Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Sobha Hartland 2 handover date?

Updated 6 October 2026 Sobha Hartland 2

Short answer

Sobha Hartland 2 hands over in phases from Q4 2026 to 2030: the villas are listed for 31 December 2026, Sobha gives June to December 2027 for the six Riverside Crescent towers, and the registered completion dates on the Dubai Land Department (DLD) register reach 31 December 2029 for Skyscape and 31 March 2030 for Skyvue. DLD inspections between 9 July and 16 September 2026 put the Riverside Crescent towers at 50.23% to 60.37% complete, and Sobha Estates villas at 68.49% on 15 September 2026. No part of Sobha Hartland 2 had handed over by 1 October 2026, and the Riverside Crescent towers have no registered completion date filed.

Earliest stated date, villas

Q4 2026

Property Finder, 31 Dec 2026; named in Sobha's 2026 handover plan, 20 Jul 2026

Latest construction progress, Riverside Crescent

50.23% to 60.37%

Six towers, DLD inspections 9 Jul to 16 Sep 2026

Registered completion dates (DLD)

31 Dec 2027 to 31 Mar 2030

Sobha Estates to Skyvue. None filed for Riverside Crescent

Developer dates, Riverside Crescent

Jun to Dec 2027

Sobha Riverside Crescent page, accessed 1 Oct 2026

Sobha Hartland 2 handover date: the latest position

Sobha Hartland 2 has no single handover date, because it is built and registered in phases. The villas come first: Property Finder lists 31 December 2026, and Sobha named Sobha Hartland II among the five projects in its plan for 6,819 handovers in 2026 (20 July 2026). Sobha gives June to December 2027 for the six Riverside Crescent towers, and the registered completion dates on the Dubai Land Department (DLD) register reach 31 December 2029 for Skyscape and 31 March 2030 for Skyvue. Prices and resale figures are on the Sobha Hartland 2 page.

No part of the community had handed over by 1 October 2026. The DLD register lists all nine Sobha projects in Bukadra as under construction. Its inspections between 9 July and 16 September 2026 put the Riverside Crescent towers at 50.23% to 60.37%, up from 26% to 45% in Sobha’s own figures for March 2026, though the two come from different sources.

Sobha Hartland 2 handover date by building

Sobha reports its villas in three series; the DLD register lists one villa project in Hartland 2, Sobha Estates, with 112 villas. Sobha has not published how the series map to that registration.

Building or phase Construction progress (DLD, date) Registered completion date Developer or portal date
Hartland II Villas, Series 1 Sobha: 89.59%, Mar 2026 Not found 31 Dec 2026 (Property Finder)
Hartland II Villas, Series 2 and 3 Sobha: 44.60% and 21.06%, Mar 2026 Not found 31 Dec 2026 (Property Finder)
Sobha Estates (112 villas) 68.49%, 15 Sep 2026 31 Dec 2027 Completion from Q4 2026, handover from 2027 (Real Estate Club Dubai)
330 Riverside Crescent 60.37%, 9 Jul 2026 Not filed Jun 2027 (Sobha)
320 Riverside Crescent 56.67%, 24 Aug 2026 Not filed Jul 2027 (Sobha)
350 Riverside Crescent 57.85%, 18 Aug 2026 Not filed Dec 2027 (Sobha); 1 Mar 2027 (Property Finder); Q1 2027 (OffplanCompare)
340 Riverside Crescent 55.02%, 18 Aug 2026 Not filed Dec 2027 (Sobha)
360 Riverside Crescent 50.67%, 16 Sep 2026 Not filed Dec 2027 (Sobha)
310 Riverside Crescent 50.23%, 9 Sep 2026 Not filed Dec 2027 (Sobha); Apr 2028 (OffplanCompare)
Skyscape (Aura, Avenue, Altius) 38.27%, 21 Sep 2026 31 Dec 2029 Dec 2028 (IST, 23 Jul 2026)
Skyvue (Solair, Spectra, Stellar) 10.54%, 30 Jul 2026 31 Mar 2030 Mar 2029 (IST, 23 Jul 2026)

IST also lists a fourth Skyvue tower, Altier, for June 2030. Sobha One, Sobha Orbis and Sobha Solis are separate projects with their own pages.

