 Oct 2026Weston by Wadan28 Apr 202931 Dec 2028earlierDLD register (snapshot 19 Oct 2026) via Continental Club
Sep 2026 (before window)DAMAC Lagoons Ibiza31 Dec 202530 Jun 2027laterDLD register via Continental Club (original registered date)
Sep 2026 (before window)DAMAC Lagoons Monte Carlo31 Dec 202531 Dec 2026laterDLD register via Continental Club (original registered date)
Sep 2026 (before window)DAMAC Lagoons Mykonos31 Dec 202528 Feb 2027laterDLD register via Continental Club (original registered date)
4 Aug 2026 (before window)Samana South Haven, Samana South Haven 2 (project 4518, 137 units)31 Mar 202930 Jun 2029laterDLD register via dubaihandover.com (4 Aug to 8 Sep 2026)
Aug 2026 (before window)Jouri Hills30 Jun 202530 Jun 2026laterDubai Handover snapshots (until late August 2026)
25 Jun 2026 (before window)Emaar Beachfront, Beachgate by Address31 Dec 202622 Sep 2026earlierfäm Properties (DLD register, earlier entry)
13 Jun 2026 (before window)Sobha Waves Opulence30 Sep 20266 Aug 2026earlierDLD via Real Estate Club Dubai
undefined 2026 (before window)Elanora by Zoya30 Sep 202731 Mar 2028laterSofia Sands, quoting the register (earlier in 2026)
18 Jul 2019 (before window)Expo Golf Villas, Expo Golf Villas 5 (Greenviews 2)2 Oct 202218 Jan 2024laterDLD escrow record via Korter (first registered date)
25 Apr 2019 (before window)Expo Golf Villas, Expo Golf Villas 4 (Greenview 1)30 Apr 202218 Jan 2024laterDLD escrow record via Korter (first registered date)
1 Oct 2017 (before window)Tonino Lamborghini Residences31 Dec 202131 Dec 2026laterDLD register (original registered date, held until 27 Aug 2026)

Registered dates that passed unfinished

24 projects reached their registered completion date between 29 Sep 2026 and 22 Oct 2026 while the last DLD inspection showed them unfinished. Expect a new registered date for most of them.

Registered dateProjectDeveloper (DLD name)Built at last inspection
30 Sep 2026Ag SquareAg68.8% (17 Sep 2026)
30 Sep 2026City Center ResidencesDar Global72.3% (10 Sep 2026)
30 Sep 2026Exotica by Al MarinaAl Marina Investment - Sole Proprietorship - Dubai Branch41.09% (19 Jun 2026)
30 Sep 2026Lanai IslandMajid Al Futtaim Tilal Al Ghaf Phase A60.56% (9 Sep 2026)
30 Sep 2026Lincoln Star ResidenceLincoln Star47.21% (26 Feb 2026)
30 Sep 2026Minati Homes 1Januss51.23% (6 Jul 2026)
30 Sep 2026Natuzzi Harmony ResidencesPeace Homes19.57% (12 Mar 2026)
30 Sep 2026Oasis LoftsOasis Lofts50.08% (8 Jun 2026)
30 Sep 2026Ocean TowerAhmed Alansari30.25% (11 Sep 2026)
30 Sep 2026Voi Residence By Hvm LivingHvm Living15.62% (6 Jul 2026)
1 Oct 2026Hearth Heights By Enawt Real Estate DevelopmentEnawt29.08% (6 Jul 2026)
1 Oct 2026MonarchZane20.02% (26 Aug 2026)
1 Oct 2026Stellar Axis By Ajmal Estate DevelopersAjmal Estate26.67% (10 Aug 2026)
1 Oct 2026Vue By Crystal BayCrystal Bay68.21% (27 Aug 2026)
2 Oct 2026Hatimi Residences by Treppan LivingFakhruddin50.77% (4 Aug 2026)
8 Oct 2026Central Park PlazaCitywalk Residential 143.68% (1 Sep 2026)
13 Oct 2026The SereneAl Mizan Serene Dwc28.15% (4 Mar 2026)
14 Oct 2026Golden Wood Views 5Golden Wood89.05% (25 Apr 2026)
15 Oct 2026Bay Residences Dubai IslandsNakheel And Excelsior47.88% (22 Jun 2026)
15 Oct 2026Cove Edition Residence 2 By ImtiazImtiaz Investment &50% (17 Aug 2026)
15 Oct 2026Luminar Tower 1Obj133.07% (30 Jul 2026)
15 Oct 2026Samha Residence 2Samha52.07% (14 Aug 2026)
15 Oct 2026Stamn OneStamn42.05% (25 Aug 2026)
16 Oct 2026Almaara ResidencesHamara Home65.52% (30 Jun 2026)

