Handover date

When will Dubai Maritime City be completed?

Updated 11 October 2026 Dubai Maritime City

Short answer

Dubai Maritime City has no single completion date. DP World is the master developer, and each residential tower has its own registered completion date on the Dubai Land Department (DLD) register, the latest being 31 December 2029 for Chelsea Residences, Chelsea Residences 2 and Prestige One Residences. Two towers are complete: Anwa (2022) and Riva Residence, recorded 100% built on 22 December 2025. Nautica One and Two were the most advanced of the rest at 85.19% and 85.45% (DLD inspection, 3 September 2026), while Mar Casa was 56.45% built on 4 August 2026 against a registered date of 31 October 2026.

Latest registered completion date (DLD)

31 Dec 2029

Chelsea Residences 1 and 2, Prestige One Residences

Most advanced tower under construction

85.45%

Nautica Two, DLD inspection 3 Sep 2026

Towers complete

2

Anwa (2022); Riva Residence, 100% at 22 Dec 2025 DLD inspection

Next registered date

31 Oct 2026

Mar Casa, 56.45% built on 4 Aug 2026

Dubai Maritime City completion date: the latest position

Dubai Maritime City will not be completed on one date. DP World runs the district, and the residential towers are built by separate developers, each with its own registered completion date on the Dubai Land Department register. In October 2026 those dates ran from 31 October 2026 for Mar Casa to 31 December 2029 for DAMAC’s Chelsea Residences and Prestige One Residences. Background on the district is on the Dubai Maritime City page.

Two towers are complete. Anwa by Omniyat was finished in 2022, and Riva Residence by Vakson was recorded 100% built on 22 December 2025. Nautica One and Two are next, both above 85% built in September 2026.

Dubai Maritime City completion date by project

Tower (developer) Construction progress (DLD, date) Registered completion date Developer or portal date
Anwa (Omniyat) Complete 2022 Complete (Bayut)
Riva Residence (Vakson) 100%, 22 Dec 2025 25 Sep 2025 Q4 2025 (Bayut)
Nautica Two (Select Global) 85.45%, 3 Sep 2026 Not filed Q4 2026 (Bayut)
Nautica One (Select Global) 85.19%, 3 Sep 2026 Not filed Q4 2026 (Bayut)
Anwa Aria (Omniyat) 84.86%, 30 Sep 2026 31 Jan 2026, passed Q4 2027 (Omniyat)
Harbour Lights (DAMAC) 64.31%, 9 Jul 2026 21 May 2027 Q2 2027 (Continental Club)
Mar Casa (Deyaar) 56.45%, 4 Aug 2026 31 Oct 2026 Q4 2026 (Bayut)
Oceanz 1 (Danube) 50.04%, 25 Aug 2026 Not filed Q1 2027 (Bayut); within 12 months (Danube, Jul 2026)
Oceanz 2 (Danube) 42.03%, 25 Aug 2026 Not found Q1 2027 (Bayut)
The Pier Residence (Continental Investments) 34.81%, 14 Jul 2026 31 Dec 2026 Not published
Coral Reef (DAMAC) 32.87%, 10 Aug 2026 Not filed Q1 2028 (Bayut)
Oceanz 3 (Danube) 20.64%, 4 Aug 2026 Not found Q1 2027 (Bayut)
LIV Maritime (LIV) 18.73%, 19 May 2026 30 Dec 2028 Not published
Saria (Beyond) 16.88%, 7 May 2026 1 Oct 2027 Q1 2028 (Beyond, Mar 2026); Q3 2027 (Bayut)
Chelsea Residences 2 (DAMAC) 5.44%, 6 Aug 2026 31 Dec 2029 Not published
Chelsea Residences (DAMAC) 5.19%, 7 Aug 2026 31 Dec 2029 Q4 2029 (Bayut)
Il Vento (Kora) 1.15%, 12 May 2026 30 Sep 2029 Not published
31 Above (Beyond) 0.51%, 18 Jun 2026 30 Dec 2028 Not published
Breez by Danube 0.14%, 14 Jul 2026 30 Jun 2029 2029 (Danube)
Prestige One Residences (Prestige Luxe) 0.11%, 23 Sep 2026 31 Dec 2029 Not published

DLD figures come from the register as republished by Continental Club and Mitchells Commercial Realty (September and October 2026). The DLD land area for these towers is Madinat Dubai Almelaheyah. The same land area also covers Mina Rashid buildings marketed as part of Rashid Yachts and Marina, such as Seascape, registered for 30 November 2026.

How the Dubai Maritime City completion date has changed

Date What happened Source
2022 Anwa by Omniyat completed, the first residential tower Bayut
25 Sep 2025 Riva Residence registered completion date DLD via Mitchells
22 Dec 2025 Riva Residence recorded 100% built, three months after its registered date DLD via Mitchells
31 Jan 2026 Anwa Aria’s registered date passes, at 73.54% by July DLD via Mitchells
24 Mar 2026 Beyond reports Saria at 10.32%, completion expected Q1 2028 Beyond via Zawya
30 Jul 2026 Danube lists Oceanz 1 to 3 among projects to hand over within 12 months Danube via GoDubai
Sep 2026 Latest registered dates on file: 31 Dec 2029 DLD via Continental Club

Saria shows how dates can differ: the DLD register gives 1 October 2027, Bayut Q3 2027, and Beyond itself Q1 2028.

What the Dubai Maritime City dates mean for payments

Each developer sets its own plan. Mar Casa asks 12% at booking with instalments linked to construction (Real Estate Club Dubai), so the remaining payments follow the building’s progress rather than the 31 October 2026 date on file. For towers with no registered completion date filed, such as Nautica, Oceanz 1 and Coral Reef, the SPA is the only document that fixes when the handover payment falls due.

What to check before relying on a Dubai Maritime City date

  1. Whether the tower is in Dubai Maritime City or Mina Rashid. Both sit in the DLD land area Madinat Dubai Almelaheyah.
  2. Which Oceanz or Chelsea building a unit is in. Oceanz 1 and Oceanz 3 were about 30 points apart in August 2026.
  3. Passed registered dates. Anwa Aria’s 31 January 2026 date and Mar Casa’s 31 October 2026 date sit well ahead of their build progress.
  4. The developer’s own date. Beyond and Danube have both given dates that differ from portals and the register.

Questions buyers also ask

When will Dubai Maritime City be completed?

There is no single date. Towers on the DLD register carry completion dates from 31 October 2026 (Mar Casa) to 31 December 2029 (Chelsea Residences and Prestige One Residences). DP World has not published an end date for the district.

Has Riva Residence been completed?

Yes, on the DLD register. Riva Residence by Vakson was recorded 100% built at the inspection of 22 December 2025, against a registered completion date of 25 September 2025 (Mitchells, 5 October 2026).

Will Mar Casa be ready by October 2026?

It is unlikely. Mar Casa by Deyaar is registered for 31 October 2026 but was 56.45% built at the DLD inspection of 4 August 2026.

When will Oceanz by Danube be completed?

Bayut lists Q1 2027, and Danube's July 2026 statement named Oceanz 1 to 3 among projects to hand over within 12 months. DLD inspections in August 2026 put Oceanz 1 at 50.04%, Oceanz 2 at 42.03% and Oceanz 3 at 20.64%, and Oceanz 1 has no registered completion date filed.