Handover date

When is the Volga Tower handover date?

Volga Tower

How this page was made: figures from the DLD project register and the developer and portal pages listed under Sources, as at 19 October 2026. Text drafted with AI assistance from those sources. Every figure matched the fact records at the build on 12 November 2026. Not yet reviewed line by line by a person. How facts are checked

Short answer

Volga Tower has no completion date on the DLD project register as at 18 October 2026; Property Finder lists December 2026 (Q4 2026). The DLD inspection on 5 October 2026 recorded the tower 51.1% complete, up from 37.93% on 25 June 2026. At that stage a 2026 handover is not realistic, and Continental Club's pace estimate points to about April 2028.

Registered completion date (DLD)

None on file

DLD register via Mitchell's, as at 18 Oct 2026

Latest construction progress

51.1%

DLD inspection, 5 Oct 2026

Portal handover date

Q4 2026

Property Finder (December 2026) and Tanami Properties; to be announced on fäm Properties

Estimated finish at recorded pace

About Apr 2028

Continental Club calculation at 2.72 points a month, not a developer date

Volga Tower handover date: the latest position

Property Finder lists December 2026 (Q4 2026) as the handover for Volga Tower, Tiger Properties’ 40 floor tower in Jumeirah Village Triangle, and Tanami Properties gives the same quarter. The DLD project register holds no completion date for it (project 2715, as at 18 October 2026), and Tiger’s project page gives none. Prices, sizes and payment plans are on the Volga Tower project page.

The DLD inspection on 5 October 2026 recorded the tower 51.1% complete. Half the work remained with under three months of 2026 left, so the Q4 2026 date is very likely to pass. Continental Club estimates completion around 4 April 2028 at the past year’s pace.

Volga Tower handover date by building

Volga Tower is a single building, so one date applies to all 391 units.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Volga Tower (DLD project 2715) 51.1%, 5 Oct 2026 None on file December 2026 (Property Finder); Q4 2026 (Tanami Properties); to be announced (fäm Properties)

The tower is registered as a ground floor with shops, four parking floors, 40 residential and commercial floors and two service floors.

How the Volga Tower handover date has changed

  • 1 June 2023: Bookings open (Property Finder); fäm Properties gives a launch date of 11 September 2023.
  • 12 July 2023: First DLD inspection at 0%.
  • 1 September 2023: Registered construction start (DLD register).
  • 6 November 2023: Gulf News reports the launch with 390 flats and five-year payment plans; no handover date given.
  • 21 April 2024: Construction start date given by Property Finder.
  • 20 February 2025: DLD inspection at 11.67%.
  • 29 December 2025: DLD inspection at 26.09%.
  • 25 June 2026: DLD inspection at 37.93%.
  • 5 October 2026: DLD inspection at 51.1%. Property Finder still lists December 2026.

The build has sped up. It took about 18 months from the first inspection to reach 11.67%, then reached 26.09% by the end of 2025 and added 25 more points in the first nine months of 2026. The 13.17 points gained between June and October 2026 is the largest single step recorded. Even at that rate, about a year of work remained after the October inspection.

What the Volga Tower handover date means for payments

A large share of the price falls due at or after handover. On the plan listed by Property Finder, 10% is due on handover and 48% after it. On the plan listed by Tanami Properties, 10% is due on handover and 30% over the 24 months after it. A later handover moves these payments later. All 119 sales registered since 2024 were bought from the developer (Continental Club), so nearly every owner is still on one of these plans.

What to check before relying on the Volga Tower date

  1. The completion date written in the SPA, since the DLD register holds none and the portal date of Q4 2026 does not match 51.1% progress.
  2. When the post-handover instalments start, and whether they run from the handover notice or the date in the SPA.
  3. New DLD inspections for project 2715, through the DLD project status service, to see whether the faster pace of mid 2026 holds.

Questions buyers also ask

What is the Volga Tower completion date?

The DLD register holds no completion date for project 2715 as at 18 October 2026. Property Finder gives an expected completion of December 2026. The registered construction start was 1 September 2023.

Is Volga Tower JVT finished?

No. It was 51.1% complete at the DLD inspection on 5 October 2026. Listings that say handover soon refer to the portal date, not a finished building.

Has the Volga Tower handover date been delayed?

Not formally, since the DLD register has no date on file and Tiger has not published one. Property Finder and Tanami Properties still show Q4 2026, while fäm Properties shows the date as to be announced. The build is about half done ten weeks before the end of 2026.

When will Volga Tower be ready at the current pace?

Continental Club estimates 100% around 4 April 2028, based on 2.72 points a month over the past year. The pace has varied: the tower gained 13.17 points between 25 June and 5 October 2026, faster than earlier periods.

Sources

  1. Mitchell's, Volga Tower (DLD project register) (opens in a new tab)mitchellscommercialrealty.com · registry as at 18 Oct 2026
  2. Tanami Properties, Volga Tower at JVT (opens in a new tab)tanamiproperties.com · accessed 19 Oct 2026
  3. fäm Properties, Volga Tower (opens in a new tab)famproperties.com · accessed 19 Oct 2026