Handover date

When is the Sobha Siniya Island handover date?

Updated 1 October 2026 Sobha Siniya Island

Short answer

Sobha Siniya Island hands over in stages from December 2027 to June 2030, according to the handover dates Sobha Realty lists for each cluster on its website (accessed 1 October 2026). The first are Palm Grove Villas and the Delphine and Selene Beach Residences in December 2027, the same date Sobha gave for phase one in November 2024, and the last are Tranquil Beach Residences and Capeside Marina Residences in June 2030. No construction progress figure has been published, because the project is in Umm Al Quwain and is not on the Dubai Land Department register.

Earliest handover (Sobha)

Dec 2027

Palm Grove Villas, Delphine and Selene Beach Residences, Sobha website, accessed 1 Oct 2026

Latest handover (Sobha)

Jun 2030

Tranquil Beach Residences and Capeside Marina Residences, Sobha website, accessed 1 Oct 2026

Latest construction progress

Not published

Umm Al Quwain project, not on the DLD register; Sobha publishes no percentage

Portal date for the villas

Dec 2028

Property Finder, accessed 28 Sep 2026, against Sobha's Dec 2027 and Jun 2028

Sobha Siniya Island handover date: the latest position

Sobha Siniya Island hands over in stages from December 2027 to June 2030, according to the dates Sobha Realty lists for each cluster on its website, checked on 1 October 2026. The first due are Palm Grove Villas and the Delphine and Selene Beach Residences, in December 2027. The last are Tranquil Beach Residences and Capeside Marina Residences, in June 2030. Prices, villa sizes and the location are on the Sobha Siniya Island page.

The project is in Umm Al Quwain, so it does not appear on the Dubai Land Department (DLD) register, which publishes registered completion dates and inspection figures for Dubai projects. Sobha has not published a construction percentage for any cluster, and Umm Al Quwain has no public project tracker.

Sobha Siniya Island handover date by cluster

None of the 18 clusters has a published progress figure or a DLD registered completion date, so the table shows Sobha’s own handover month for each.

Cluster Homes Sobha’s handover date
Palm Grove Villas 4 bedroom villas Dec 2027
Delphine Beach Residences 1 to 3 bedroom apartments Dec 2027
Selene Beach Residences 1 to 3 bedroom apartments and duplexes Dec 2027
Coraline Beach Residences 1 to 3 bedroom apartments and duplexes Mar 2028
Coral Beach Villas 5 and 6 bedroom villas Jun 2028
Aquamarine Beach Residences 1 to 3 bedroom apartments and duplexes Jun 2028
Florine Beach Residences Apartments Sep 2028
Coastline Beach Residences 1 to 3 bedroom apartments and duplexes Sep 2028
Pierside Marina Residences 1 to 3 bedroom apartments Mar 2029
Starline Beach Residences Apartments Jun 2029
Yachtside Marina Residences 1 and 2 bedroom apartments Jun 2029
Pristine Beach Residences Apartments Sep 2029
Bayfront Marina Residences 1 to 3 bedroom apartments Sep 2029
Bayside Marina Residences 1 to 3 bedroom apartments Sep 2029
Canalside Marina Residences 1 to 3 bedroom apartments Dec 2029
Pearlside Marina Residences 1 to 3 bedroom apartments Mar 2030
Tranquil Beach Residences Apartments Jun 2030
Capeside Marina Residences 1 to 3 bedroom apartments Jun 2030

Portals give later dates for the villas than Sobha does. Property Finder lists December 2028 for the main villa project and 30 June 2028 for Villas Phase 2, and EZRE lists Q2 2028 (accessed 28 Sep 2026). Sobha’s own pages give December 2027 and June 2028.

How the Sobha Siniya Island handover date has changed

Sobha’s first date has held so far, while each later release has added a later date.

Date What happened Source
16 Jul 2024 Sobha launched Siniya Island villas. Metropolitan Properties, citing Sobha
6 Nov 2024 Sobha said phase one would be complete by December 2027. The bridge was almost complete, dredging had begun and building works were due to start in Q2 2025. Khaleej Times
2024 to 2026 Later beach and marina clusters released with handover dates from March 2028 to June 2030. Sobha
Jan 2026 Capeside Marina Residences brochure gives an anticipated completion date of June 2030. Sobha
6 Apr 2026 Construction start for Villas Phase 2, with completion on 30 June 2028. Property Finder
1 Oct 2026 Sobha still lists December 2027 for Palm Grove, Delphine and Selene. Sobha

What the Sobha Siniya Island handover date means for payments

Portals describe a 10/50/40 plan: 10% on booking, 50% during construction and 40% on handover. Realty Hunting describes the same total as 10% on booking, 10% on signing the agreement, 40% during construction and 40% on handover, and Paul Palmer notes that current launches have no post-handover plan (12 Aug 2026). On a Palm Grove villa from AED 10.75 million, Sobha’s listed price, the handover payment is AED 4.3 million. That 40% is the largest single payment, and it falls due in the month the cluster hands over.

What to check before relying on the Sobha Siniya Island date

  1. Which cluster your unit is in. Sobha’s dates run from December 2027 to June 2030, 30 months apart.
  2. The completion date and grace period in your SPA, since Sobha’s villa dates and the portal dates differ by up to a year.
  3. Registration and escrow with Umm Al Quwain’s Department of Land and Property, not the DLD, since Dubai’s project status enquiry service does not cover the island.
  4. A written construction update from Sobha for your cluster, as no public progress figure exists to check the December 2027 and later dates against.

Questions buyers also ask

What is the Sobha Siniya Island handover date?

It depends on the cluster. Sobha's website lists December 2027 for Palm Grove Villas, Delphine and Selene, June 2028 for Coral Beach Villas, and dates up to June 2030 for the later beach and marina residences (accessed 1 Oct 2026).

When will the Sobha Siniya Island villas be ready?

Sobha lists December 2027 for Palm Grove Villas (4 bedrooms) and June 2028 for Coral Beach Villas (5 and 6 bedrooms). Property Finder gives later dates: December 2028 for the main villa project and 30 June 2028 for Villas Phase 2.

Has the Sobha Siniya Island handover date been delayed?

No delay has been announced. In November 2024 Sobha said phase one would be complete by December 2027, and its website still gives December 2027 for the first three clusters (Khaleej Times, 6 Nov 2024; Sobha, accessed 1 Oct 2026).

How far along is construction at Sobha Siniya Island?

No percentage has been published. The project is not on Dubai's DLD register, and Sobha has not released progress figures. Property Finder records construction on Villas Phase 2 starting on 6 April 2026.

How much is due at the Sobha Siniya Island handover?

Portals and Sobha's partners describe 40% on handover, with no post-handover plan. On a Palm Grove villa from AED 10.75 million on Sobha's website, that is AED 4.3 million.

Sources

  1. Property Finder, Sobha Siniya Island (opens in a new tab)propertyfinder.ae · accessed 28 Sep 2026
Request a Unit Review