Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Saria by Beyond handover date?

Updated 11 October 2026 Saria by Beyond

Short answer

Beyond gives Q1 2028 for the Saria by Beyond handover, while the DLD register holds a registered completion date of 1 October 2027. The DLD inspection on 1 October 2026 recorded 30.99% complete. With 69% of the work left, the registered date will not be met, and even Q1 2028 needs a faster pace than the tower has shown so far.

Registered completion date (DLD)

1 Oct 2027

DLD project register via Continental Club

Latest construction progress

30.99%

DLD inspection, 1 Oct 2026

Developer's stated date

Q1 2028

Beyond via Zawya, 24 Mar 2026

Date change since launch

Q4 2027 to Q1 2028

Propsearch

Saria by Beyond handover date: the latest position

Beyond expects Saria to be completed in Q1 2028, and Property Finder lists expected completion on 31 March 2028. The DLD project register still holds a registered completion date of 1 October 2027. Prices, sizes and the payment plan are on the Saria by Beyond page.

The DLD inspection on 1 October 2026 recorded the tower 30.99% complete, a year before its registered date. Construction has sped up in 2026, but the registered date is out of reach, and Q1 2028 depends on keeping up the latest pace.

Saria by Beyond handover date by building

Saria is one tower, registered as DLD project 3115 with 372 units.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Saria by Beyond 30.99%, 1 Oct 2026 1 Oct 2027 Q1 2028 (Beyond, Mar 2026); 31 Mar 2028 (Property Finder); Q3 2029 (Inside Realty)

For the other towers in the district, see the Dubai Maritime City handover date page.

How the Saria by Beyond handover date has changed

Date What happened Source
23 Sep 2024 Launch; payment schedule anticipates completion in Q1 2028 Metropolitan; Saria sales microsite
1 Nov 2024 Registered construction start DLD register
6 Dec 2024 Beyond says Saria is sold out Business Wire
24 Oct 2025 Inspection records 7.12% DLD register
28 Jan 2026 Inspection records 10.32% DLD register
24 Mar 2026 Beyond reports about 10% and Q1 2028 completion Zawya
7 May 2026 Inspection records 16.88% DLD register
1 Oct 2026 Inspection records 30.99% DLD register

Propsearch records an earlier estimate of Q4 2027, close to the registered date, later revised to Q1 2028. The payment schedule published at launch already pointed the final payment to Q1 2028, so the gap between the registered date and Beyond’s date has existed since sales began.

Between 7 May and 1 October 2026 the tower gained about 2.9 points a month. At that pace the remaining 69% would take about two years, to around late 2028. Continental Club’s longer-run average of 2.12 points a month points to mid 2029. Reaching completion by 31 March 2028 would need about 3.8 points a month for the next 18 months.

What the Saria by Beyond handover date means for payments

Half the price is due on completion. The other 50% is paid on fixed dates: 10% on booking, 10% a month later and six 5% instalments every April and October from 2025 to 1 October 2027 (Saria sales microsite). Those dates do not move with construction, so buyers will have paid 50% by October 2027 whatever the progress. A later completion only delays the final 50%, giving more time to arrange a mortgage or sell before it falls due.

What to check before relying on the Saria by Beyond date

  1. The completion date and grace period in the SPA, since the registered date of 1 October 2027 will pass with the tower unfinished.
  2. The 1 April 2027 and 1 October 2027 instalments, which fall due before completion on any of the published dates.
  3. The next DLD inspections. A pace of about 3.8 points a month is needed to reach Q1 2028.

Questions buyers also ask

When will Saria by Beyond be completed?

Beyond expects completion in Q1 2028, and Property Finder lists 31 March 2028. The DLD register still shows a registered completion date of 1 October 2027. The tower was 30.99% complete on 1 October 2026.

Has the Saria by Beyond handover date been delayed?

Yes, by about one quarter so far. Propsearch records an original estimate of Q4 2027, later revised to Q1 2028. The DLD registered date of 1 October 2027 has not been updated.

How fast is construction moving at Saria?

Progress went from 7.12% on 24 October 2025 to 10.32% on 28 January 2026, 16.88% on 7 May 2026 and 30.99% on 1 October 2026 (DLD project register via Continental Club).

Is Saria by Beyond finished?

No. It was 30.99% complete at the DLD inspection on 1 October 2026.

Sources

  1. Property Finder, Saria project page (opens in a new tab)propertyfinder.ae · accessed 11 Oct 2026
  2. Propsearch, Saria by Beyond (opens in a new tab)propsearch.ae · updated 11 Jul 2026
  3. Inside Realty, Saria by BEYOND (opens in a new tab)insiderealty.ae · accessed 11 Oct 2026
Request a Unit Review