Illustration: construction cranes on a residential tower at dusk
Handover date

When will Meydan Horizon be completed?

Updated 12 October 2026 Meydan Horizon

Short answer

Meydan Horizon has no single completion date, and none of its towers is finished. Its projects, built by separate developers, carry Dubai Land Department (DLD) registered completion dates from 30 June 2027 (The Waterway, Future Residence) to 31 August 2029 (Rove Home Meydan Horizon). At the latest DLD inspections, the furthest along were Ayaan Heights at 20.3% (8 July 2026), Claydon House at 15.72% (6 August 2026) and The Waterway at 14.73% (17 August 2026); most others were under 10% (DLD register via Continental Club, updated 4 and 5 October 2026). With The Waterway 14.73% built ten months before its registered date, the 2027 dates are likely to move.

Registered completion dates (DLD)

Jun 2027 to Aug 2029

The Waterway 30 Jun 2027 to Rove Home 31 Aug 2029. DLD register via Continental Club, Oct 2026

Most advanced tower

20.3%

Ayaan Heights, DLD inspection 8 Jul 2026

Earliest registered date, progress

14.73%

The Waterway, registered for 30 Jun 2027. DLD inspection 17 Aug 2026

Towers complete

None named

No Meydan Horizon tower recorded complete on DLD register trackers, Oct 2026

Meydan Horizon completion date: the latest position

Meydan Horizon, the canal and lagoon district in Bu Kadra, Mohammed Bin Rashid City, has no single completion date. Meydan is the master developer, and each tower is built by its own developer with its own Dubai Land Department (DLD) registered completion date. Those dates run from 30 June 2027 to 31 August 2029, and no tower in the district is recorded as finished. See the Meydan Horizon district page for prices and developers.

Construction is at an early stage across the district. The most advanced tower, Ayaan Heights, was 20.3% built on 8 July 2026. Of the 18 towers with a published DLD inspection, 14 were under 10%.

Meydan Horizon completion date by project

Progress figures are DLD site inspections, republished from the register by Continental Club (updated 4 and 5 October 2026).

Project Developer Construction progress (DLD, date) Registered completion date Developer or portal date
The Waterway (115 units) Prestige One 14.73% (17 Aug 2026) 30 Jun 2027 Q2 2027
Future Residence (152 units) True Future 0% (25 Aug 2025, latest published) 30 Jun 2027 Q2 2027
Al Vista (384 units) Dubai Investments 5.5% (1 Jul 2026) 20 Oct 2027 Q4 2027
Helvetia Verde (109 units) DHG Properties 0.62% (6 Jul 2026) 30 Nov 2027 Q1 2028 (DHG)
Claydon House (415 units) Ellington 15.72% (6 Aug 2026) 31 Dec 2027 Q2 2027 (Bayut)
Belmore Residences (214 units) Ellington 6.53% (6 Aug 2026) 31 Dec 2027 Q4 2027
Helvetia Azure (63 homes) DHG Real Estate Not published Not found Q4 2027 (DHG at launch)
Parkway by Prestige One (274 units) Prestige One 10.9% (17 Aug 2026) 31 Jan 2028 Q1 2028
Ayaan Heights I (130 units) Invest Group Overseas (registered as Digo Real Estate Development) 20.3% (8 Jul 2026) 31 Mar 2028 March 2028 (Data Habibi)
The Caden by Prescott (229 units) Prescott 0.47% (2 Jun 2026) 15 May 2028 Q3 2028
Riverton House (151 units) Ellington 0%, design stage (22 Dec 2025) Q2 2028 (no day shown) Q2 2028
Eaton Square (24 units) Ellington 5.39% (20 Jul 2026) 30 Jun 2028 Q2 2028
The Winslow (260 units, including offices) IGO 0.03% (29 Jun 2026) 30 Jun 2028 Q2 2028
Mia Tower (210 units) Stamn Development Not published Not shown Q2 2028 (developer)
Wynwood Horizon (165 units) Imtiaz 9.6% (16 Sep 2026) 30 Oct 2028 May 2028 (Imtiaz)
Highgrove by Ellington (296 units) Ellington 7% (6 Aug 2026) 31 Dec 2028 (was Q4 2027) Q4 2027
Chavelle by Imtiaz (145 units) Imtiaz 0% (22 Jan 2026) 15 Mar 2029 Q1 2029
Symphony (369 units) Imtiaz 6.3% (16 Sep 2026) 15 Jun 2029 Q2 2029
Zen Lagoons (177 units) Zennova Realty 0% (9 Feb 2026) 30 Jun 2029 Q2 2029
Rove Home Meydan Horizon (190 units) Al Ain Properties with Rove 0% (11 Nov 2025) 31 Aug 2029 Q1 2029 (Bayut)

Rove Home appears on the register as “R Home MH” and Symphony as “Imtiaz Symphony Tower”. Meydan’s own Bu Kadra Tower has no published date. Propsearch credits Ayaan Heights to MAG Group, while Property Finder and the register name Invest Group Overseas.