Projects recorded at 100% built

  • 7 Oct 2026: Arabian Ranches 3, Anya (DLD via Continental Club (Ready) and Dubai Handover (latest inspection), read 28 Oct 2026)
  • 7 Oct 2026: Arabian Ranches 3, Anya 2 (DLD register via Continental Club (Ready))
  • 19 Oct 2026: Altai Tower (DLD register via Continental Club (status Ready from the same date))

New DLD inspections

59 projects had a new inspection reading in this period. Points are the change from the previous reading.

InspectionProjectBuiltPreviousChange
22 Oct 2026Sobha Solis17.92%13.22% (5 May 2026)+4.70 points
21 Oct 2026Samana Parkville13.88%5.12% (18 Jun 2026)+8.76 points
20 Oct 2026Barari Gate by ADE1.67%0% (24 Nov 2025)+1.67 points
20 Oct 2026Divine Al Barari20.32%12.28% (19 May 2026)+8.04 points
20 Oct 2026Samana Barari Lagoons16.52%11.84% (2 Jun 2026)+4.68 points
19 Oct 2026Altai Tower100%98.43% (29 Sep 2026)+1.57 points
19 Oct 2026Marquis One0.29%0% (16 Mar 2026)+0.29 points
15 Oct 2026105 Residences by Kamdar12.45%10.1% (13 Jul 2026)+2.35 points
15 Oct 2026Azizi Zain80.15%66.21% (30 Jun 2026)+13.94 points
15 Oct 2026LIV Lux87.12%78.96% (2 Jun 2026)+8.16 points
14 Oct 2026Azizi Venice 1345.87%40.33% (22 Apr 2026)+5.54 points
14 Oct 2026Greenz by Danube0.1%0% (27 Mar 2026)+0.10 points
14 Oct 2026Veona By Gutti21.66%11.08% (18 Jun 2026)+10.58 points
14 Oct 2026Wellington Grand Villas62.07%50.91% (27 Jul 2026)+11.16 points
13 Oct 2026Amazonia1.35%0.02% (29 Jun 2026)+1.33 points
13 Oct 2026Avenew888-Loom1.63%0.04% (30 Jul 2026)+1.59 points
13 Oct 2026Cove Edition Residence 625.86%20.09% (13 Jul 2026)+5.77 points
13 Oct 2026Ghaff Land Residence66.41%64.46% (15 Jul 2026)+1.95 points
13 Oct 2026Palm Jebel Ali - The Beach And Coral Collection2.41%1.56% (13 Jul 2026)+0.85 points
13 Oct 2026Palm Jebel Ali - The Beach And Coral Collection - Frond B2.68%1.69% (13 Jul 2026)+0.99 points
13 Oct 2026Palm Jebel Ali - The Beach And Coral Collection - Frond C2.77%1.69% (13 Jul 2026)+1.08 points
13 Oct 2026Palm Jebel Ali - The Beach And Coral Collection - Frond D2.21%1.59% (13 Jul 2026)+0.62 points
13 Oct 2026Palm Jebel Ali - The Beach And Coral Collection - Frond E2.6%1.38% (13 Jul 2026)+1.22 points
13 Oct 2026Palm Jebel Ali - The Beach And Coral Collection - Frond F2.51%1.29% (13 Jul 2026)+1.22 points
13 Oct 2026Reem By Vision70.35%53.14% (23 Jul 2026)+17.21 points
13 Oct 2026Seacliff By Imtiaz7.7%4.71% (20 Jul 2026)+2.99 points
13 Oct 2026The Promise Villas28.45%0% (3 Nov 2025)+28.45 points
13 Oct 2026The Wilds Residences0.02%0% (3 Feb 2026)+0.02 points
12 Oct 2026Cove Edition Residence90.22%66.48% (13 Jul 2026)+23.74 points
12 Oct 2026La Boutique by LMD52.5%38.09% (18 Jun 2026)+14.41 points
12 Oct 2026Longford Residences By Devan Real Estate Development32.72%12.28% (25 Mar 2026)+20.44 points
12 Oct 2026Samana Mykonos Signature86%80.48% (14 May 2026)+5.52 points
