Handover date

When is the Sobha Central handover date?

Updated 12 October 2026 Sobha Central

Short answer

Sobha lists a handover date of December 2029 for The Horizon, The Serene and The Tranquil, and December 2030 for The Mirage and The Pinnacle (Sobha Realty, accessed 1 October 2026); The Eden is shown for December 2029 on other sales listings. The DLD register files Sobha Central as three projects: Phase I and Phase II, with registered completion dates of 30 June 2030, and project 4328, with 31 December 2031. The latest DLD inspection, on 29 September 2026, put Phase I at 7.08% complete and Phase II at 6.42%, up from 2.76% and 2.34% in March 2026. The register does not name the towers, so which registered date applies depends on the project a unit is filed under.

Registered completion date (DLD), Phase I and Phase II

30 Jun 2030

DLD register via Mitchells, accessed 1 Oct 2026

Latest construction progress, Phase I

7.08%

DLD inspection, 29 Sep 2026; Phase II 6.42%

Sobha's date, first four towers

Dec 2029

Sobha Realty; The Mirage and The Pinnacle Dec 2030

Project 4328, registered completion date

31 Dec 2031

DLD register via Dubai Handover, accessed 1 Oct 2026

Sobha Central handover date: the latest position

Sobha gives each Sobha Central tower its own handover date: December 2029 for The Horizon, The Serene and The Tranquil, and December 2030 for The Mirage and The Pinnacle. The Eden has no date on Sobha’s page and is listed for December 2029 on the Sobha Central sales site. More on the development: Sobha Central.

On the DLD register, Sobha Central is three projects that do not use the tower names. Phase I and Phase II are registered for completion on 30 June 2030, and project 4328 on 31 December 2031. The last DLD inspection of Phase I and Phase II, on 29 September 2026, recorded 7.08% and 6.42%. Project 4328 was at 0% in January 2026.

Sobha Central handover date by building

Registered project Construction progress (DLD, date) Registered completion date Developer or portal date
Phase I, project 3713 (2 buildings, 2,383 homes) 7.08%, 29 Sep 2026 30 Jun 2030 Q2 2030 (Augusta Properties)
Phase II, project 4042 (2 buildings, 2,143 homes) 6.42%, 29 Sep 2026 30 Jun 2030 Q2 2030 (Augusta Properties)
Project 4328 (2,169 units, 101 floors) 0%, 16 Jan 2026 31 Dec 2031 Not published

Sobha’s own dates are published by tower:

Tower Sobha’s handover date Other published dates
The Horizon Dec 2029 (anticipated completion 31 Dec 2029) Dec 2029 (Property Finder)
The Eden Not shown Dec 2029 (Sobha Central sales site)
The Serene Dec 2029 30 Dec 2029 (PropertyStellar)
The Tranquil Dec 2029 Dec 2029 (Sobha Central sales site)
The Mirage Dec 2030 Q1 2030 (Property Finder, via HCO)
The Pinnacle Dec 2030 Q4 2030 (Springfield Properties)

Sobha has not published which towers sit in which registered project. Phase I is filed as two buildings described as ground plus 75 floors, and Phase II as two buildings of ground plus 60 and ground plus 65 floors.

How the Sobha Central handover date has changed

Date What happened Source
14 May 2025 Sobha Central launches with The Horizon (1,225 homes); first tower slated for December 2029. Sobha Realty
1 Aug 2025 Phase I registered start, completion 30 June 2030. DLD register via Mitchells
1 Oct 2025 Phase II registered start, completion 30 June 2030. DLD register via Mitchells
10 Nov 2025 The Mirage launches (677 homes) after AED 3.5 billion of sales across the first towers. Sobha Realty
16 Jan 2026 Project 4328 inspected at 0%; registered start later set for 31 March 2026, completion 31 December 2031. DLD register via Dubai Handover
26 to 28 Mar 2026 Phase I 2.76%, Phase II 2.34%. DLD register via Mitchells
29 Sep 2026 Phase I 7.08%, Phase II 6.42%; registered completion still 30 June 2030. DLD register via Continental Club
1 Oct 2026 Sobha lists Dec 2029 for four towers and Dec 2030 for The Mirage and The Pinnacle. Sobha Realty

The Horizon’s December 2029 date has held since launch. Each later tower has been given a later date, rather than any tower being moved back.

What the Sobha Central handover date means for payments

Sobha’s standard plan for Sobha Central is 60/40: 20% at booking, 40% during construction and 40% on handover (Property Finder for The Horizon; Sobha Realty). On The Horizon’s launch price of AED 1.7 million for a 1 bedroom, the handover payment is AED 680,000. Augusta Properties reported a 20/80 offer on Sobha Central, 20% at booking and 80% on completion, valid until 27 September 2026, which puts most of the price on the handover date.

What to check before relying on the Sobha Central date

  1. Which registered project the unit is filed under. The SPA or Oqood shows the DLD project number: 3713 and 4042 carry 30 June 2030, and 4328 carries 31 December 2031.
  2. Whether the tower date and the registered date match. Sobha’s December 2029 towers are six months ahead of the 30 June 2030 registered dates for Phase I and Phase II.
  3. How much is due at completion. A unit bought on the 20/80 offer owes 80% at handover, against 40% on the standard plan.
  4. The next DLD inspection. The latest figures for Phase I and Phase II date from 29 September 2026 and for project 4328 from January 2026, and DLD’s project status enquiry shows new ones by project number.

Questions buyers also ask

What is the Sobha Central handover date?

Sobha lists December 2029 for The Horizon, The Serene and The Tranquil and December 2030 for The Mirage and The Pinnacle (Sobha Realty, accessed 1 October 2026). The DLD register gives 30 June 2030 for Phase I and Phase II and 31 December 2031 for project 4328.

What is the Sobha Central completion date?

The registered completion dates are 30 June 2030 for Sobha Central Phase I (2,383 homes) and Phase II (2,143 homes), and 31 December 2031 for project 4328 (2,169 units). Sobha's own anticipated completion date for The Horizon is 31 December 2029.

Which Sobha Central tower hands over first?

The Horizon, launched on 14 May 2025 as the first tower, with delivery slated for December 2029 (Sobha Realty). The Serene and The Tranquil carry the same December 2029 date on Sobha's site.

Has the Sobha Central handover date been delayed?

Sobha's date for The Horizon has not changed since launch: December 2029. Later towers carry later dates, December 2030 for The Mirage and The Pinnacle. Property Finder listed The Mirage for Q1 2030, earlier than Sobha's own December 2030.

How far along is Sobha Central construction?

Phase I was 7.08% complete and Phase II 6.42% at the DLD inspection of 29 September 2026, up from 2.76% on 26 March 2026 and 2.34% on 28 March 2026. Project 4328 was at 0% on 16 January 2026.

Sources

  1. Sobha Realty, Sobha Central (opens in a new tab)sobharealty.com · accessed 1 Oct 2026