When is the Jade Tower handover date?
Short answer
The Jade Tower completion date in the DLD project register is 31 March 2027, and Property Finder lists the same Q1 2027 date. A DLD inspection on 2 October 2026 recorded the tower 11% complete, up from 9.43% in June 2026. With 89% of the work left, the March 2027 date is very likely to move, and Tiger has not yet published a revised one.
Registered completion date (DLD)
31 Mar 2027
DLD project register via Continental Club, 10 Oct 2026
Latest construction progress
11%
DLD inspection, 2 Oct 2026
Developer's stated date
Q1 to Q2 2027
Q1 2027 on Property Finder; Q2 2027 developer-supplied on Continental Club
Progress in six months
+3.4 points
7.64% on 1 Apr 2026 to 11% on 2 Oct 2026
Jade Tower handover date: the latest position
The DLD project register holds 31 March 2027 as the completion date for Jade Tower, Tiger Properties’ 28 floor apartment tower in Majan. Property Finder lists the same date, while Continental Club shows a developer-supplied Q2 2027. Prices, sizes and payment plans are on the Jade Tower project page.
The DLD inspection on 2 October 2026 recorded the tower 11% complete. That leaves 89% of the work for the under six months to the registered date. The date in the register has not been updated, and Tiger has not announced a new one.
Jade Tower handover date by building
Jade Tower is a single building, so one date applies to all 436 units.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Jade Tower (DLD project 3074) | 11%, 2 Oct 2026 | 31 Mar 2027 | Q1 2027 (Property Finder); Q2 2027 (developer via Continental Club) |
The tower has one basement, a ground floor, four parking floors, 28 residential floors and a roof.
How the Jade Tower handover date has changed
- 1 April 2024: Bookings open and registered construction start, with completion set for 31 March 2027 (Property Finder; DLD register).
- 3 May 2024: Construction start date given by Property Finder.
- 1 April 2026: DLD inspection at 7.64%.
- 18 June 2026: DLD inspection at 9.43%.
- 2 October 2026: DLD inspection at 11%. The registered date is still 31 March 2027.
The registered date has stayed the same since launch, but progress has not kept up with it. About 30 months after the registered start, the tower is about one ninth complete. In the six months to October 2026 it gained about 3.4 points, roughly 0.6 points a month. Continental Club now shows a developer-supplied Q2 2027, the only sign of the date sliding so far.
Sales have continued while the build runs late. DLD registrations in August and September 2026 included 1 bedrooms at AED 1.17 million to AED 1.27 million, above the 1 bedroom median of AED 852,324, and Continental Club counts only one resale among 210 registered sales.
What the Jade Tower handover date means for payments
Most Jade Tower buyers are on plans that run past handover. The main 70/30 plan takes 20% at booking and 50% during construction, then 30% over 24 months after handover. Releases listed in 2026 take only 10% on handover and 50% over 48 months after it (Home4You, ezre). Buyers on the 60/40 plan owe 40% on handover. In each case the handover date sets when the final instalments begin, so a delay pushes them later rather than cancelling them.
What to check before relying on the Jade Tower date
- The completion date and grace period in the SPA, compared with the 11% DLD figure.
- Whether construction instalments are linked to progress or to calendar dates, since the build is running far behind the March 2027 date.
- New DLD inspections for project 3074, through the DLD project status service, for any change in pace or a revised registered date.
Questions buyers also ask
When will Jade Tower be completed?
The registered completion date is 31 March 2027. The tower was 11% complete on 2 October 2026, so completion by that date is not realistic on the recorded pace, and a new date has not been published.
Has the Jade Tower handover date been delayed?
Not formally. The DLD register and Property Finder still show 31 March 2027, the date used since sales began in April 2024. Continental Club now shows a developer-supplied Q2 2027, one quarter later.
Is Jade Tower in Majan finished?
No. It was 11% complete at the DLD inspection on 2 October 2026. The structure is at an early stage.
When do post-handover payments start at Jade Tower?
On the main 70/30 plan, 30% of the price is paid over 24 months after handover. Those instalments begin only once the tower is handed over, so a later completion date moves them later too.