Handover date

When is the Jumeirah Asora Bay handover date?

Updated 1 October 2026 Jumeirah Asora Bay

Short answer

The Jumeirah Asora Bay handover date is 31 March 2029, the registered completion date on the Dubai Land Department (DLD) register for the residences and the neighbouring hotel, and Property Finder, Bayut and Propsearch all give Q1 2029 or March 2029. The DLD site inspection of 12 August 2026 put construction at 4.40% complete, up 0.39 points since 21 May 2026. Meraas says marine works and piling are done and foundations come next, so almost all of the building remains to be built in the 31 months to the registered date.

Registered completion date (DLD)

31 Mar 2029

DLD register, project 3445, via Continental Club, 8 Sep 2026

Latest construction progress

4.40%

DLD site inspection, 12 Aug 2026

Portal date

Q1 2029

Property Finder, Bayut, Propsearch, accessed 1 Oct 2026

Date change since launch

None announced

Property Finder, construction start 1 May 2025, completion 31 Mar 2029

Jumeirah Asora Bay handover date: the latest position

Jumeirah Asora Bay is registered for completion on 31 March 2029. That is the date the Dubai Land Department holds for project number 3445, which covers the 29 Jumeirah Residences and the Jumeirah Asora Bay hotel next to them. Property Finder lists the same expected completion, and Bayut, Propsearch and DataHabibi give Q1 2029 or March 2029. More on prices and sizes is on the Jumeirah Asora Bay page.

The DLD site inspection of 12 August 2026 recorded the project 4.40% complete, 15 months after the registered construction start of 1 May 2025. Progress rose 0.39 points from the inspection of 21 May 2026. Meraas’s project page says marine works and piling are finished and foundation works are due to start next, as the project moves into main construction. That leaves almost the whole building to go up in the 31 months between the August inspection and 31 March 2029.

Jumeirah Asora Bay handover date by building

The DLD register counts two buildings under one project number, one progress figure and one registered date. The Ocean Mansions are marketed separately.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Jumeirah Residences Asora Bay (ground plus 11, 29 homes) 4.40%, whole project, 12 Aug 2026 31 Mar 2029 Q1 2029 (Property Finder, Bayut, Propsearch)
Jumeirah Asora Bay hotel (ground plus 7, 103 rooms, 20 hotel villas) 4.40%, whole project, 12 Aug 2026 31 Mar 2029 Not sold as homes
Ocean Mansions Not published separately Not published separately Jun 2029 (JRE)

Building descriptions are from the developer’s filing on the DLD register, via Continental Club. Sources disagree on the mansions: JRE lists three seven bedroom mansions, while OffPlan Insider counts six Ocean Mansions of four to seven bedrooms.

How the Jumeirah Asora Bay handover date has changed

The date has not moved since launch.

Date What happened Source
Late Apr 2025 Meraas opened sales, with completion due in March 2029. Property Finder; DataHabibi
1 May 2025 Registered construction start on the DLD register. DLD register
8 Dec 2025 Property Finder marked the residences sold out from the developer. Property Finder
21 May 2026 About 4.01% complete at the DLD site inspection. DLD register, via Continental Club
12 Aug 2026 4.40% complete at the DLD site inspection. Registered completion date 31 March 2029. DLD register, via Continental Club
Sep 2026 Continental Club’s project summary shows Q4 2030, while the DLD extract on the same page still states 31 March 2029. Continental Club

No Meraas statement giving a date later than March 2029 was found as of 1 October 2026.

What the Jumeirah Asora Bay handover date means for payments

The published plan is 20% at booking, 40% during construction and 40% on handover. That makes the handover payment as large as all the construction instalments combined. On the AED 48.96 million 4 bedroom sale registered on 14 May 2026, 40% is about AED 19.6 million. On the AED 65 million sale of 5 August 2026, it is AED 26 million.

Because the 40% is tied to handover, any change to the 31 March 2029 date moves the timing of the largest single payment. One tracker lists a 10/40/50 split instead, so the plan in each SPA is the one that applies.

What to check before relying on the Jumeirah Asora Bay date

  1. Whether your home is a residence or an Ocean Mansion. The registered 31 March 2029 date applies to project 3445. No separate registered date for the mansions was found, and one portal gives June 2029.
  2. The completion date and grace period in your SPA, since 40% of a price above AED 45 million falls due on that date.
  3. The next DLD inspection for project 3445. At the August 2026 inspection, foundations had not started, and later inspections will show how fast the building rises.
  4. For a resale purchase, how much the seller has paid. The seller has typically paid the 20% booking amount and part of the 40% construction share, and the buyer takes on the rest.

Questions buyers also ask

What is the Jumeirah Asora Bay completion date?

31 March 2029. That is the registered completion date for DLD project number 3445, which covers the residences and the Jumeirah Asora Bay hotel (Continental Club, DLD data, 8 Sep 2026). Property Finder lists the same expected completion, and Bayut and Propsearch give Q1 2029 and March 2029.

Is Jumeirah Asora Bay finished?

No. The DLD site inspection of 12 August 2026 put the project at 4.40% complete. Meraas says marine works and piling are complete and foundation works are due to start next.

Has the Jumeirah Asora Bay handover date been delayed?

Meraas has not announced a change, and Property Finder, Bayut, Propsearch and DataHabibi still give Q1 2029 (accessed 1 Oct 2026). One tracker, Continental Club, shows Q4 2030 in its project summary, but the DLD extract on the same page still states 31 March 2029.

When will the Jumeirah Asora Bay Ocean Mansions be ready?

JRE lists the Ocean Mansions with a June 2029 completion, three months after the registered date for the residences. OffPlan Insider, Meraas's marketing partner, counts six Ocean Mansions where JRE lists three. No separate DLD registered date for the mansions was found.

How much is due at the Jumeirah Asora Bay handover?

40%. The published plan is 20% at booking, 40% during construction and 40% on handover (Property Finder, Bayut, Propsearch). On the AED 48.96 million sale registered on 14 May 2026, the handover payment would be about AED 19.6 million.

Sources

  1. DataHabibi, Jumeirah Asora Bay (opens in a new tab)datahabibi.ae · accessed 1 Oct 2026
  2. OffPlan Insider, Jumeirah Asora Bay (opens in a new tab)offplaninsider.com · accessed 1 Oct 2026
Request a Unit Review