When is the Legado by Prescott handover date?
Short answer
The DLD register gives Legado by Prescott a completion date of 31 August 2027, while Prescott has given Q4 2027 since launch in September 2024. A DLD inspection on 30 September 2026 recorded the tower 23.31% complete. With about three quarters of the work left and 11 months to the registered date, both dates are under pressure.
Registered completion date (DLD)
31 Aug 2027
DLD project register via Continental Club, updated 5 Oct 2026
Latest construction progress
23.31%
DLD inspection, 30 Sep 2026
Developer's stated date
Q4 2027
Prescott, 9 Sep 2024
Progress, July to September 2026
+3.18 points
DLD inspections, 2 Jul to 30 Sep 2026
Legado by Prescott handover date: the latest position
The Dubai Land Department (DLD) register gives Legado by Prescott a completion date of 31 August 2027. Prescott has given Q4 2027 since the launch on 9 September 2024, and its payment plans show the handover payment due in Q4 2027. Full project details are on the Legado by Prescott page.
The latest DLD inspection, on 30 September 2026, recorded the tower 23.31% complete. Between 2 July and 30 September 2026 progress rose by 3.18 points, about 1 point a month. Finishing by Q4 2027 would need a much faster pace from here.
Legado by Prescott handover date by building
Legado is a single 34 storey tower with 343 units in the DLD register.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Legado by Prescott | 23.31% (30 Sep 2026) | 31 Aug 2027 | Q4 2027 (Prescott); Aug 2027 (Property Finder) |
Progress and the registered date are from the DLD project register via Continental Club.
How the Legado by Prescott handover date has changed
| Date | Event | Source |
|---|---|---|
| 1 Sep 2024 | Registered construction start | DLD via Continental Club |
| 9 Sep 2024 | Prescott launches Legado, handover Q4 2027 | Prescott |
| Sep 2024 | Payment plan schedules the handover payment for Q4 2027 | Prescott factsheet |
| 2 Jul 2026 | DLD inspection records 20.13% | DLD via Continental Club |
| 30 Sep 2026 | DLD inspection records 23.31%; registered date 31 August 2027 | DLD via Continental Club |
The developer date has not changed. The registered date of 31 August 2027 sits one to four months before Prescott’s Q4 2027. About 77% of the work remained at the end of September 2026.
What the Legado by Prescott handover date means for payments
Construction instalments on Legado are fixed to calendar dates, not to progress. On the standard plan, buyers pay 20% on booking and 40% in seven instalments from January 2025 to February 2027, so 60% is paid before handover even if the tower is late. The remaining 40% is due on handover. On the post-handover plan, 10% is due on handover and 30% over three years after, at 2.5% a quarter (Prescott factsheet). A later handover moves only the handover and post-handover payments.
What to check before relying on the Legado by Prescott date
- The completion date and grace period in the SPA, given the gap between 31 August 2027 and Q4 2027.
- The calendar instalments. The February 2027 payment falls due whatever stage the tower has reached.
- The start of post-handover instalments. On the 60/10/30 plan, the three year schedule begins at handover, so a later handover also pushes back the final payment.
- The next DLD inspection. At about 1 point a month, the tower would be well short of complete by late 2027; a faster figure on the next inspection would change that.
Questions buyers also ask
Is Legado by Prescott finished?
No. The tower was 23.31% complete at the DLD inspection of 30 September 2026 (DLD project register via Continental Club).
What is the Legado by Prescott completion date?
The DLD registered completion date is 31 August 2027. Prescott gives Q4 2027, and Property Finder shows August 2027.
Has the Legado by Prescott handover date been delayed?
Not officially. Prescott's Q4 2027 date has not changed since launch on 9 September 2024. Progress of about 1 point a month in mid 2026 is slower than needed to finish by either date.
When is the last Legado by Prescott construction instalment?
On the standard plan, the last 5% construction instalment falls in February 2027. The remaining 40% is due on handover (Prescott factsheet).