Handover date

When is the DAMAC Bay by Cavalli handover date?

Updated 1 October 2026 DAMAC Bay by Cavalli

Short answer

DAMAC gives Q3 2027 as the DAMAC Bay by Cavalli handover date, and earlier named July 2027, while the Dubai Land Department (DLD) register holds a registered completion date of 15 January 2027. The DLD site inspection of 18 August 2026 put construction at 33.76% complete, which would need far faster progress than recorded so far to meet the register date. The Q4 2028 date seen on some listings belongs to DAMAC Bay 2, a separate project next door.

Registered completion date (DLD)

15 Jan 2027

DLD register, project 2559, via Mitchells, 28 Sep 2026

Latest construction progress

33.76%

DLD site inspection, 18 Aug 2026

Developer's stated date

Q3 2027

DAMAC project page, accessed 1 Oct 2026; July 2027 in DAMAC's 23 Dec 2024 update

Portal estimate

2026

Propsearch milestones, updated 18 Sep 2026

DAMAC Bay handover date: the latest position

DAMAC gives Q3 2027 as the handover quarter for DAMAC Bay by Cavalli on its project page, and its December 2024 construction update named July 2027. The Dubai Land Department register holds an earlier registered completion date of 15 January 2027. At the DLD site inspection of 18 August 2026, the project was 33.76% complete. Prices, sizes and the payment plan are covered on the DAMAC Bay by Cavalli page.

The project moved from 7.10% in October 2024 to 33.76% in August 2026, about 27 points in 22 months. Meeting the register date would mean building the remaining 66.24% in the five months to 15 January 2027. DAMAC’s own Q3 2027 leaves about a year from the inspection.

DAMAC Bay handover date by building

The DLD register lists 1,087 homes in project number 2559, filed as three towers on a shared basement and podium. It gives one progress figure and one date for all of them.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Tower A (47 floors) 33.76%, whole project, 18 Aug 2026 15 Jan 2027 Q3 2027 (DAMAC)
Tower B (47 floors) 33.76%, whole project, 18 Aug 2026 15 Jan 2027 Q3 2027 (DAMAC)
Tower C (48 floors) 33.76%, whole project, 18 Aug 2026 15 Jan 2027 Q3 2027 (DAMAC)
DAMAC Bay 2 (separate project, 646 homes) 30.3%, Jul 2026 Not the same register entry Q4 2028 (DAMAC, Jun 2024)

Floor counts are from the developer’s filed description on the DLD register (Mitchells, 28 September 2026). DAMAC markets the towers as 42 storeys and Propsearch counts 1,066 units, against 1,087 on the register. DAMAC Bay 2 is listed only to separate the two projects.

How the DAMAC Bay handover date has changed

DAMAC’s date has stayed in mid 2027 since 2024. Early portal estimates of 2026 have passed.

Date What happened Source
26 Jan 2023 DAMAC launched DAMAC Bay by Cavalli: three towers in Dubai Harbour. DAMAC, via Zawya
15 Apr 2023 Registered construction start. Registered completion date 15 January 2027. DLD register, via Mitchells
11 Jun 2024 7% complete, piling and excavation done. Expected completion Q3 2027. DAMAC, via Construction Week
17 Oct 2024 7.10% complete. “On schedule” for July 2027. DAMAC
23 Dec 2024 Main works contract with China State Construction Engineering Corporation; foundation works under way. Completion July 2027. DAMAC
18 Aug 2026 33.76% complete at the DLD site inspection. DLD register, via Mitchells
1 Oct 2026 DAMAC’s page still shows Q3 2027; Propsearch still shows a 2026 estimate. DAMAC; Propsearch

What the DAMAC Bay handover date means for payments

DAMAC lists a 60/40 plan, which broker listings break down as 20% at booking, 40% during construction and 40% at handover. The median registered sale price is AED 3.95 million (Mitchells, DLD data, 28 September 2026), so the handover payment on a median unit is about AED 1.58 million. Because 40% is tied to handover, any move from Q3 2027 shifts the largest single payment.

What to check before relying on the DAMAC Bay date

  1. Which date your SPA uses. The register says 15 January 2027 and DAMAC says Q3 2027, and the grace period runs from the SPA date.
  2. That your unit is in DAMAC Bay, project 2559, not DAMAC Bay 2. Listings mix the two, and only DAMAC Bay 2 carries Q4 2028.
  3. The DLD progress for project 2559 through DLD’s project status enquiry service. The next inspection after August 2026 will show whether a third quarter 2027 finish is on track.

Questions buyers also ask

What is the DAMAC Bay by Cavalli completion date?

DAMAC's project page gives Q3 2027 (accessed 1 Oct 2026), and DAMAC's December 2024 update named July 2027. The DLD register holds an earlier registered completion date of 15 January 2027 for project number 2559 (Mitchells, 28 Sep 2026).

Is DAMAC Bay by Cavalli finished?

No. The DLD site inspection of 18 August 2026 put DAMAC Bay at 33.76% complete, and the register listed it as under construction on 28 September 2026.

Has the DAMAC Bay handover date been delayed?

DAMAC's own date has held at July 2027 or Q3 2027 since June 2024. Portal estimates have slipped: Propsearch still shows an estimated completion of 2026. The register date of 15 January 2027 is about six months earlier than DAMAC's own date.

Is DAMAC Bay due in Q4 2028?

No. Q4 2028 is the date DAMAC gave for DAMAC Bay 2, a separate two tower project, in its June 2024 update. The same update gave Q3 2027 for DAMAC Bay (Construction Week, 11 Jun 2024).

How much is due at the DAMAC Bay handover?

40% of the price under DAMAC's 60/40 plan, which brokers show as 20% at booking, 40% during construction and 40% at handover. On the AED 3.95 million median registered sale price, that is AED 1.58 million (Mitchells, DLD data, 28 Sep 2026).

Sources