Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Lilac at DAMAC Hills handover date?

Updated 11 October 2026 Lilac at DAMAC Hills

Short answer

Lilac at DAMAC Hills has a registered completion date of 31 January 2030 in the Dubai Land Department (DLD) register, and broker pages show Q1 2030. The DLD inspection on 24 April 2026 recorded 0% progress, ahead of a registered construction start of 31 July 2026. DAMAC has not published its own handover date, so the register is the only firm reference.

Registered completion date (DLD)

31 Jan 2030

DLD register via Continental Club

Latest construction progress

0%

DLD inspection, 24 Apr 2026

Developer's stated date

Not published

Q1 2030 on broker pages, Oct 2026

Date change since registration

None

Daily register snapshots, Aug to Oct 2026, Dubai Handover

Lilac at DAMAC Hills handover date: the latest position

Lilac at DAMAC Hills has a registered completion date of 31 January 2030. The Dubai Land Department (DLD) lists it as “Damac Hills - Lilac”, project 4468, filed by Damac Crescent Properties. Full project details are on the Lilac at DAMAC Hills page.

DAMAC has not announced a handover date of its own. Broker pages quote Q1 2030, taken from the register. The DLD inspection on 24 April 2026 recorded 0%, and the register sets the construction start for 31 July 2026.

Lilac at DAMAC Hills handover date by building

Lilac is a single 12 storey apartment building with 288 units.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Lilac (288 apartments) 0% (24 Apr 2026) 31 Jan 2030 Q1 2030 (Autograph Realtors, Data Habibi); DAMAC date not published

Dubai Handover lists the same inspection as 22 April 2026. Both sources agree on 0% and on the 31 January 2030 date.

The building has a ground floor, two podium levels, nine residential floors and a roof, with 161 studios, 118 one bedroom, 8 two bedroom and 1 three bedroom apartments (DLD inventory via Data Habibi). All 288 share one registration, so every unit carries the same completion date. For comparison, DAMAC District, DAMAC’s other new registration in DAMAC Hills, was 4.07% complete on 22 September 2026 against a registered date of 30 March 2029, about ten months earlier than Lilac.

How the Lilac at DAMAC Hills handover date has changed

Date What was stated Source
22 to 24 Apr 2026 DLD inspection at 0%; completion 31 January 2030 DLD register via Continental Club and Dubai Handover
31 Jul 2026 Registered construction start DLD register via Continental Club
10 Aug 2026 Listed among DAMAC’s 2026 registrations, 288 units, January 2030 Certified Poor
4 Aug to 1 Oct 2026 Daily snapshots: active, 0%, 31 January 2030 Dubai Handover

There is no launch date to compare with, because DAMAC had not published a launch, price list or payment plan for Lilac by October 2026. Data Habibi’s statement that construction began in January 2024 conflicts with the register’s 31 July 2026 start.

What the Lilac at DAMAC Hills handover date means for payments

No payment plan has been published, so the share due at handover is not known. At DAMAC District, also in DAMAC Hills, the plan put 30% on handover (Certified Poor). Whatever plan Lilac uses, the registered 31 January 2030 date sets how long construction instalments are likely to run.

What to check before relying on the Lilac at DAMAC Hills date

  1. That the booking is for DLD project 4468, not a similarly named DAMAC listing.
  2. The completion date and grace period in the SPA, once DAMAC issues sales documents.
  3. A non-zero DLD inspection after 31 July 2026, the first sign that work matches the registered start.

Questions buyers also ask

When will Lilac at DAMAC Hills be completed?

The DLD register gives 31 January 2030 (Continental Club; Dubai Handover, snapshot 1 October 2026).

Has construction started at Lilac?

Not according to the register. The DLD inspection on 24 April 2026 recorded 0%, and the registered construction start is 31 July 2026. Register snapshots still showed 0% on 1 October 2026.

Has the Lilac handover date been delayed?

No change is recorded. Daily register snapshots from August to October 2026 show the same 31 January 2030 date.

Is Lilac the same as DAMAC District?

No. Both are DAMAC projects in DAMAC Hills, but DAMAC District is a separate registration with 1,197 units and a completion date of 30 March 2029.

Sources

  1. Data Habibi, Lilac at Damac Hills (opens in a new tab)datahabibi.ae · accessed 11 Oct 2026
  2. Autograph Realtors, Lilac at Damac Hills (opens in a new tab)autographrealtors.com · accessed 11 Oct 2026
Request a Unit Review