Handover date

When is the Ananda Residences handover date?

Ananda Residences

How this page was made: figures from the DLD project register and the developer and portal pages listed under Sources, as at 19 October 2026. Text drafted with AI assistance from those sources. Every figure matched the fact records at the build on 12 November 2026. Not yet reviewed line by line by a person. How facts are checked

Short answer

The Ananda Residences completion date in the DLD project register is 31 May 2028, and Tiger Properties and Property Finder give Q2 2028. A DLD inspection on 7 October 2026 recorded the twin towers 3.2% complete, up from 2.55% in August 2026. With almost 97% of the work left and 19 months to go, the May 2028 date is very likely to move, and Tiger has not published a revised one.

Registered completion date (DLD)

31 May 2028

DLD project register via Mitchell's, 18 Oct 2026

Latest construction progress

3.2%

DLD inspection, 7 Oct 2026

Developer's stated date

Q2 2028

Tiger via Continental Club; Property Finder lists May 2028

Pace over the past year

0.32 points a month

Continental Club, from DLD inspections to 7 Oct 2026

Ananda Residences handover date: the latest position

The DLD project register holds 31 May 2028 as the completion date for Ananda Residences, Tiger Properties’ twin towers in Motor City. Tiger gives Q2 2028 and Property Finder lists May 2028. Prices, sizes and payment plans are on the Ananda Residences project page.

The DLD inspection on 7 October 2026 recorded the project 3.2% complete. That leaves almost 97% of the work for the 19 months to the registered date. The register has not been updated, and Tiger has not announced a new date.

Ananda Residences handover date by building

The two towers are registered as one DLD project, number 3535, so one date and one progress figure cover all 1,027 units. Continental Club lists the project as Ananda Towers; Mitchell’s and the current register row use Ananda Residences.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Block A (G + 53 floors + 2 mechanical + roof) 3.2%, 7 Oct 2026 (whole project) 31 May 2028 Q2 2028 (Tiger); May 2028 (Property Finder)
Block B (G + 53 floors + 2 mechanical + roof) 3.2%, 7 Oct 2026 (whole project) 31 May 2028 Q2 2028 (Tiger); May 2028 (Property Finder)

Source: DLD project register via Mitchell’s and Continental Club. The towers share one basement.

How the Ananda Residences handover date has changed

  • 1 February 2025: Bookings open and registered construction start, with completion set for 31 May 2028 (Property Finder; DLD register).
  • 10 April 2025: Alnair reports the launch with a Q2 2028 handover and a two year post-handover plan.
  • 13 October 2025: Tiger announces phase one sold out (Gulf News).
  • 8 December 2025: Property Finder marks the project sold out.
  • 31 December 2025: DLD inspection at 0.28%.
  • 5 August 2026: DLD inspection at 2.55%.
  • 7 October 2026: DLD inspection at 3.2%. The registered date is still 31 May 2028.

The date has not moved since launch. The build has gained about 2.9 points in the nine months since December 2025, and 0.65 points in the two months from August to October 2026. Continental Club puts the pace over the past year at 0.32 points a month and calculates that at this rate the towers would reach 100% in 2052. That projection is a calculation, not a developer date, but it shows how far the pace would need to rise to meet May 2028.

What the Ananda Residences handover date means for payments

On the main 20/50/10/20 plan, 10% of the price falls due on handover and 20% over the 24 months after it. On the 20/40/10/30 plan, 10% is due on handover and 30% after it. Tiger’s October 2025 offer put 1 to 3 bedroom units on 70% during construction with 30% over two years after handover (Gulf News). In each case the handover date sets when the last 30% or 40% starts, so a later completion moves those payments later rather than cancelling them.

What to check before relying on the Ananda Residences date

  1. That the SPA names DLD project 3535, whichever of the two names a listing uses.
  2. The completion date and grace period in the SPA, compared with the 3.2% DLD figure and 31 May 2028.
  3. Whether construction instalments follow DLD progress or fixed dates, since half of the price on the main plan falls due during construction.
  4. New DLD inspections for project 3535, through the DLD project status service, for any change in pace or a revised registered date.

Questions buyers also ask

When will Ananda Towers be completed?

Ananda Towers is the same project as Ananda Residences, DLD project 3535. The registered completion date is 31 May 2028. It was 3.2% complete on 7 October 2026, so completion by that date is not realistic on the recorded pace, and no new date has been published.

Has the Ananda Residences handover date been delayed?

Not formally. The DLD register, Tiger and Property Finder still show May 2028 or Q2 2028, the target given at launch in 2025. Progress is well behind what that date needs.

Do both Ananda towers hand over at the same time?

On the register, yes. Block A and Block B sit under one DLD project with one completion date of 31 May 2028 and one progress figure for both towers.

Is Ananda Residences Motor City finished?

No. It was 3.2% complete at the DLD inspection on 7 October 2026, about 20 months after the registered construction start of 1 February 2025.