Illustration: construction cranes on a residential tower at dusk
Handover date

When is The One by Prestige One handover date?

Updated 11 October 2026 The One by Prestige One

Short answer

The One by Prestige One, an office building in Barsha Heights, has a registered completion date of 30 June 2027 in the Dubai Land Department project register, and Prestige One gives June 2027. The DLD inspection of 16 September 2026 recorded 7.03% complete. Launch material in 2024 quoted Q4 2026, and with about 93% of the work left nine months before the registered date, the timetable is tight.

Registered completion date (DLD)

30 Jun 2027

DLD project register via Continental Club, registry updated 5 Oct 2026

Latest construction progress

7.03%

DLD inspection, 16 Sep 2026

Developer's stated date

June 2027

Prestige One project page, accessed 11 Oct 2026

Date quoted at launch

Q4 2026

Grand Reve Realty; Tanami Properties; DXB Off Plan

The One by Prestige One handover date: the latest position

The One by Prestige One has a registered completion date of 30 June 2027 in the Dubai Land Department (DLD) project register, and Prestige One’s project page gives June 2027, citing the project’s disclosure documents. The DLD inspection of 16 September 2026 recorded 7.03% complete. Full project details are on The One by Prestige One page.

The date itself matches across the developer and the register. The gap is in progress: about 93% of a 14 floor building with three basements remained at mid-September 2026, and the last quarter added less than half a point.

The One by Prestige One handover date by building

The One is a single office building of 41 units.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
The One by Prestige One (41 units) 7.03% (16 Sep 2026) 30 Jun 2027 June 2027 (Prestige One); Q2 2027 (ezre)

Figures from the DLD register via Continental Club, registry updated 5 October 2026. The building is registered as 3B+G+14+R in Al Thanyah First.

How The One by Prestige One handover date has changed

Date What was stated Source
2024 Launch; brokers quote Q4 2026 handover Prestige One; Grand Reve Realty; Tanami Properties
1 Jan 2025 Registered construction start; completion date 30 June 2027 DLD register via Continental Club
8 May 2026 A broker page still quotes December 2026 Aigents Realty
11 Jun 2026 DLD inspection at 6.54% DLD register via Continental Club
16 Sep 2026 DLD inspection at 7.03%; date unchanged DLD register via Continental Club
Oct 2026 Prestige One gives June 2027 Prestige One project page

The register has carried 30 June 2027 since construction was recorded as starting. Marketing dates moved from Q4 2026 to June 2027, a shift of about six months.

What The One by Prestige One handover date means for payments

The launch plan was 20% on booking, 45% in nine quarterly instalments of 5% over 27 months, and 35% on completion (DXB Off Plan). Those instalments are time-based, so a buyer who booked at launch would have paid most of the 65% before the building is finished, whatever the pace on site. The final 35% moves with the completion date. Prestige One’s page labels that 35% as post-handover, while brokers describe it as due on completion.

What to check before relying on The One by Prestige One date

  1. The SPA date and grace period. Contracts signed in 2024 may carry Q4 2026.
  2. The pace on site. Reaching 100% by 30 June 2027 would need about 30 points a quarter, against 0.49 points between June and September 2026.
  3. When the final 35% is due, on completion or after handover, as sources differ.

Questions buyers also ask

What is The One by Prestige One completion date?

30 June 2027, the completion date for DLD project 3332, The One By Prestige One (via Continental Club).

Has The One by Prestige One handover date been delayed?

Yes, against launch material. Brokers quoted Q4 2026 in 2024. Prestige One's page now gives June 2027, matching the DLD register.

Is The One by Prestige One finished?

No. It was 7.03% complete at the DLD inspection of 16 September 2026, up from 6.54% on 11 June 2026.

When did construction of The One by Prestige One start?

The DLD register records a construction start on 1 January 2025.

Sources