Handover date

When is the Auresta Tower handover date?

Auresta Tower

How this page was made: figures from the DLD project register and the developer and portal pages listed under Sources, as at 19 October 2026. Text drafted with AI assistance from those sources. Every figure matched the fact records at the build on 12 November 2026. Not yet reviewed line by line by a person. How facts are checked

Short answer

The Auresta Tower completion date in the DLD project register is 31 December 2028, and Tiger Properties gives the same Q4 2028. A DLD inspection on 8 October 2026 recorded the tower 4.44% complete, up from 2% in July 2026. The date has held since launch, but the build would need to run several times faster than its pace so far to meet it.

Registered completion date (DLD)

31 Dec 2028

DLD project register via Continental Club, 16 Oct 2026

Latest construction progress

4.44%

DLD inspection, 8 Oct 2026

Developer's stated date

Q4 2028

Tiger via Continental Club; December 2028 on Property Finder

Progress in 2026

+4.44 points

0% on 8 Jan 2026 to 4.44% on 8 Oct 2026

Auresta Tower handover date: the latest position

The DLD project register holds 31 December 2028 as the completion date for Auresta Tower, Tiger Properties’ 63 floor tower in Jumeirah Village Circle (JVC). Tiger gives Q4 2028 and Property Finder lists December 2028. Prices, sizes and payment plans are on the Auresta Tower project page.

The DLD inspection on 8 October 2026 recorded the tower 4.44% complete. The date in the register has not changed since sales began, and Tiger has not announced a different one.

Auresta Tower handover date by building

Auresta Tower is a single building, so one date applies to all 840 registered units, including the offices and shops.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Auresta Tower (DLD project 3734) 4.44%, 8 Oct 2026 31 Dec 2028 Q4 2028 (developer via Continental Club); December 2028 (Property Finder)

The tower has three basements, a ground floor with retail, four parking floors, five office floors and 55 residential floors. The escrow account is with First Abu Dhabi Bank. Property Finder spells the address “Arista Tower”.

How the Auresta Tower handover date has changed

  • 30 April 2025: First DLD registered sale (Real Estate IQ).
  • 1 May 2025: Sales start and registered construction start, with completion set for December 2028 (Property Finder; DLD register).
  • 16 June 2025: First DLD inspection at 0%.
  • 30 June 2025: Project registered with DLD (Real Estate IQ).
  • 8 January 2026: DLD inspection still at 0%.
  • 27 July 2026: DLD inspection at 2%.
  • 8 October 2026: DLD inspection at 4.44%. The registered date is still 31 December 2028.

The date has stayed the same since launch. In the 17 months after the registered start, the tower reached 4.44%, all of it recorded in 2026. The most recent gain, 2.44 points in about ten weeks, is the fastest so far, at roughly 1 point a month. Finishing by 31 December 2028 would need about 3.6 points a month, and Continental Club’s own estimate from the inspections so far puts 100% far later.

What the Auresta Tower handover date means for payments

How much is tied to handover depends on the plan. On the 48 month plan offered in October 2026, 10% is due on handover and 50% is paid after it in instalments of about 3.1% every three months (OffPlan.ae). On the 10/30/60 plan, 60% falls due on handover. Early buyers on the 20/40/10/30 plan pay 10% on handover and 30% over the next 24 months (Tanami Properties). In each case the handover date sets when the largest payments begin.

What to check before relying on the Auresta Tower date

  1. The completion date and grace period in the SPA, compared with the 4.44% DLD figure.
  2. Which plan the unit was bought on, since the share due on handover ranges from 10% to 60%.
  3. New DLD inspections for project 3734, through the DLD project status service, to see whether the pace of late 2026 holds.

Questions buyers also ask

When will Auresta Tower be completed?

The registered completion date is 31 December 2028. The tower was 4.44% complete on 8 October 2026, so about 95% of the work remains for the 27 months to that date.

Has the Auresta Tower handover date been delayed?

No. The DLD register, Tiger and Property Finder all still give 31 December 2028 or Q4 2028, the date used since sales began on 1 May 2025.

Is Auresta Tower in JVC finished?

No. It was 4.44% complete at the DLD inspection on 8 October 2026. The site was still at 0% in January 2026.

When do post-handover payments start at Auresta Tower?

On the October 2026 plan, 50% of the price is paid over 48 months after handover; on early plans, 20% or 30% over 24 months. Those instalments begin only once the tower is handed over.