When is the Binghatti Elite handover date?
Short answer
Binghatti Elite's handover date is Q2 2026 on Binghatti's own project page, and the DLD registered completion date is 30 June 2026. Both have passed. The last DLD inspection, on 20 April 2026, recorded the tower at 53.25% complete, and the register still showed that figure on 29 September 2026. Binghatti has not published a revised date, and the tower has not been handed over.
Registered completion date (DLD)
30 Jun 2026
Passed. DLD register via Continental Club, 29 Sep 2026
Latest construction progress
53.25%
DLD inspection, 20 Apr 2026
Developer's stated date
Q2 2026
Binghatti project page, accessed 1 Oct 2026
Progress at previous inspection
28.44%
DLD inspection, 3 Nov 2025
Binghatti Elite handover date: the latest position
Binghatti Elite was due to be completed in Q2 2026. That is still the date on Binghatti’s own project page, and the Dubai Land Department (DLD) register holds a matching registered completion date of 30 June 2026. Both have passed, and the tower has not been handed over. More on prices and the building: Binghatti Elite.
The last DLD site inspection, on 20 April 2026, recorded the tower at 53.25% complete. Trackers that recheck the register daily or twice weekly showed no newer inspection through late September 2026, and Continental Club’s list of 29 September 2026 still showed 53.25%. Binghatti has not published a revised handover date.
Binghatti Elite handover date by building
Binghatti Elite is one 1,745-unit tower (1,587 studios and 158 one bedroom apartments), registered with the DLD as project 3341.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Binghatti Elite (4 basements, ground, 2 podium and 23 residential floors) | 53.25% (20 Apr 2026) | 30 Jun 2026 | Binghatti: Q2 2026. Propsearch: Q2 2026 |
How the Binghatti Elite handover date has changed
| Date | Event | Source |
|---|---|---|
| 17 Oct 2024 | First DLD inspection: 0% | DLD via Dubai Handover |
| 7 Nov 2024 | Project registered with DLD. Binghatti markets it for Q2 2026 | DLD via Dubai Handover; Binghatti |
| 30 Nov 2024 | Registered construction start | DLD via Mitchell’s |
| 3 Nov 2025 | DLD inspection: 28.44% | DLD via Dubai Handover |
| 20 Apr 2026 | DLD inspection: 53.25% | DLD via Mitchell’s, fäm Properties |
| 30 Jun 2026 | Registered completion date passes | DLD register |
| 29 Sep 2026 | Register unchanged: 53.25%, date still 30 Jun 2026 | Continental Club |
The date itself has not been moved. Binghatti still shows Q2 2026 and the register still shows 30 June 2026. What has changed is that the date has passed with close to half the building left to complete at the last inspection. Binghatti delivered about 1,700 units in H1 2026, including Binghatti Apex, Ghost and Ivory (Binghatti, 27 July 2026), and Elite was not among them.
What the Binghatti Elite handover date means for payments
Binghatti’s plan is 20% at booking, 50% during construction and 30% on completion. The 30% completion payment falls due at handover, so it moves with the actual handover date rather than the 30 June 2026 date on the register.
| Unit | Price from | 30% due on completion |
|---|---|---|
| Studio | AED 600,000 | AED 180,000 |
| 1 bedroom | AED 1,124,999 | AED 337,500 |
Prices are Binghatti’s, September 2026. Many units now change hands before completion. DLD recorded 630 sales in the building between April 2025 and 18 September 2026, most of them studios (Mitchell’s).
What to check before relying on the Binghatti Elite date
- The grace period in your SPA. With 30 June 2026 passed, the grace period, not the Q2 2026 date, sets when the developer is contractually late.
- Whether a new DLD inspection has been filed. The 53.25% figure dates from 20 April 2026, so a newer reading on the DLD project status service would show how far the tower has moved since.
- Written confirmation of a revised date from Binghatti, since its project page still shows Q2 2026.
- For resale buyers, how much of the 50% construction share is already paid and what remains for the 30% due on completion.
Questions buyers also ask
What is the Binghatti Elite handover date?
Binghatti lists Q2 2026, and the DLD registered completion date is 30 June 2026. Both have passed. Binghatti had not published a revised date by 1 October 2026 (Binghatti; DLD register via Continental Club, 29 Sep 2026).
Is Binghatti Elite finished?
No. The last DLD inspection, on 20 April 2026, recorded 53.25% complete, and the register still listed the project as under construction in September 2026.
Has the Binghatti Elite handover been delayed?
Yes, against its own dates. The 30 June 2026 registered completion date passed with the tower at 53.25% at its last inspection. The SPA usually allows a grace period after the anticipated completion date, so the contractual position depends on your agreement.
How much is due at handover at Binghatti Elite?
30% of the price is due on completion under Binghatti's 20/50/30 plan. On a studio at AED 600,000 that is AED 180,000 (Binghatti, September 2026).