Handover date

When is the Golf Residences by Prestige One handover date?

Updated 11 October 2026 Golf Residences by Prestige One

Short answer

The DLD register holds a completion date of 16 February 2028 for Golf Residences by Prestige One, and Prestige One gives February 2028. The latest DLD inspection, on 10 August 2026, recorded 35.74% progress. At the 2.65 points a month achieved over the past year, Continental Club projects 100% around 18 August 2028, about six months after the registered date, and early listings had quoted Q3 2027.

Registered completion date

16 Feb 2028

DLD project register via Continental Club

Latest DLD construction progress

35.74%

DLD inspection, 10 Aug 2026

Developer's stated date

February 2028

Prestige One, accessed 11 Oct 2026

Portal date at earlier listings

Q3 2027

UAE-Prop, accessed 11 Oct 2026

Golf Residences by Prestige One handover date: the latest position

The DLD register holds a completion date of 16 February 2028 for Golf Residences by Prestige One, and Prestige One gives February 2028, which it says is the date in the project’s disclosure documents. Full project details are on the Golf Residences by Prestige One page.

The tower was 35.74% complete at the DLD inspection on 10 August 2026. Progress has been steady, but slower than the date needs. Continental Club measures 2.65 points a month over the past year and projects 100% around 18 August 2028 at that pace. Reaching 100% by 16 February 2028 would need about 3.6 points a month from the August inspection. Prestige One’s nearby Vista building in Dubai Sports City handed over in April 2026, a few months after its estimated 2025 completion (Gulf News; Propsearch).

Golf Residences by Prestige One handover date by building

The project is one G+3P+19+R tower with 226 homes.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Golf Residences by Prestige One (226 units, DLD project 3131) 35.74% (10 Aug 2026) 16 Feb 2028 February 2028 (Prestige One); Q1 2028 (HomeSearch); Q3 2027 (UAE-Prop)

All 226 homes are in the same building and share the same registered date.

How the Golf Residences by Prestige One handover date has changed

Date Event Source
2024 Launch; portal listings quote Q3 2027 Prestige One, UAE-Prop
9 Dec 2024 Registered construction start (Prestige One gives 16 January 2025) DLD register, Prestige One
19 Sep 2025 DLD inspection: 7.49% DLD register via Continental Club
20 Apr 2026 DLD inspection: 25.13% DLD register via Continental Club
10 Aug 2026 DLD inspection: 35.74%; registered completion 16 February 2028 DLD register via Continental Club
Oct 2026 Prestige One page gives February 2028 Prestige One

The project’s date has moved from 2027 to February 2028 since launch. Progress picked up in 2026, with 10.61 points added between April and August.

What the Golf Residences by Prestige One handover date means for payments

Prestige One’s current indicative plan puts 60% of the price on handover, after 20% down and 20% during construction. Earlier releases appear on portals with 35% on handover (20/45/35, Data Habibi) or 70% (30/70, UAE-Prop). On the median 2 bedroom DLD sale of AED 1,710,800, a 60% handover payment is about AED 1.03 million and a 35% payment about AED 599,000. If completion slips toward August 2028, that payment moves with it.

What to check before relying on the Golf Residences by Prestige One date

  1. The date in the SPA. Buyers from the 2024 launch may hold contracts that quote 2027.
  2. The grace period the SPA allows after the completion date, given the gap between the current pace and February 2028.
  3. The share due at handover under the specific plan signed, since splits range from 35% to 70%.

Questions buyers also ask

What is the Golf Residences by Prestige One completion date?

The DLD register holds 16 February 2028 (DLD project 3131), via Continental Club with the registry updated 8 October 2026. Prestige One gives February 2028 and says this is the date in the project's disclosure documents.

How far along is Golf Residences by Prestige One?

35.74% at the DLD inspection on 10 August 2026, up from 25.13% on 20 April 2026 and 7.49% on 19 September 2025.

Will Golf Residences by Prestige One be ready on time?

The public figures point to a tight finish. Reaching 100% by 16 February 2028 needs about 3.6 points a month from August 2026. Continental Club measures 2.65 points a month over the past year, which would take the tower to 100% around 18 August 2028.

Has the Golf Residences by Prestige One handover date been delayed?

Listings from the 2024 launch period quoted Q3 2027 (UAE-Prop), and Data Habibi reports an earlier DLD record with completion in 2027. Prestige One and the DLD register now both give February 2028.

Sources

  1. Mitchells, Golf Residences by Prestige One DLD registry and sales (opens in a new tab)mitchellscommercialrealty.com · register as at 4 Oct 2026
  2. Propsearch, Vista by Prestige One (opens in a new tab)propsearch.ae · accessed 11 Oct 2026
Request a Unit Review