12 Oct 2026Soul By Vision77.03%62.05% (17 Jul 2026)+14.98 points
12 Oct 2026The First Collection At Dubai Studio City31.86%21.02% (13 Jul 2026)+10.84 points
12 Oct 2026The Melgrano42.78%32.04% (18 Jun 2026)+10.74 points
12 Oct 2026Verde By Vision11.97%1.59% (14 Apr 2026)+10.38 points
12 Oct 2026Vista By Vision12.2%3.38% (14 May 2026)+8.82 points
9 Oct 2026Como Residences24.77%20.88% (6 Jul 2026)+3.89 points
9 Oct 2026Myra Onyx85.88%66.77% (2 Jul 2026)+19.11 points
9 Oct 2026Rose Gardens 251.46%31.76% (4 Jun 2026)+19.70 points
8 Oct 2026Atelis at D31.44%0.96% (6 Jul 2026)+0.48 points
8 Oct 2026Auresta Tower4.44%2% (27 Jul 2026)+2.44 points
8 Oct 2026Avenew888 - Modo21.21%15.48% (27 Aug 2026)+5.73 points
8 Oct 2026Bulgari Lighthouse Dubai80.01%63.61% (9 Jul 2026)+16.40 points
8 Oct 2026Capital One at Motor City20.02%11.09% (2 Jul 2026)+8.93 points
8 Oct 2026Coastal Haven By Prestige Harbour Real Estate Development33%23.05% (30 Jun 2026)+9.95 points
8 Oct 2026Cove Grand by Imtiaz13.4%8.67% (8 Jul 2026)+4.73 points
8 Oct 2026Havelock Heights40%28.01% (25 Jun 2026)+11.99 points
8 Oct 2026Lincoln Star Residence Iii0.3%0% (13 Nov 2025)+0.30 points
8 Oct 2026Luxury Canal Residences28.88%17.71% (30 Jun 2026)+11.17 points
8 Oct 2026One.B Tower10.1%5.77% (3 Mar 2026)+4.33 points
8 Oct 2026South Park Residences By Wellington96.77%91.33% (20 Jul 2026)+5.44 points
8 Oct 2026Sportz by Danube80.22%68.83% (7 Sep 2026)+11.39 points
7 Oct 2026Address Grand Downtown10.76%4.72% (30 Apr 2026)+6.04 points
7 Oct 2026Ananda Towers3.2%2.55% (5 Aug 2026)+0.65 points
7 Oct 2026Guzel Towers7.3%6.96% (24 Jul 2026)+0.34 points
7 Oct 2026LIV Maritime28.12%18.73% (19 May 2026)+9.39 points
7 Oct 2026Orise by Beyond17.64%8.61% (7 May 2026)+9.03 points
7 Oct 2026Sky Gate Tower4.68%1.56% (31 Mar 2026)+3.12 points

How this log is built

  • Data: each weekly copy of the register is saved as a dated snapshot. Consecutive snapshots are compared row by row on project name and developer. Readings newer than the latest snapshot come from the DLD inspection recorded on our project page for that project.
  • Window: 29 Sep 2026 to 22 Oct 2026. Date moves seen before the window stay listed because they explain current registered dates.
  • Limits: the register shows only the current registered date, so a move made and reversed between two snapshots is not seen. The handover date in your SPA is the one that applies to your unit.
  • Updates: rebuilt from each weekly snapshot. The updated date changes only when the data changes.

Download the log as CSV. Free to reuse with a link to this page.

DLD data you can check yourself

  • Developer delay record: Projects past their registered completion date, by developer. CSV download included.
  • Handover calendar: Registered completion dates by quarter, with progress so far. CSV download included.