Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Eden Hills handover date?

Updated 11 October 2026 Eden Hills

Short answer

The DLD register gives Eden Hills a registered completion date of 25 December 2026, but the project was only 3.54% complete at the DLD inspection on 22 September 2026, so that date will be missed. H&H Development said in January 2025 that its second phase would be completed in Q1 2028, and Bayut shows Q1 2028 for the community. Phase 1 dates given at launch, Q4 2026 or 2027, also look out of reach at the current pace.

Registered completion date (DLD)

25 Dec 2026

DLD project register via Continental Club

Latest construction progress

3.54%

DLD inspection, 22 Sep 2026

Developer's stated date (phase 2)

Q1 2028

H&H via Metropolitan, 24 Jan 2025

Phase 1 date given at launch

Q4 2026 or 2027

Arabian Business; Gulf Construction Online, 16 Nov 2024

Eden Hills handover date: the latest position

The DLD project register gives Eden Hills a registered completion date of 25 December 2026. At the latest DLD inspection, on 22 September 2026, the community was 3.54% complete, so that date will pass with almost all of the work still ahead. Prices, sizes and the payment plan are on the Eden Hills page.

H&H Development’s most recent published date is Q1 2028, given for the second phase in January 2025 (Metropolitan). Bayut shows Q1 2028 for the whole community, while Property Finder still shows December 2026. H&H had not announced a revised date by 11 October 2026.

Eden Hills handover date by phase

The register lists Eden Hills as one project, DLD number 3311, with 279 units and one progress figure. H&H sells it in phases, with different dates.

Phase Construction progress (DLD, date) Registered completion date Developer or portal date
Phase 1 (104 villas at launch) 3.54%, 22 Sep 2026 (whole project) 25 Dec 2026 Q4 2026 (Arabian Business) or 2027 (Gulf Construction Online, 16 Nov 2024)
Phase 2 3.54%, 22 Sep 2026 (whole project) 25 Dec 2026 Q1 2028 (Metropolitan, 24 Jan 2025; Bayut)
29 custom plots 3.54%, 22 Sep 2026 (whole project) 25 Dec 2026 Not published

H&H’s marketed total is 327 villas and plots. The register’s 279 units and its separate count of 158 villas do not match that figure, so a unit’s phase is best confirmed on its SPA.

How the Eden Hills handover date has changed

Date What happened Source
14 Nov 2023 Plots launched from AED 18.1 million; handover “in about 20 months” Metropolitan
16 Nov 2024 H&H announces 327 villas, 104 sold; construction from October, phase 1 in 2027 Gulf Construction Online
24 Jan 2025 Second phase released; completion scheduled for Q1 2028 Metropolitan
1 Mar 2025 Construction start registered DLD register
23 Jun 2026 DLD inspection records 2.79% DLD register
22 Sep 2026 DLD inspection records 3.54% DLD register

The first date, about 20 months from November 2023, pointed to mid 2025. The phase 1 date then moved to Q4 2026 or 2027, depending on the report, and the phase 2 date to Q1 2028. At the June to September 2026 pace of 0.25 points a month, even Q1 2028 would need a large increase in site activity.

What the Eden Hills handover date means for payments

The plan asks for 25% on booking, 25% within 6 months and 25% within 12 months, leaving 25% for handover (Bayut; Property Finder). The first three payments are tied to calendar dates, not construction progress, so early buyers have already paid 75% while the project is at 3.54%. On an AED 18 million villa, the handover payment is AED 4.5 million, and it moves with the handover date.

What to check before relying on the Eden Hills date

  1. The completion date in the SPA for the specific phase, since phase 1 and phase 2 were sold with different dates and the register holds one.
  2. Whether H&H has applied to DLD to extend the 25 December 2026 registered date, through the DLD project status enquiry.
  3. The next DLD inspection, which will show whether the pace has picked up from 0.25 points a month.

Questions buyers also ask

When will Eden Hills be completed?

The DLD register still shows 25 December 2026, but progress was 3.54% on 22 September 2026. H&H's latest published date is Q1 2028 for the second phase (Metropolitan, 24 Jan 2025), which Bayut also shows.

Has the Eden Hills handover date been delayed?

In practice, yes. The launch announcement put phase 1 at Q4 2026 or 2027, the register says 25 December 2026, and progress was 3.54% in September 2026. H&H had not announced a revised date by 11 October 2026.

When will Eden Hills phase 2 be ready?

H&H said in January 2025 that construction of the second phase was scheduled for completion in the first quarter of 2028 (Metropolitan, 24 Jan 2025).

How far along is construction at Eden Hills?

3.54% complete on 22 September 2026, up from 2.79% on 23 June 2026 (DLD project register via Continental Club).

Sources

  1. Bayut, Eden Hills area guide (opens in a new tab)bayut.com · accessed 11 Oct 2026
  2. Property Finder, Eden Hills project page (opens in a new tab)propertyfinder.ae · accessed 11 Oct 2026
Request a Unit Review