
When is the Sera Gardens by Vision handover date?
Short answer
Sera Gardens by Vision has a registered completion date of 1 April 2028, and Property Finder lists April 2028. The last published DLD inspection, on 7 April 2026, recorded 0%, ahead of a registered construction start on 1 August 2026. The date has moved later since pre-launch estimates of Q4 2027, so the date written in an early buyer's SPA may differ from the register.
Registered completion date (DLD)
1 Apr 2028
DLD register via Continental Club
Latest construction progress
0%
DLD inspection, 7 Apr 2026
Registered construction start
1 Aug 2026
DLD register via Dubai Data
Pre-launch estimate
Q4 2027
Propsearch, updated 31 May 2026; Proprain
Sera Gardens by Vision handover date: the latest position
Sera Gardens by Vision is registered with the Dubai Land Department (DLD) for completion on 1 April 2028. Property Finder lists the same month. Before launch, Propsearch and agents gave an estimated Q4 2027. Full project details are on the Sera Gardens by Vision page.
The project is at the very start of construction. The only published DLD inspection, on 7 April 2026, recorded 0%, and the register gives 1 August 2026 as the construction start. No newer inspection had been published by 30 September 2026.
Sera Gardens by Vision handover date by building
Sera Gardens is one building in Me’aisem First, Dubai Production City, registered as DLD project 4455 under the name Sera Gardens By Vision. The escrow account is held at The National Bank of Fujairah, and Vision’s own project page still showed the building as coming soon in October 2026.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Sera Gardens by Vision (G+P+8+R, 246 apartments) | 0% (7 Apr 2026) | 1 Apr 2028 | Apr 2028 (Property Finder); Q1 2028 (JRE); Q4 2027 before launch |
How the Sera Gardens by Vision handover date has changed
| Date | What happened | Source |
|---|---|---|
| Feb 2026 | First trace of the project; estimated handover Q4 2027 | Propsearch |
| 7 Apr 2026 | DLD inspection, 0% | DLD register via Continental Club |
| 6 May 2026 | Registered with the DLD, completion date 1 Apr 2028 | DLD register via Dubai Data |
| 13 May 2026 | Vision publicises Sera by Vision | Vision Developments, LinkedIn |
| Jun 2026 | First registered sales, 16 in the month | Dubai Data |
| 1 Aug 2026 | Registered construction start | DLD register |
| 11 Oct 2026 | Property Finder lists April 2028 | Property Finder |
The change happened at registration. Pre-launch estimates of Q4 2027 gave way to a registered date of 1 April 2028, and the portals have since moved to match. Vision’s own project page gives no handover date (accessed 11 October 2026).
What the Sera Gardens by Vision handover date means for payments
Sera Gardens is sold on a 20/80 plan: 20% on booking and 80% on handover (Property Finder and Proprain). With the median registered price at AED 960,000, the handover payment on a typical unit is about AED 768,000. That sum falls due when the building is handed over, so any change to the date moves the bulk of each buyer’s payment.
What to check before relying on the Sera Gardens by Vision date
- The anticipated completion date in the SPA, which may differ for buyers who reserved on Q4 2027 marketing.
- The grace period in the SPA beyond that date.
- A mortgage pre-approval that will still be valid in 2028, since 80% of the price is due at handover.
Questions buyers also ask
When will Sera Gardens by Vision be completed?
The DLD register gives 1 April 2028, and Property Finder lists April 2028. JRE lists Q1 2028 and some agents still show the pre-launch estimate of Q4 2027.
Has construction started at Sera Gardens by Vision?
The register gives a construction start of 1 August 2026. The only published DLD inspection, on 7 April 2026, recorded 0%, and no later figure had been published by 30 September 2026 (Dubai Data).
Has the Sera Gardens by Vision handover date been delayed?
The registered date of 1 April 2028 is later than the Q4 2027 given before launch, by about one to two quarters. Since registration in May 2026 the date has not changed.
How many homes are in Sera Gardens by Vision?
246 apartments in one building of ground, podium, eight residential floors and roof (DLD register and Vision Developments).