Continental Club’s DLD transaction tables for the Meydan Horizon location also include Sobha Hartland 2 towers such as Skyvue and Skyscape. Their dates are on the Sobha Hartland 2 page.

How the Meydan Horizon completion date has changed

Several marketed dates no longer match the register. Bayut still lists Claydon House for Q2 2027, while the register gives 31 December 2027. Imtiaz gave May 2028 for Wynwood Horizon, against a registered 30 October 2028. Bayut lists Rove Home for Q1 2029, against a registered 31 August 2029. Highgrove by Ellington’s registered completion date has moved from Q4 2027 to 31 December 2028 on the DLD register (Continental Club, register updated 11 October 2026), while its marketed date is still Q4 2027 and it was 7% built on 6 August 2026. One date runs the other way: DHG markets Helvetia Verde for Q1 2028, but its registered completion date is 30 November 2027.

The earliest registered dates also look tight. The Waterway, under construction since 15 November 2024, was 14.73% built on 17 August 2026, with about ten months left to its registered 30 June 2027. Future Residence, also registered for 30 June 2027, has no inspection newer than 0% on 25 August 2025. Helvetia Verde was still finishing excavation in early August 2026, according to DHG.

What the Meydan Horizon completion date means for payments

Many Meydan Horizon towers leave a large share of the price to completion. Wynwood Horizon is sold on 20% down, 40% during construction and 40% at handover (Continental Club), and Data Habibi lists the same 20/40/40 split for Ayaan Heights. Helvetia Azure launched on a 60/40 plan, with 40% due at completion (Alnair). Under these plans a later completion date moves 40% of the price to a later date.

What to check before relying on a Meydan Horizon date

  1. Which developer and DLD project number the unit sits under, since each tower in Meydan Horizon is a separate registration with its own date.
  2. The registered completion date against the marketed quarter, given the gaps at Claydon House, Highgrove, Wynwood Horizon and Rove Home.
  3. How recent the last inspection is. Future Residence and Rove Home have no inspection since 2025.
  4. The completion date and grace period in the SPA, especially for towers with 40% due at handover.

Questions buyers also ask

When will Meydan Horizon be completed?

Not before 2029 on current registered dates. The earliest towers are registered for 30 June 2027 and the latest, Rove Home Meydan Horizon, for 31 August 2029. Meydan's own Bu Kadra Tower has no published date (DLD register via Continental Club, October 2026).

Is any part of Meydan Horizon finished?

No named tower. The most advanced at the latest DLD inspections were Ayaan Heights (20.3%, 8 July 2026), Claydon House (15.72%, 6 August 2026) and The Waterway (14.73%, 17 August 2026).

When is the Claydon House handover date?

The DLD register gives Claydon House by Ellington a registered completion date of 31 December 2027, with the tower 15.72% built on 6 August 2026. Bayut lists Q2 2027, which no longer matches the register.

When will Symphony and Wynwood Horizon by Imtiaz be completed?

Wynwood Horizon is registered for 30 October 2028 and was 9.6% built on 16 September 2026; Imtiaz had given May 2028. Imtiaz Symphony Tower is registered for 15 June 2029 and was 6.3% built on 16 September 2026.

Who builds the towers in Meydan Horizon?

Meydan, now part of Dubai Holding, is the master developer. The towers are built by separate developers, including Ellington, Imtiaz, Prestige One, DHG, Dubai Investments, Invest Group Overseas, Prescott, Al Ain Properties and Stamn, each on its own schedule.

Sources

  1. Continental Club, Al Vista (DLD project 3802) (opens in a new tab)continentalclub.ae · registry updated 5 Oct 2026
  2. Continental Club, Helvetia Verde (DLD project 4057) (opens in a new tab)continentalclub.ae · registry updated 4 Oct 2026
  3. Continental Club, Ayaan Heights I (DLD project 3610) (opens in a new tab)continentalclub.ae · registry updated 4 Oct 2026
  4. Propsearch, Ayaan Heights (opens in a new tab)propsearch.ae · accessed 6 Oct 2026
  5. Data Habibi, Ayaan Heights (opens in a new tab)datahabibi.ae · accessed 6 Oct 2026
  6. Continental Club, Riverton House (DLD project 4036) (opens in a new tab)continentalclub.ae · registry updated 5 Oct 2026
  7. Continental Club, Eaton Square (DLD project 4301) (opens in a new tab)continentalclub.ae · registry updated 4 Oct 2026
  8. Continental Club, The Winslow (DLD project 3634) (opens in a new tab)continentalclub.ae · registry updated 4 Oct 2026
  9. Continental Club, Mia Tower (opens in a new tab)continentalclub.ae · updated 9 Sep 2026
  10. Continental Club, Zen Lagoons (DLD project 4340) (opens in a new tab)continentalclub.ae · registry updated 5 Oct 2026
Request a Unit Review