Handover date

When is the Berkeley Square by Prestige One handover date?

Updated 11 October 2026 Berkeley Square by Prestige One

Short answer

Berkeley Square by Prestige One has a registered completion date of 30 March 2028 in the DLD project register, and Prestige One gives March 2028. The DLD inspection on 25 June 2026 recorded 3% complete. With about 21 months left, the building needs a fast pace to meet the date, and the SPA grace period is the main thing to check.

Registered completion date (DLD)

30 Mar 2028

DLD project register via Continental Club and Data Dubai, accessed 11 Oct 2026

Latest construction progress

3%

DLD inspection, 25 Jun 2026

Developer's stated date

March 2028

Prestige One, Berkeley Square North page

Date change since launch

None

Q1 2028 at the July 2025 launch (Dubai Housing)

Berkeley Square by Prestige One handover date: the latest position

Berkeley Square By Prestige One is registered with the Dubai Land Department for completion on 30 March 2028. Prestige One’s project page says handover is anticipated in March 2028, as stated in its disclosure documents. Full project details are on the Berkeley Square by Prestige One page.

The DLD inspection on 25 June 2026 recorded 3%. The building is low-rise, at two basements, ground and five floors, so it needs less time than a tower, but 97% of the work remained with 21 months to go.

Berkeley Square by Prestige One handover date by building

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Berkeley Square By Prestige One (DLD project 3847, 241 units) 3% (25 Jun 2026) 30 Mar 2028 March 2028 (Prestige One, for North); Q1 2028 (portals)
Berkeley Square South No separate DLD record found Not found Q1 2028 (WeNest)

Prestige One markets the scheme as two buildings, North and South. Its North page gives 241 homes, which matches the DLD record. Broker pages for South also quote 241 units and Q1 2028, so it is unclear whether South is a second building or another name for the same release.

How the Berkeley Square by Prestige One handover date has changed

Date Event Source
24 Jun 2025 Expressions of interest open at AED 20,000 per unit Wady Properties
26 Jun 2025 First DLD inspection, 0% Data Dubai
1 Jul 2025 Bookings open and registered construction start; completion Q1 2028 Dubai Housing; DLD register
25 Jul 2025 Project registered with DLD, completion 30 Mar 2028 Data Dubai
21 Nov 2025 DLD inspection, 0% Data Dubai
25 Jun 2026 DLD inspection, 3% Data Dubai
Oct 2026 Register still shows 30 Mar 2028 Continental Club; Data Dubai

The date has held since launch. The slow start is the point to watch: no progress was recorded in the first 11 months, and 3% in the first year.

What the Berkeley Square by Prestige One handover date means for payments

On the standard plan, 20% is paid on booking and 45% in eight instalments between 3 and 24 months after booking, on fixed dates. Buyers who booked in July 2025 will have paid 65% by mid 2027, before most of the building is complete. The final 35% is due on completion.

On the post-handover plan, 10% is due on completion and 35% follows at 1% a month for 35 months. If completion slips past March 2028, the start of those monthly payments slips with it.

What to check before relying on the Berkeley Square by Prestige One date

  1. Which building is named in the SPA, North or South, and the date for it.
  2. The grace period after 30 March 2028, given 3% progress in June 2026.
  3. Progress before the last fixed-date instalments. The Dubai REST app shows the DLD percentage for project 3847.

Questions buyers also ask

When will Berkeley Square by Prestige One be ready?

The DLD register sets 30 March 2028 as the completion date, and Prestige One says March 2028. The building was 3% complete on 25 June 2026.

What is the Berkeley Square completion date?

30 March 2028, as filed with DLD under project number 3847 (Data Dubai, data through 29 Sep 2026).

Has the Berkeley Square handover date been delayed?

No change has been recorded. Dubai Housing gave Q1 2028 when bookings opened on 1 July 2025, and both DLD and Prestige One still show March 2028. Progress reached 3% only at the June 2026 inspection.

When will Berkeley Square South be ready?

Broker pages give Q1 2028 for Berkeley Square South too (WeNest). The DLD record found covers 241 units, the count Prestige One gives for Berkeley Square North, and no separate DLD date for South appears in the sources checked.

Sources

  1. Prestige One, Berkeley Square North (opens in a new tab)prestigeone.ae · accessed 11 Oct 2026
  2. WeNest, Berkeley Square South (opens in a new tab)wenestre.com · accessed 11 Oct 2026
Request a Unit Review