How the Sobha Hartland 2 handover date has changed

Date What happened Source
Oct 2023 Sobha Estates (10 Oct) and 330 Riverside Crescent (12 Oct) registered to start. 330 due 1 June 2027. DLD register; Property Finder
10 May 2024 310, 320, 340, 350 and 360 Riverside Crescent registered to start. Propsearch’s first estimate for 320 was May 2026. DLD register; Propsearch
15 Aug 2024 Skyscape registered to start, completion 31 December 2029. DLD register
1 Apr 2025 Skyvue registered to start, completion 31 March 2030. DLD register
19 Nov 2025 Broker listing gives Q2 2026 for the 112 villa phase. House and Hedges
Mar 2026 Sobha: villa Series 1 at 89.59%, Riverside Crescent 26% to 45%, Skyscape 13%. Sobha Q1 2026 update
20 Jul 2026 Sobha names Hartland II in its 2026 handover plan. Business Today Middle East
Jul to Sep 2026 DLD: Riverside Crescent 50.23% to 60.37%, Sobha Estates 68.49%, Skyscape 38.27%. DLD register, via Mitchells
1 Oct 2026 Property Finder shows 31 December 2026 for the villas. Property Finder

What the Sobha Hartland 2 handover date means for payments

Property Finder lists the villas at 10% at launch, 70% during construction and 20% on handover. On the AED 16,203,560 launch price of a 5 bedroom villa, the handover payment is AED 3,240,712. Broker listings for Sobha Estates describe 20% at booking, 60% during construction and 20% on handover (11 July 2026), and an earlier listing for the 112 villa phase put 40% on handover (19 November 2025). The handover share therefore ranges from 20% to 40% depending on the release.

What to check before relying on the Sobha Hartland 2 date

  1. Which registration your unit is in. The villa series, Sobha Estates and each Riverside Crescent tower carry different dates and progress.
  2. The SPA date for Riverside Crescent units, since none of the six towers has a registered completion date, and Sobha and brokers disagree for 310 and 350.
  3. Skyscape’s two dates. Sobha markets December 2028, while the register holds 31 December 2029.
  4. For villa buyers, the handover notice, since Sobha includes Hartland II in its 2026 deliveries but has not said which villas.

Questions buyers also ask

What is the Sobha Hartland 2 completion date?

There is no single date. Property Finder lists the villas for 31 December 2026. Sobha gives June 2027 for 330 Riverside Crescent, July 2027 for 320 and December 2027 for 310, 340, 350 and 360. The DLD register holds 31 December 2027 for Sobha Estates, 31 December 2029 for Skyscape and 31 March 2030 for Skyvue.

Is Sobha Hartland 2 finished?

No. The DLD register listed every Sobha project in Bukadra, where Hartland 2 sits, as under construction as of September 2026. The most advanced registered project, Sobha Estates, was 68.49% complete on 15 September 2026.

When will Riverside Crescent at Sobha Hartland 2 be ready?

Sobha's page gives June 2027 for 330, July 2027 for 320 and December 2027 for the other four towers. DLD inspections between July and September 2026 put the towers at 50.23% (310) to 60.37% (330). Some brokers give other dates, such as Q1 2027 for 350 and April 2028 for 310.

Has the Sobha Hartland 2 handover date been delayed?

The villa dates have moved. A November 2025 broker listing for the 112 villa phase gave Q2 2026, and Property Finder now shows 31 December 2026. Skyscape's registered completion date, 31 December 2029, is a year after the December 2028 date in Sobha's marketing.

How much is due at the Sobha Hartland 2 handover?

Property Finder lists 10/70/20 for the villas, so 20% is due on handover. Broker listings for Sobha Estates give 20% at booking, 60% during construction and 20% on handover (11 Jul 2026).

Sources

  1. Mitchell's, Sobha L.L.C DLD registered projects (opens in a new tab)mitchellscommercialrealty.com · accessed 1 Oct 2026
  2. Mitchell's, Sobha Estates DLD registry (DLD project 2793) (opens in a new tab)mitchellscommercialrealty.com · accessed 1 Oct 2026
  3. Mitchell's, Skyscape DLD registry (DLD project 3160) (opens in a new tab)mitchellscommercialrealty.com · accessed 1 Oct 2026
  4. Mitchell's, Skyvue DLD registry (DLD project 3435) (opens in a new tab)mitchellscommercialrealty.com · accessed 1 Oct 2026
  5. Sobha Realty, Riverside Crescent (opens in a new tab)sobharealty.com · accessed 1 Oct 2026
Request a Unit Review