Handover date

When is the Red Square Tower handover date?

Red Square Tower

How this page was made: figures from the DLD project register and the developer and portal pages listed under Sources, as at 19 October 2026. Text drafted with AI assistance from those sources. Every figure matched the fact records at the build on 12 November 2026. Not yet reviewed line by line by a person. How facts are checked

Short answer

Red Square Tower has no completion date on the DLD project register as at 18 October 2026; Property Finder lists a Q2 2027 handover and some agents still show Q4 2026. The last DLD inspection, on 27 March 2026, recorded the twin towers 26.71% complete. With about 73% of the work left at that inspection, a handover by either date would need a much faster build than recorded so far.

Registered completion date (DLD)

None on file

DLD register via Mitchell's, as at 18 Oct 2026

Latest construction progress

26.71%

DLD inspection, 27 Mar 2026

Portal handover date

Q2 2027

Property Finder, expected completion 14 Apr 2027; Q4 2026 on Driven Properties and Inside Realty

Progress in nine months

+17.9 points

8.8% on 3 Jul 2025 to 26.71% on 27 Mar 2026

Red Square Tower handover date: the latest position

The DLD project register holds no completion date for Red Square Tower, Tiger Properties’ twin 34 floor towers in JVT, registered as “Red Square” (project 2789). Property Finder lists a Q2 2027 handover with an expected completion of 14 April 2027, while Driven Properties and Inside Realty show Q4 2026. Prices, sizes and payment plans are on the Red Square Tower project page.

The last DLD inspection on file, dated 27 March 2026, recorded the project 26.71% complete. No later inspection had been published by 18 October 2026 (Mitchell’s). Tiger’s own project page gives no handover date.

Red Square Tower handover date by building

The two towers share one podium and one DLD project number, so the register gives one progress figure for both.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Red Square A and Red Square B (DLD project 2789) 26.71%, 27 Mar 2026 None on file Q2 2027 (Property Finder); Q4 2026 (Driven Properties, Inside Realty)

The DLD description is a podium of an upper ground floor, three basements, four parking floors and a ground floor, with two towers of 34 floors and a roof. Tiger announced 417 apartments in one tower and 419 in the other; the register holds 835 units.

How the Red Square Tower handover date has changed

  • 1 January 2024: Registered construction start and sales launch (DLD register; Property Finder).
  • 10 January 2024: Tiger announces the Red Square Twin Towers with five-year payment plans and no handover date.
  • 19 January 2024: First DLD inspection at 0%.
  • 12 February 2025: DLD inspection at 7.2%.
  • 15 June 2025: Construction start date given by Property Finder.
  • 3 July 2025: DLD inspection at 8.8%.
  • 27 March 2026: DLD inspection at 26.71%.
  • October 2026: Property Finder lists Q2 2027; other agents still list Q4 2026.

Progress was slow for the first 18 months, then picked up: 17.9 points in the nine months to March 2026, about 2 points a month. Data Dubai puts the average since February 2025 at 1.46 points a month. Either pace leaves most of the work still to do in 2027, so both the Q4 2026 and Q2 2027 dates look unlikely.

What the Red Square Tower handover date means for payments

On the 20/60/20 plan listed by Property Finder, the final 20% is due on handover. Inside Realty lists 70/30 and 80/20 plans with up to 2 years of payments after handover. In each case the handover date sets when the last instalments fall due, so a later completion moves them later rather than removing them. Nearly all 730 sales registered to September 2026 were bought off-plan from the developer (Mitchell’s).

What to check before relying on the Red Square Tower date

  1. The completion date written in the SPA, since the DLD register holds none and agents disagree.
  2. New DLD inspections for project 2789, through the DLD project status service, since the March 2026 figure is more than six months old.
  3. Whether construction instalments follow progress or calendar dates, given the gap between the build and the Q4 2026 date some agents still quote.

Questions buyers also ask

What is the Red Square Tower completion date?

The DLD register holds no completion date for project 2789 as at 18 October 2026. Property Finder gives an expected completion of 14 April 2027 (Q2 2027). The registered construction start was 1 January 2024.

Is Red Square Tower JVT finished?

No. It was 26.71% complete at the DLD inspection on 27 March 2026, the latest on file in October 2026.

Has the Red Square Tower handover date been delayed?

Agent listings have moved from Q4 2026 to Q2 2027 on Property Finder, while Driven Properties and Inside Realty still show Q4 2026. Tiger has not published a date, and the DLD register has none to compare against.

Do Red Square Tower A and B hand over at the same time?

The two towers sit on one shared podium and are registered as a single DLD project, 2789, with one progress figure. No separate dates have been published for Red Square A and Red Square B.

Sources