When is the Tiger Sky Tower handover date?
Short answer
Tiger Properties gives a Tiger Sky Tower handover date of Q4 2028, and Property Finder lists December 2028, but the DLD project register holds no completion date for the tower. The DLD inspection on 10 September 2026 recorded it 10.24% complete, up from 9.30% in May 2026. At launch in May 2024 Tiger gave Q2 2029, and the recorded pace is far slower than either date needs.
Registered completion date (DLD)
None on file
DLD project 2579, via Mitchell's, 18 Oct 2026
Latest construction progress
10.24%
DLD inspection, 10 Sep 2026
Developer's stated date
Q4 2028
Property Finder (December 2028) and Continental Club
Date at launch
Q2 2029
Tiger Group, 20 May 2024; Al Bayan, 27 May 2024
Tiger Sky Tower handover date: the latest position
Tiger Properties gives a handover date of Q4 2028 for Tiger Sky Tower, its 122 floor apartment tower in Business Bay, and Property Finder lists December 2028. The DLD project register has no completion date on file for the tower. Prices, sizes and payment plans are on the Tiger Sky Tower project page.
The DLD inspection on 10 September 2026 recorded the tower 10.24% complete. That leaves almost 90% of the work for the 27 months to December 2028. Property Finder still shows about 7%, a figure from the July 2025 inspection.
Tiger Sky Tower handover date by building
Tiger Sky Tower is a single building, so one date applies to all 849 registered units.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Tiger Sky Tower (DLD project 2579) | 10.24%, 10 Sep 2026 | None on file | Q4 2028 (developer via Continental Club; December 2028 on Property Finder); 2029 (Skyscraper Atlas) |
The DLD description is six basements, a ground floor, five podium floors, 109 floors and a roof. The escrow account is with Emirates NBD. The Arabic name in the register is برج تايجر سكاي (Mulki).
How the Tiger Sky Tower handover date has changed
- 1 May 2024: Sales start and registered construction start (Property Finder; DLD register).
- 14 May 2024: First DLD inspection at 2.76%.
- 20 to 27 May 2024: Tiger announces the tower with completion in Q2 2029 and handover to buyers from the second half of 2029, after about four years of building (Tiger Group; Al Bayan).
- 21 January 2025: DLD inspection at 5.84%.
- 4 July 2025: DLD inspection at 6.81%.
- 31 December 2025: DLD inspection at 7.29%.
- 21 May 2026: DLD inspection at 9.30%.
- 10 September 2026: DLD inspection at 10.24%. Listings now give Q4 2028.
The developer date is now about six months earlier than the one given at launch, while the build has run slowly. The tower gained 3.43 points between July 2025 and September 2026, about 0.25 points a month, and Continental Club puts the pace over the past year at 0.35 points a month. Reaching 100% by December 2028 would need about 3.3 points a month. Without a registered completion date, there is no DLD date against which a delay can be measured.
What the Tiger Sky Tower handover date means for payments
On the main plan, buyers pay 20% at booking and 40% during construction, then 10% on handover and 30% over the 24 months after it (Property Finder, Continental Club). On the 20/40/40 plan listed by Peak Trust, 40% falls due on handover. In both cases at least 40% of the price is tied to handover, so its timing sets when the largest payments fall.
What to check before relying on the Tiger Sky Tower date
- The completion date written in the SPA, since the DLD register has none on file and the marketing date has changed from Q2 2029 to Q4 2028.
- How construction instalments are scheduled, by calendar date or by DLD progress, given the slow pace recorded since 2024.
- New DLD inspections for project 2579, through the DLD project status service, and whether a completion date is registered.
Questions buyers also ask
When will Tiger Sky Tower be completed?
Tiger gives Q4 2028. The DLD register has no completion date on file. The tower was 10.24% complete on 10 September 2026, and at the pace of the past year it would need many more years than the developer date allows.
Has the Tiger Sky Tower handover date been delayed?
Not on paper. Tiger said in May 2024 that completion would be in Q2 2029, with handover from the second half of 2029. Listings in 2026 give an earlier Q4 2028. Progress since launch has been slow, about 7.5 points in 28 months.
Is Tiger Sky Tower finished?
No. It was 10.24% complete at the DLD inspection on 10 September 2026, with six basements, five podium floors and 109 tower floors planned.
When do post-handover payments start at Tiger Sky Tower?
On the main plan, 10% is due on handover and 30% over the 24 months after it. Those instalments begin only once the tower is handed over, so a later handover moves them later.