Samana Mykonos Signature
Samana's 300 unit private pool apartment building in Arjan. Its registered completion date of 30 April 2026 has passed at 80% built; Samana now says Q1 2027. Prices, sales and payment plan.
Short answer
Samana Mykonos Signature, a 300 unit building in Arjan, is not yet handed over. Its registered completion date in the Dubai Land Department (DLD) project register, 30 April 2026, has passed, and the last DLD inspection on 14 May 2026 put construction at 80.48%. Samana Developers' project page now gives Q1 2027. Sales began in October 2023 with launch prices from about AED 645,000, and registered off-plan sales in July to September 2026 ran from AED 787,831 for a studio to AED 1.9 million for a 2 bedroom.
- Status
- under construction
- Handover date
- Samana now states Q1 2027; registered completion date of 30 Apr 2026 has passed
- Construction
- 80.48% complete (DLD inspection, 14 May 2026)
- Payment plan
- 15% on booking, 25% during construction, 60% on handover (launch plan)
- Starting price
- From about AED 645,000 at launch (Oct 2023)
Construction progress
80.48%
DLD inspection, 14 May 2026
Registered completion date
30 Apr 2026 (passed)
DLD project register via Continental Club
Developer's stated date
Q1 2027
Samana Developers, accessed 11 Oct 2026
Units
300
One building, basement, ground, mezzanine and 8 floors
When will Samana Mykonos Signature be handed over?
Samana Developers’ project page now gives an anticipated completion date of Q1 2027 for Samana Mykonos Signature (accessed 11 October 2026). The Dubai Land Department (DLD) project register still shows a completion date of 30 April 2026, which has passed. The register lists the building as project number 2587, under construction.
The date has moved several times. Data Habibi records an original developer promise of Q4 2025 and a current target of Q2 2027, a 20 month postponement. Property Finder still shows April 2026 and labels the project ready, which does not match the DLD record. Dubainary and OffplanIndex show Q4 2026.
Building-by-building dates and how the date has changed: Samana Mykonos Signature handover date.
Samana Mykonos Signature construction update
A DLD inspection on 14 May 2026 put construction at 80.48%, up 7.81 points from the inspection of 22 January 2026 (DLD project register via Continental Club). Construction started on 1 October 2023. The register describes one building of a basement, ground floor, mezzanine and eight floors. At the pace recorded between January and May 2026, about two points a month, the remaining 20% would take about nine months from May 2026, into early 2027. That fits Samana’s Q1 2027 date more closely than the register date. No newer inspection had been published by 11 October 2026.
Samana Mykonos Signature homes and sizes
The building has 300 units on the DLD register, in the Al Barsha South Third area, which buyers know as Arjan. Samana describes it as following its earlier Samana Mykonos project, with a Greek island design and private pools on many balconies. Retail units are also listed.
| Home type | Size |
|---|---|
| Studio | 389 to 720 sq ft |
| 1 bedroom | 827 to 1,513 sq ft |
| 2 bedroom | 1,300 to 1,898 sq ft |
Sizes are from floor plans listed by Data Habibi (accessed 11 October 2026).
Samana Mykonos Signature prices and resale
Bookings opened on 1 October 2023 (Property Finder). Launch prices are given as about AED 645,000 by Data Habibi, AED 625,000 for a 389 sq ft unit by Continental Club and AED 746,973 by Property Finder. Samana’s own page now shows a starting price of AED 426,000, well below any registered sale, without saying which unit it applies to.
The DLD register shows 18 sales between 16 July 2025 and 3 September 2026, all off-plan, with a median of AED 1,306 per sq ft (Mitchells). Recent examples:
- Studios of about 421 sq ft: AED 787,831 to AED 880,178 in July 2026, and AED 849,000 on 1 September 2026, about AED 2,016 to AED 2,093 per sq ft.
- 1 bedroom of 850 sq ft: AED 1,100,250 on 3 September 2026.
- 2 bedroom of 1,796 sq ft: AED 1,903,141 on 21 July 2026.
For comparison, off-plan sales across Arjan had a median of AED 1,730 per sq ft in the 12 months to 23 September 2026 (Mitchells). Continental Club counts 331 registered sales on the project in total.
Samana Mykonos Signature payment plan
At launch, Property Finder and Data Habibi listed 15% on booking, 25% during construction and 60% on handover. OffplanIndex now lists 20% on booking, 20% during construction and 60% on handover, with nothing after handover. Dubainary lists newer options with up to 80% due on handover. On a AED 850,000 studio, a 60% handover payment would be AED 510,000. Dubainary lists a service charge of AED 15 per sq ft.
Samana Mykonos Signature developer and delivery record
Samana Developers is filed in the register through Samana International Real Estate Development. On 16 April 2026 it handed over Samana Santorini in Dubai Studio City and said it had delivered more than 1,300 units (Business Today Middle East). Samana Mykonos Signature is behind its own first target: Q4 2025 at launch, 30 April 2026 on the register, and Q1 2027 now.
What to check before buying at Samana Mykonos Signature
- The completion date in the SPA, since the register date of 30 April 2026 has passed and Samana now gives Q1 2027.
- Whether the unit has a private pool, as layouts with and without pools are sold in the same size bands.
- The share due on handover, which is 60% or more on the listed plans.
- The next DLD inspection, through the DLD project status service, for progress after 80.48%.
Samana Mykonos Signature location: Arjan, Dubai
Map shows the area. Check the exact plot in the developer's site plan or the DLD project record. Check any project's DLD status.
Questions buyers also ask
What is the Samana Mykonos Signature handover date?
Samana Developers' project page gives an anticipated completion date of Q1 2027 (accessed 11 October 2026). The DLD register still shows 30 April 2026, which has passed. The last DLD inspection, on 14 May 2026, recorded 80.48% complete.
What is the Samana Mykonos Signature completion date?
The registered completion date is 30 April 2026 (DLD project number 2587), now passed. Samana gives Q1 2027 and Data Habibi lists Q2 2027.
Is Samana Mykonos Signature ready?
No. Property Finder labels the project ready, but the DLD register lists it as under construction at 80.48% on 14 May 2026, and all 18 sales registered from July 2025 to September 2026 were off-plan sales (Mitchells).
What is the Samana Mykonos Signature price?
Launch prices started from about AED 645,000 (Data Habibi) to AED 746,973 (Property Finder) in 2023. Registered sales from July to September 2026 included studios of about 421 sq ft at AED 787,831 to AED 880,178 and a 1 bedroom of 850 sq ft at AED 1,100,250 (Mitchells).
What is the Samana Mykonos Signature payment plan?
At launch, Property Finder and Data Habibi listed 15% on booking, 25% during construction and 60% on handover. Later listings show 20/20/60, still with 60% due on handover.