Anwa Aria by Omniyat in Dubai Maritime City: 84.86% built in September 2026, Omniyat now gives Q4 2027 and the DLD completion date of 31 January 2026 has passed. Prices and payment plan.
Short answer
Omniyat now gives Q4 2027 for Anwa Aria by Omniyat, while the DLD register still shows a completion date of 31 January 2026, which has passed. A DLD inspection on 30 September 2026 recorded the tower 84.86% complete, up from 73.54% in July. At launch in mid 2023 the handover was marketed for 2026. Prices started from about AED 1.02 million for a studio, and 40% is due on handover.
- Status
- under construction
- Handover date
- Omniyat states Q4 2027; DLD registered completion date 31 Jan 2026 (passed); Property Finder lists Q4 2026
- Construction
- 84.86% complete (DLD inspection, 30 Sep 2026)
- Payment plan
- 15% on booking, 45% during construction, 40% on handover
- Starting price
- From about AED 1.02 million (studio); 1 bedrooms from AED 2.4 million at launch in 2023
Construction progress
84.86%
DLD inspection, 30 Sep 2026
Developer's completion date
Q4 2027
Omniyat project page, accessed 11 Oct 2026
DLD registered completion date
31 Jan 2026, passed
DLD project register via Continental Club
Median registered price, 1 bedroom
AED 2.41 million
70 sales, Continental Club, transactions updated 7 Oct 2026
When will Anwa Aria by Omniyat be handed over?
Omniyat’s project page now gives completion in Q4 2027 for Anwa Aria by Omniyat, and Bayut lists the same quarter. Property Finder still lists Q4 2026. The Dubai Land Department (DLD) register, where the project appears as Anwa Aria By Omniyat, project 2726, holds a completion date of 31 January 2026, which passed with the tower unfinished.
The tower was 84.86% complete at the DLD inspection on 30 September 2026. At launch in mid 2023 it was marketed for a 2026 handover, with sources split between Q1 2026 (Data Habibi) and Q4 2026 (Metropolitan). Data Habibi counts the move to Q4 2027 as a 23 month delay.
Building-by-building dates and how the date has changed: Anwa Aria by Omniyat handover date.
Anwa Aria by Omniyat construction update
The register records construction starting on 14 August 2023 and eight inspections so far.
| Date | Recorded progress | Source |
|---|---|---|
| Dec 2025 (portal update) | 51.56% | Property Finder |
| 3 Jul 2026 | 73.54% | DLD register via Continental Club and HomeSearch |
| 30 Sep 2026 | 84.86% | DLD register via Continental Club |
The tower added 11.32 points between July and September 2026, about 3.6 points a month. Continental Club projects 100% around February 2027 at that pace, which would be well ahead of Omniyat’s Q4 2027 date. Construction percentage does not include the time needed for completion certificates and handover. The escrow account is held at ADCB.
Anwa Aria by Omniyat homes and sizes
Omniyat lists 175 residences across 30 levels, including 14 townhouses and 2 penthouses. The DLD register lists 192 units in one building of a ground floor, four podium levels and 32 floors, with retail included (HomeSearch; Continental Club).
| Home type | Size | Units (DLD) |
|---|---|---|
| Studio | 387 to 487 sq ft | 43 |
| 1 bedroom | 828 to 976 sq ft | 66 |
| 2 bedroom | 1,451 to 1,680 sq ft | 63 |
| 3 bedroom, incl. townhouses and duplexes | 2,408 to 6,553 sq ft | 17 |
| 4 bedroom | 4,740 to 4,772 sq ft | 2 |
Sizes and unit counts are from the DLD register via Continental Club. Omniyat’s own ranges run to 5,628 sq ft for 3 bedroom townhouses and 6,929 sq ft for penthouses.
Anwa Aria by Omniyat prices and resale
Metropolitan reported 1 bedrooms from AED 2.4 million at the 2023 launch. Data Habibi lists studios from about AED 1.02 million. Property Finder marks the project sold out from the developer.
The DLD register shows 163 sales, about 1% of them resales. Median registered prices are AED 1,201,328 for a studio of about 463 sq ft, AED 2,409,984 for a 1 bedroom of about 936 sq ft and AED 4,322,880 for a 2 bedroom of about 1,539 sq ft, about AED 2,631 per sq ft overall (Continental Club, DLD transactions updated 7 October 2026). On 5 October 2026 a 1 bedroom of about 936 sq ft registered at AED 2,426,990 and a 2 bedroom of about 1,662 sq ft at AED 4,322,880. Property Finder lists a 445 sq ft studio sold for AED 1,100,000 on 12 December 2025.
Anwa Aria by Omniyat payment plan
The plan is 15% on booking, 45% during construction and 40% on handover, sold as 60/40 (Bayut; Property Finder; Continental Club). There is no post-handover plan. On a 1 bedroom at the median AED 2,409,984, the handover payment is about AED 964,000. With the building at 84.86%, most of the construction instalments have fallen due.
Anwa Aria by Omniyat developer and delivery record
Omniyat is a Dubai developer known for high value towers on Palm Jumeirah and in Business Bay. The DLD register lists Anwa Aria under Blue Star Real Estate Development. Its first Dubai Maritime City tower, Anwa, launched in December 2014 with a Q2 2020 handover target (Arabian Business, June 2019) and was completed in 2022, the first residential tower in Dubai Maritime City. On Palm Jumeirah, Orla by Omniyat is registered for 31 December 2026, with Omniyat targeting completion in early 2027.
What to check before buying at Anwa Aria by Omniyat
- The completion date in the SPA and how far its grace period runs, since the registered 31 January 2026 date has passed.
- Which date the seller quotes, Q4 2026, early 2027 or Q4 2027, for a resale with a 40% handover payment still due.
- Whether the unit is in the tower or a podium townhouse or duplex, as layouts and sizes vary widely.
- The next DLD inspection, to see whether the 3.6 point monthly pace holds above 90%.
Anwa Aria by Omniyat location: Dubai Maritime City, Dubai
Map shows the area. Check the exact plot in the developer's site plan or the DLD project record. Check any project's DLD status.
Questions buyers also ask
What is the Anwa Aria by Omniyat handover date?
Omniyat's project page gives completion in Q4 2027, and Bayut lists Q4 2027. Property Finder lists Q4 2026. The DLD register's completion date of 31 January 2026 has passed. The tower was 84.86% complete on 30 September 2026.
What is the Anwa Aria completion date?
The registered completion date is 31 January 2026 for DLD project 2726, and it has passed with the tower unfinished. Omniyat's current date is Q4 2027. At the July to September 2026 pace, Continental Club projects 100% in early 2027.
What is the Anwa Aria by Omniyat price?
Studios started from about AED 1.02 million (Data Habibi), and 1 bedrooms from AED 2.4 million at launch in 2023 (Metropolitan). Median registered prices are AED 1,201,328 for a studio, AED 2,409,984 for a 1 bedroom and AED 4,322,880 for a 2 bedroom (Continental Club, 7 Oct 2026).
What is the Anwa Aria by Omniyat payment plan?
15% on booking, 45% during construction and 40% on handover, often called 60/40 (Bayut; Property Finder; Continental Club).
Is Anwa Aria the same as Anwa?
No. Anwa by Omniyat is the earlier tower in Dubai Maritime City, completed in 2022. Anwa Aria is a separate, newer tower, marketed at launch in 2023 as Anwa II.