When was Cloud Tower JVT handed over?
Short answer
Cloud Tower in JVT was handed over on 29 October 2025, when Tiger Properties announced the official handover of the twin towers. The DLD inspection of 20 October 2025 recorded the project 100% complete. The registered completion date was 28 February 2025, so the towers were finished about eight months late.
Handed over
29 Oct 2025
Tiger Properties, 29 Oct 2025
Latest construction progress
100%
DLD inspection, 20 Oct 2025 (project 2212)
Registered completion date (DLD)
28 Feb 2025
DLD project register via Continental Club and Real Estate IQ
Delay against the registered date
About 8 months
28 Feb 2025 registered; 72.1% built on 10 Feb 2025
Cloud Tower handover date: the latest position
Cloud Tower, Tiger Properties’ pair of towers in Jumeirah Village Triangle (JVT), was handed over on 29 October 2025. Tiger announced the official handover that day, and the DLD inspection of 20 October 2025 had recorded the project 100% complete. Prices, rents and sizes are on the Cloud Tower project page.
The registered completion date was 28 February 2025. The project, also marketed as Cloud Towers and Cloud Twin Tower, was 72.1% built at the inspection of 10 February 2025, so completion came about eight months after the date on file.
Cloud Tower handover date by building
The two towers, Cloud A and Cloud B, are one DLD project, so a single completion record and a single handover date apply to both.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Cloud A (Block A, 27 floors plus roof) | 100%, 20 Oct 2025 | 28 Feb 2025 | Handed over 29 Oct 2025 (Tiger) |
| Cloud B (Block B, 29 floors plus roof) | 100%, 20 Oct 2025 | 28 Feb 2025 | Handed over 29 Oct 2025 (Tiger) |
Source: DLD register, project 2212, via Real Estate IQ and Continental Club. The project holds 456 units, 447 of them homes. Dubricks lists 229 units for Block A.
How the Cloud Tower handover date has changed
- 1 March 2022: Tiger launched the project at an event at the Sheraton JBR (Dubai Immo, 3 March 2022). The DLD register gives the same day as the construction start.
- 11 March 2022: Project registered with the DLD and bookings opened, with completion set for 28 February 2025 (DLD register; Property Finder).
- 3 November 2022: DLD inspection at 3.45%.
- 29 August 2023: DLD inspection at 15.39%.
- April 2024: Agents still quoted handover in February 2025 (Select House, 11 April 2024).
- 10 February 2025: DLD inspection at 72.1%, in the month of the registered date.
- 14 October 2025: DLD inspection at 98.3%.
- 20 October 2025: DLD inspection at 100%.
- 29 October 2025: Official handover (Tiger Properties).
The registered date was not moved in the register while the build ran late. Progress between August 2023 and February 2025 averaged about 3.3 points a month, and the last 28 points took eight months.
What the Cloud Tower handover date means for payments
On the main plan listed by Property Finder and Continental Club, buyers paid 20% on booking, 40% during construction and 20% on handover, so that 20% fell due around October 2025. A further 20% runs over 24 months after handover (Select House), which takes those instalments to about late 2027. Dubai Immo reported a launch plan in March 2022 with 50% paid over four years after handover, which would run to about late 2029. Because handover came eight months late, these post-handover schedules started later than buyers first expected.
What to check before relying on the Cloud Tower date
- The handover date in the buyer’s own handover notice, since post-handover instalments are counted from it, not from 28 February 2025.
- How much of a post-handover plan is still owed on a resale unit, and whether Tiger will issue the NOC before it is cleared.
- The DLD record for project 2212, through the DLD project status service, which shows the finished status and final inspection.
Questions buyers also ask
Is Cloud Tower JVT finished?
Yes. The DLD inspection of 20 October 2025 recorded 100%, the register lists the project as finished, and Tiger Properties handed it over on 29 October 2025.
What was the Cloud Tower completion date?
The DLD register holds 28 February 2025 as the completion date, and Property Finder gives the same date. Actual completion was recorded at the 20 October 2025 inspection.
Was the Cloud Tower handover delayed?
Yes, by about eight months. The towers were 72.1% built at the inspection of 10 February 2025, in the month they were due. Progress reached 98.3% on 14 October 2025 and 100% on 20 October 2025.
Were Cloud A and Cloud B handed over at the same time?
Yes. Both towers sit in one DLD project, number 2212, with one completion record and one handover on 29 October 2025.