When is the Binghatti Hills handover date?
Short answer
Binghatti gives Q2 2026 as the Binghatti Hills completion date, and that quarter has passed; the DLD register holds no registered completion date for the project. The latest DLD inspection, on 24 July 2026, put construction at 90% complete. Portal dates now range from September 2026 to April 2027, and Binghatti had not announced a handover or a revised date as of 1 October 2026.
Registered completion date (DLD)
Not filed
DLD project 3053, via Mitchells Commercial Realty, 27 Sep 2026
Latest construction progress
90%
DLD inspection, 24 Jul 2026
Developer's stated date
Q2 2026
Binghatti project page, accessed 1 Oct 2026. Now passed
Portal dates
Sep 2026 to Apr 2027
Property Finder listings, accessed 1 Oct 2026
Binghatti Hills handover date: the latest position
Binghatti’s project page gives Q2 2026 as the completion date for Binghatti Hills in Dubai Science Park. That quarter ended on 30 June 2026, and as of 1 October 2026 Binghatti had not published a revised date or announced a handover. The Dubai Land Department register holds no registered completion date for the project, which is DLD project 3053. Prices, sizes and the payment plan are on the Binghatti Hills page.
The latest DLD site inspection, on 24 July 2026, recorded the project at 90% complete, and the register still showed it as under construction on 27 September 2026. Portals disagree on when it will now finish: Data Habibi lists a current target of Q3 2026, while Property Finder lists 1 September 2026 for the Phase 3 building and April 2027 for its main Binghatti Hills listing.
Binghatti Hills handover date by building
The DLD register records Binghatti Hills as one project with 1,687 homes in 2 buildings. Binghatti markets 1,666 homes plus 21 shops, and Property Finder splits the project into phases. DLD publishes one progress figure for the whole project, not one per building.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Binghatti Hills, DLD project 3053 (2 buildings) | 90%, 24 Jul 2026 | Not filed | Q2 2026 (Binghatti); Q3 2026 (Data Habibi) |
| Binghatti Hills Phase 3 (1 building) | Not published separately | Not filed | 1 Sep 2026 (Property Finder) |
| Binghatti Hills, Property Finder main listing | Not published separately | Not filed | April 2027 (Property Finder) |
| Binghatti Hillviews, DLD project 3321 (separate tower) | 32.6%, 25 Jun 2026 | 1 Apr 2026 | Q4 2026 (Binghatti) |
Property Finder’s April 2027 listing gives a construction start of 15 March 2025, which does not match the registered start of 1 April 2024 on the DLD register. Binghatti Hillviews, often searched as “Binghatti Hills View”, is a different tower at an earlier stage, with its own dates.
How the Binghatti Hills handover date has changed
| Date | What happened | Source |
|---|---|---|
| Feb 2024 | Project first traced | Propsearch |
| 1 Apr 2024 | Registered construction start | DLD register, via Mitchells |
| 10 Jun 2024 | Phase 3 construction start, completion listed for 1 Sep 2026 | Property Finder |
| 2024 to 2026 | Completion given as Q2 2026 | Binghatti project page |
| 30 Jun 2026 | Q2 2026 ends with no handover announced | Binghatti |
| 24 Jul 2026 | DLD inspection records 90% complete | DLD, via HomeSearch |
| Sep 2026 | Current target listed as Q3 2026, a three month postponement | Data Habibi |
| 30 Sep 2026 | Q3 2026 ends with no handover announced | Binghatti |
The Q2 2026 date on Binghatti’s page has not been changed since it passed. The only later dates come from portals, and they do not agree with each other.
What the Binghatti Hills handover date means for payments
Binghatti’s plan is 20% on booking, 50% during construction and 30% on completion, so almost a third of the price is tied to the completion date. On a studio at the launch price of AED 800,000, that is AED 240,000 due on completion. If completion moves later, that payment moves with it. There is no post-handover plan on Binghatti’s published terms.
DLD registered 457 sales at Binghatti Hills between 28 April 2025 and 28 September 2026 (Mitchells Commercial Realty), so many resale buyers also take on the 30% completion payment from the original buyer.
What to check before relying on the Binghatti Hills date
- The tower name on the SPA. Binghatti Hills, Binghatti Hillside and Binghatti Hillviews are three different Dubai Science Park towers. Hillviews was 32.6% built in June 2026, against 90% for Hills.
- The building and phase. Property Finder gives September 2026 for Phase 3 and April 2027 for its main listing, so the phase changes the portal date.
- The completion date and grace period in the SPA. With no registered completion date on the DLD register, the SPA is the only written date for a unit.
- The amount still owed at completion. On a resale, the 30% completion payment is usually still outstanding and falls due when Binghatti issues the completion notice.
Questions buyers also ask
Is Binghatti Hills finished?
No. The DLD inspection on 24 July 2026 put Binghatti Hills at 90% complete, and the DLD register still listed it as under construction on 27 September 2026 (Mitchells Commercial Realty). Binghatti had not announced a handover as of 1 October 2026.
What is the Binghatti Hills completion date?
Binghatti's project page gives Q2 2026. That quarter ended on 30 June 2026. Data Habibi now lists a current target of Q3 2026, and Property Finder lists 1 September 2026 for the Phase 3 building and April 2027 for its main Binghatti Hills listing. Binghatti has not published a revised date.
Has the Binghatti Hills handover date been delayed?
Yes, against Binghatti's own date. Q2 2026 passed with the project at 90% built in late July 2026. Data Habibi records a three month postponement to Q3 2026, and that quarter also ended on 30 September 2026 without an announced handover.
What is the Binghatti Hillviews handover date?
Binghatti Hillviews is a separate tower in Dubai Science Park (DLD project 3321). Binghatti's page gives Q4 2026. The DLD register shows a registered completion date of 1 April 2026 and recorded 32.6% complete at its inspection on 25 June 2026 (Mitchells Commercial Realty). Binghatti Hillside is a third, separately named Binghatti tower in the same area.
How much is due at the Binghatti Hills handover?
Binghatti's plan is 20% on booking, 50% during construction and 30% on completion. On a studio at the launch price of AED 800,000, the completion payment is AED 240,000.