Handover date

When is the Peninsula Dubai Residences handover date?

Updated 11 October 2026 Peninsula Dubai Residences

Short answer

The DLD register holds a completion date of 8 January 2029 for both towers of Peninsula Dubai Residences, matching H&H's Q1 2029 target. The latest DLD inspections recorded Tower 1 at 5.6% on 10 September 2026 and Tower 2 at 6% on 13 August 2026. One broker page shows Q2 2029, and about 94% of the work remained in each tower at those readings.

Registered completion date (DLD)

8 Jan 2029

Both towers, DLD register via Continental Club, Oct 2026

Latest construction progress

5.6% and 6%

Tower 1 (10 Sep 2026), Tower 2 (13 Aug 2026), DLD

Developer's stated date

Q1 2029

H&H via Continental Club; Property Finder 8 Jan 2029

Latest broker date

Q2 2029

FOGO Real Estate, May 2026

Peninsula Dubai Residences handover date: the latest position

The Dubai Land Department (DLD) register holds a completion date of 8 January 2029 for both towers of Peninsula Dubai Residences, on the Dubai Peninsula in Jumeirah 2. H&H targets Q1 2029, and Property Finder lists 8 January 2029. More on the project: Peninsula Dubai Residences.

Both towers are at an early stage. Tower 1 was 5.6% complete on 10 September 2026 and Tower 2 was 6% complete on 13 August 2026. Each added about 2 percentage points in the three months before those readings. The DLD values the project at AED 700 million, an estimate the developer submitted before construction (Propsearch).

Peninsula Dubai Residences handover date by building

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Peninsula Dubai Residences - Tower 1 (DLD project 3396, 75 units) 5.6% (10 Sep 2026) 8 Jan 2029 Q1 2029 (H&H); 8 Jan 2029 (Property Finder)
Peninsula Dubai Residences - Tower 2 (DLD project 3548, 102 units) 6% (13 Aug 2026) 8 Jan 2029 Q1 2029 (H&H); January 2029 (Propsearch)

RSHP’s design shows four residential towers around a central hotel (Dezeen, 22 April 2025). Only two residential towers are in the DLD register so far. Both escrow accounts are with Emirates NBD.

How the Peninsula Dubai Residences handover date has changed

  • November 2024: first trace of the project in public records, with an estimated start in March 2025 (Propsearch).
  • 3 March 2025: construction registered as starting, with a registered completion date of 8 January 2029.
  • 22 April 2025: RSHP’s design published (Dezeen).
  • 2025 to 2026: DLD sales recorded in both towers, 151 in all by October 2026 (Continental Club).
  • 22 November 2025: a broker listing gave Q1 2029 and the 50/50 plan (Elevation).
  • May 2026: FOGO Real Estate listed Q2 2029, the only later date found.
  • 13 August and 10 September 2026: DLD inspections at 6% (Tower 2) and 5.6% (Tower 1). The register still holds 8 January 2029.

What the Peninsula Dubai Residences handover date means for payments

The 50/50 plan puts 10% on booking, 40% during construction and 50% on handover (Property Finder). On a 1 bedroom bought at AED 7.3 million, the handover payment is about AED 3.65 million. On a 3 bedroom in Tower 2 at AED 34.3 million, it is about AED 17.15 million. Any change to the completion date moves this payment with it.

What to check before relying on the Peninsula Dubai Residences date

  1. Which tower the unit is in. The two towers share a registered date but are inspected separately, on different dates.
  2. The completion date and grace period in the SPA, which governs the 50% handover payment.
  3. That the listing is the Jumeirah 2 project. Some data pages mix it up with The Peninsula by Select Group in Business Bay, which has different towers and dates.

Questions buyers also ask

When will Peninsula Dubai Residences be completed?

The DLD registered completion date is 8 January 2029 for both Tower 1 and Tower 2. H&H targets Q1 2029. Construction was registered as starting on 3 March 2025.

When will Peninsula Dubai Residences Tower 1 be ready?

Tower 1 is registered for 8 January 2029 and was 5.6% complete at the DLD inspection of 10 September 2026, up from 3.56% on 4 June 2026.

When will Peninsula Dubai Residences Tower 2 be ready?

Tower 2 is also registered for 8 January 2029 and was 6% complete at the DLD inspection of 13 August 2026, up from 3.95% on 7 May 2026.

Has the Peninsula Dubai Residences handover date been delayed?

No change has been announced. The register, H&H, Property Finder and Propsearch all give January 2029 or Q1 2029. One broker page, FOGO, shows Q2 2029.

Sources

  1. Continental Club, Peninsula Dubai Residences Tower 1 (DLD register) (opens in a new tab)continentalclub.ae · DLD inspection 10 Sep 2026; registry updated 4 Oct 2026
  2. Continental Club, Peninsula Dubai Residences Tower 2 (DLD register) (opens in a new tab)continentalclub.ae · DLD inspection 13 Aug 2026; registry updated 8 Oct 2026
  3. Propsearch, Peninsula Dubai Residences (opens in a new tab)propsearch.ae · updated 26 Mar 2026, accessed 11 Oct 2026